Braemar Park Master Plan Implementation

Share Braemar Park Master Plan Implementation on Facebook Share Braemar Park Master Plan Implementation on Twitter Share Braemar Park Master Plan Implementation on Linkedin Email Braemar Park Master Plan Implementation link

The Braemar Park master plan was created in 2017 with the help of residents and community members. City Council approved the master plan on Jan. 3, 2018. On Nov. 8, 2022, voters approved via referendum a local option sales tax to allocate $8.1 million of project funding for implementation and next phases of the Braemar Park master plan. Project planning efforts are moving forward for completing final design and constructing improvements in the park. Additional stakeholder and public engagement will occur during preliminary and final design to integrate comment and feedback into the design process.

Current proposed trail and park improvements include:

  • Walking trails
  • Mountain bike trails
  • Cross-country skiing trails
  • Pickleball
  • Courtney Fields baseball complex improvements
  • Wayfinding signs and trail connections
  • Natural resource restoration
  • Improved parking and access to Braemar Golf Course, Braemar Arena, and Courtney Fields

The Braemar Park master plan was created in 2017 with the help of residents and community members. City Council approved the master plan on Jan. 3, 2018. On Nov. 8, 2022, voters approved via referendum a local option sales tax to allocate $8.1 million of project funding for implementation and next phases of the Braemar Park master plan. Project planning efforts are moving forward for completing final design and constructing improvements in the park. Additional stakeholder and public engagement will occur during preliminary and final design to integrate comment and feedback into the design process.

Current proposed trail and park improvements include:

  • Walking trails
  • Mountain bike trails
  • Cross-country skiing trails
  • Pickleball
  • Courtney Fields baseball complex improvements
  • Wayfinding signs and trail connections
  • Natural resource restoration
  • Improved parking and access to Braemar Golf Course, Braemar Arena, and Courtney Fields
  • Arbor Day Thank You

    Share Arbor Day Thank You on Facebook Share Arbor Day Thank You on Twitter Share Arbor Day Thank You on Linkedin Email Arbor Day Thank You link
    supporting image

    Thank you to all the volunteers that helped on Arbor Day. We were able to plant over 200 trees to add to restoration and future canopy and habitat at Braemar Park. A great group of volunteers helped us to enhance our Eastern Trail border off Gleason and contributed greatly to our future canopy and trail habitat.


    Thanks to all our volunteers

  • Arbor Day Event

    Share Arbor Day Event on Facebook Share Arbor Day Event on Twitter Share Arbor Day Event on Linkedin Email Arbor Day Event link
    supporting image

    The annual Arbor Day celebration and tree planting comes to Braemar Golf Course this year to enhance the natural areas around the courses.

    • Volunteers of all ages are welcome to join the celebration 10 a.m. to 2 p.m. Friday, April 25. Those who volunteer are asked to meet in the courtyard area next to the Braemar Golf Course Clubhouse, 6364 John Harris Drive.
    • Park Maintenance staff will demonstrate how to properly plant a tree, then divide the volunteers into groups that will fan out across the area to plant more trees.
    • Prior to the event, Park Maintenance will use an auger to break up the soil at the planting spots, so no heavy digging will be required. Shovels and other equipment will be provided.
    • Volunteers should bring gloves and wear closed-toed shoes and clothes they don’t mind getting dirty. Bring a reusable water bottle to stay hydrated.

    Volunteers are asked to register in advance at EdinaMN.gov/ArborDay to help plan the needed supplies and groups. Walk-up volunteers can register at the event.

    Food and beverages will be available for purchase. A limited number of free tree saplings will be handed out so volunteers can plant a tree in their own yards.

  • Spring fever

    Share Spring fever on Facebook Share Spring fever on Twitter Share Spring fever on Linkedin Email Spring fever link
    supporting image

    Warmer weathers have us dreaming of summer and trails opening. The City has signed a multi year restoration contract with RES to maintain and enhance the natural areas in the hill around Braemar Park. This team is already hard at work removing additional areas of buckthorn and preparing for a season of invasive species management and restoration seeding to enhance and restore the woodland and oak savannas around the park.

    At Courtney Fields contractor are still at work finishing safety netting and site work to prepare for the 2025 baseball season. The playground will also be completed this spring and available for use to visitors and neighborhood public. We will keep you updated and let you know when it is ready for play.

  • Trail updates

    Share Trail updates on Facebook Share Trail updates on Twitter Share Trail updates on Linkedin Email Trail updates link
    supporting image

    Edina has partnered with MORC, Minnesota Off-Road Cyclists at Braemar Park Trails. MORC will help to support Edina with trail maintenance and improvements. Trail information can now be found at their website here. Trail closures can also be viewed on Trailbot or at MORC's website here for all MORC managed trails. Trail needs can be reported through Trailbot or Edina 311.

  • Grand Opening Tomorrow!

    Share Grand Opening Tomorrow! on Facebook Share Grand Opening Tomorrow! on Twitter Share Grand Opening Tomorrow! on Linkedin Email Grand Opening Tomorrow! link
    supporting image

    Join us Wednesday September 4th at 5:00 pm at the Braemar Golf Dome and trail head for our Braemar Trails Grand Opening and Ribbon cutting. We will be thanking all those who supported the project from idea through completion. MORC, BORCA, Wolf Tooth Components, and Yardi will be on site. Take a hike or bike with us and celebrate the trails.

  • Trails Partially OPENED

    Share Trails Partially OPENED on Facebook Share Trails Partially OPENED on Twitter Share Trails Partially OPENED on Linkedin Email Trails Partially OPENED link

    West side trails are open! Thanks to Edina MTB team for your help clearing debris. Please be cautious riding for shifted debris and rutting on trails. Staff and contractors are working on East side.

  • NOTICE: NO THROTTLED E-BIKES ON TRAILS

    Share NOTICE: NO THROTTLED E-BIKES ON TRAILS on Facebook Share NOTICE: NO THROTTLED E-BIKES ON TRAILS on Twitter Share NOTICE: NO THROTTLED E-BIKES ON TRAILS on Linkedin Email NOTICE: NO THROTTLED E-BIKES ON TRAILS link
    supporting image

    Braemar Trails have been prohibited to motorized vehicles but the City has expanded that to also include Class 2 and Class 3 E- bikes.

    The City of Edina has drafted an agreement for City approval on September 3rd with Minnesota Off -Road Cycling (MORC). To partner on trail maintenance and long term trail vision. To help support trail maintenance the City has decided to prohibit Class 2 and Class 3 E-bikes on Braemar trails. City staff has recorded damage and received reports of damage on trail system from these bikes. The aggressive tires and throttle speeds have contributed to erosion and feature integrity. The City will continue to allow Class 1 pedal assist E-bikes. The City made this decision to both support MORC's position and partnership as well as to promote long term sustainability of soft surface trail system.

    Rules and Regulations will be posted at trail heads.

  • Hiking Trails Map

    Share Hiking Trails Map on Facebook Share Hiking Trails Map on Twitter Share Hiking Trails Map on Linkedin Email Hiking Trails Map link
    supporting image

    The hiking and pedestrian trails are available for use at Braemar trails. These trails can be accessed from multiple points and link together with a shared use path on Braemar Blvd/Hilary Lane. Biking trails are still being worked on and are anticipated to open this week, weather dependent. Please stay on hiking trails at this time so contractors can continue to work on biking trails and restoration work on the site. A pedestrian trail map can be downloaded here.

  • Dirt Capping and finishing touches for Trails

    Share Dirt Capping and finishing touches for Trails on Facebook Share Dirt Capping and finishing touches for Trails on Twitter Share Dirt Capping and finishing touches for Trails on Linkedin Email Dirt Capping and finishing touches for Trails link
    supporting image

    Pathfinder is putting the icing on the cake for the Braemar Trails. They are applying clay capping to the jump-line and SW trail segment to improve trail surfacing and wear. Walking paths are open for hikers and all trees are clear. Biking trails are not yet ready and still have contractors doing tree work and natural resources work.

  • Trails Nearing Completion

    Share Trails Nearing Completion on Facebook Share Trails Nearing Completion on Twitter Share Trails Nearing Completion on Linkedin Email Trails Nearing Completion link
    supporting image

    We ask your patience a little while longer for our Braemar Trails. Currently contractors and staff are working on finishing touches for the trails. Trails will remain closed until these items are completed. We will post a map and trail guidelines once we have completed these. We will also let everyone know an official grand opening date and time. We are very excited for the trails to be opened and users to start enjoying the space.

Page last updated: 28 Apr 2025, 07:27 AM