Construction Update 7/8 (current week, 7/14 and 7/21)

Thanks for keeping up to speed with us as the project develops. Keep in mind this information will change as the course of construction and weather affect our work.

This week

  • Final week of sanitary sewer installation in Phase 1

Week of 7/14

  • Nighttime water outage will be coordinated for valves affecting 7101, 7141, and 7151 York. These outages will be communicated by Edina Public Works directly with each affected property.
  • Placement of new road aggregate base in south phase.

Week of 7/21

  • Placement of curb and gutter, concrete driveways, walks, and final grade of aggregate base.

Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina