Share Final Update on Facebook
Share Final Update on Linkedin
Email Final Update link
Lift station 6 construction and restoration is complete. The station is under normal operations by Public Works staff.
Share Update on Facebook
Share Update on Linkedin
Email Update link
We're working the last steps for the lift station 6 project, there are intermittent workers on site, and usual visits by City workers to operate the station.
Share Update on Facebook
Share Update on Linkedin
Email Update link
The site is starting to look more like the project image. In the last month demolition completed on the old lift station, and seeding and tree planting was done. We're still working a few punch-list items inside the station. In the next month we will see paving, concrete and more finishing touches to the site, street, boulevard and nearby sidewalk.
Share Update on Facebook
Share Update on Linkedin
Email Update link
The old station demolition is nearly complete. When the site dries out from the recent rainfall, there will be several utility installations and final grading will begin. Restoration including paving sidewalks, driveway, landscaping and seeding will take most of July.
Share Update on Facebook
Share Update on Linkedin
Email Update link
Outside the station we're waiting for Xcel Energy to disconnect the former station from power, and then the demolition will begin.
Inside the station the contractor is putting on finishing touches. The station is up and running and we're working to seal and finish the spaces and test the equipment. Pictured is the overhead crane that is used to pull the submersible pumps for maintenance and repair.
Share Update on Facebook
Share Update on Linkedin
Email Update link
Startup week is going well, and the end of construction is near. Here are the remaining steps and approximate times:
- April - Startup of new station, connection of new pipes, demolition of old station starts
- May - Demolition of old station finishes, final grading starts
- June - Final grading finishes, driveway, sidewalk preparation, paving starts,
- July - Paving and sidewalk finishes, final seed and landscaping
We're coordinating with a separate contractor for the related pedestrian connections and intersection improvements. We'll update with more details for those improvements when they are better known.
Share Update on Facebook
Share Update on Linkedin
Email Update link
During the week of April 1, the new station will be programmed, tested and commissioned. The new station will run with the old station off, but available as backup as the operators train on the new station during the week and over the next weekend.
Following the testing and commissioning period, the old station will be demolished and final site utilities will be installed.
The old station served for 70 years!
Share Update on Facebook
Share Update on Linkedin
Email Update link
Lot of action but nothing much to see these days, here's a summary of the work inside the station:
- Insulation, roofing materials
- Framing, drywall
- painting, coatings
- electrical, communications
- plumbing, pumps
Share Update on Facebook
Share Update on Linkedin
Email Update link
This week roofing, insultation and waterproof membrane are going on. Once the structure is water tight internal work such as dry wall and electrical can begin.
Share Update on Facebook
Share Update on Linkedin
Email Update link
The station is going vertical this week and next with precast concrete panels, welding, pump lifting beam, roof truss installation, fence and electrical pad installation.