The introduction letter is in the mail and calls are already coming in. Here are the key Q&As of interest so far:

  • This work is only in the southbound lane
  • We're working from the south to the north
  • Phase 1a and 1b (Hazelton intersection and south) is split to maintain traffic access for York Plaza and York Condos east and west
  • We're reaching out specifically with three properties with key access constraints
  • Sanitary service is generally not interrupted, we've reached out to one property individually where a <1 day outage is planned
  • We're in design phase now with bidding and contractor selection to follow. We'll share an approximate start date in the Spring once a contractor is selected

Thanks to everyone who has reached out so far to help inform our work.