Construction Update 8/12 (Current week, 8/18 and 8/25)
Thanks for keeping up to speed with us as the project develops. Keep in mind this information will change as the course of construction and weather affect our work.
Key Update
- Phase 1 is wrapping up with restoration of roadways. This phase will be paved, striped and open to traffic before we move to Phase 2, north of Hazelton.
- Most probable time for Phase 2 switch over would be September 2, after the holiday weekend.
- The phase change could come with 1 day of closure for Both Hazelton Road and 70th Street (2 eastbound intersection lanes, right and through at York)
This week
- Paving of first two layers of bituminous pavement (roadway and driveways). There may be short durations (less than 15 minutes) while pavement is being placed in or in front of driveways where access is not possible. Please be patient.
- Placement of remaining concrete sidewalk
- A contractor for Xcel Energy may be on site to replace street lights this week. (Currently at-risk as Xcel is nonresponsive) If they miss this window, they may have to close a lane to work on the P1 area.
Week of 8/18
- Concrete cure time
- Installation of signs and pedestrian crossing equipment.
- Placement of topsoil
- The final layer of bituminous pavement may be paved this week (slight chance late week)
Week of 8/25
- The final layer of bituminous pavement will be paved this week
- Pavement markings
- Preparation for phase switch over.
Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina
Share Construction Update 8/12 (Current week, 8/18 and 8/25) on Facebook
Share Construction Update 8/12 (Current week, 8/18 and 8/25) on Twitter
Share Construction Update 8/12 (Current week, 8/18 and 8/25) on Linkedin
Email Construction Update 8/12 (Current week, 8/18 and 8/25) link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends