York Avenue Trunk Sanitary

Share York Avenue Trunk Sanitary on Facebook Share York Avenue Trunk Sanitary on Twitter Share York Avenue Trunk Sanitary on Linkedin Email York Avenue Trunk Sanitary link

The project includes design and construction of a new trunk sanitary sewer pipe and manholes in the southbound lanes of York Avenue (CSAH 31) between the Promenade and 69th Street West intersection. The improvements are listed in the 2023-2028 Capital Improvement Plan (CIP) under CIP #19-335 and are funded by the sanitary sewer utility.

Planned construction is for Summer/Fall 2025

The scope of construction includes;

  • 2 phases of construction over 4 months to construct new and upgraded Sanitary sewer pipe
  • Phased closures of southbound York between the Promenade and 69th Street West
  • New sections of road, curb, crosswalks and catch basins

The project includes design and construction of a new trunk sanitary sewer pipe and manholes in the southbound lanes of York Avenue (CSAH 31) between the Promenade and 69th Street West intersection. The improvements are listed in the 2023-2028 Capital Improvement Plan (CIP) under CIP #19-335 and are funded by the sanitary sewer utility.

Planned construction is for Summer/Fall 2025

The scope of construction includes;

  • 2 phases of construction over 4 months to construct new and upgraded Sanitary sewer pipe
  • Phased closures of southbound York between the Promenade and 69th Street West
  • New sections of road, curb, crosswalks and catch basins

Ask a Question

Submit questions about the project here and city staff will get back to you!

If this is an emergency, please dial 911. If you have an after-hours, urgent, project related matter, please contact our after hours non-emergency line at 952-826-1600.

loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Share Having a home office along York (York Plaza) how much quiet enjoyment will be taken by this project? on Facebook Share Having a home office along York (York Plaza) how much quiet enjoyment will be taken by this project? on Twitter Share Having a home office along York (York Plaza) how much quiet enjoyment will be taken by this project? on Linkedin Email Having a home office along York (York Plaza) how much quiet enjoyment will be taken by this project? link

    Having a home office along York (York Plaza) how much quiet enjoyment will be taken by this project?

    Norwoods Realty asked 11 days ago

    Hi Norwoods Realty, Thanks for reaching out,

    It looks like your home has a front row seat to construction this summer and your balcony may be as close as 70’ to the construction. As far as how much quiet enjoyment you may lose this summer, a few factors come to mind;

    • Work hours: Our work will be 7am to 7pm, and may end earlier depending on the day.  
    • Phase of construction: Construction near you will being on June 9, and digging starts by mid-week.  We’ll be north and out of view within the first month or less of work, but will be back to patch up curbs, pave and clean up.  When we’re out front, expect a bit of dust, and construction sounds like engine idle and working, back up beeping, clank and clatter from moving around big pipes and structure, setting and taking up forms, and cleaning up with a sweeper.
    • Age and interests: You may be able to sell box seats to the construction!  We’re particularly popular with the 4-15 age set, and construction fans of all ages.  Just make sure to stay safely back from the construction zone. We’re putting in a big deep pipe that could serve for centuries helping toilets flush and that’s a moment filled with wonder. =)

     Keep checking back, on the updated schedule and reach out if you see anything amiss.