The contractor has confirmed that work will begin on Monday, June 2nd. On that day, southbound York Avenue will close to traffic, with a detour to France Avenue in place via 69th Street. Northbound traffic will remain open throughout construction.
To improve efficiency for the contractor, it has been agreed to construct the project in two phases, as shown below:
- From the York Plaza Apartments and just south of 70th Street
- From the 70th Street intersection to 69th Street
Within phase 1, the Hazelton Road intersection will remain open to traffic until construction has progressed far enough to force its closure (approximately late June). Phase 1 is tentatively scheduled to be completed around late August, at which time work within phase 2 will begin. Further updates on exact timing will be provided throughout the summer.
Access to York Plaza Apartments and Condos will be maintained via northbound York Avenue throughout construction. Access to Target will be possible from the west on both Hazelton Road and 70th Street after the Hazelton Road intersection closes. The Target driveway on York Avenue will be closed beginning on June 2nd for the remainder of construction.
Work is anticipated to be completed around mid-October.