Construction Update 9/9 (Current week, 9/15, and 9/22)
Thanks for keeping up to speed with us as the project develops. Keep in mind this information will change as the course of construction and weather affect our work.
Key Update
- Traffic control change to Phase 2b, which closes eastbound 69th at the east most Galleria entrance is schedule for Wednesday September 17th.
This week
- Installation of new sanitary sewer pipe.
- Coordination with private utilities to locate, clear, deenergize or relocate lines on the alignment near 69th and York to prepare for late September sewer installation. This week there will be communications contractor working near 69th to do this work.
Week of 9/15
- Installation of new sanitary sewer pipe.
- A <1 day lane closure on northbound York right turn lane near 69th, likely the 16th or 17th of September.
- Traffic control change to Phase 2b, which closes eastbound 69th at the east most Galleria entrance
Week of 9/22
- Installation of new sanitary sewer pipe.
Please note any items of coordination and direct any questions to William Bauer, SEH, and Ross Bintner, City of Edina
Share Construction Update 9/9 (Current week, 9/15, and 9/22) on Facebook
Share Construction Update 9/9 (Current week, 9/15, and 9/22) on Twitter
Share Construction Update 9/9 (Current week, 9/15, and 9/22) on Linkedin
Email Construction Update 9/9 (Current week, 9/15, and 9/22) link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends