Prospect Knolls A/C/D Neighborhood Roadway Reconstruction
Share Prospect Knolls A/C/D Neighborhood Roadway Reconstruction on Facebook
Share Prospect Knolls A/C/D Neighborhood Roadway Reconstruction on Twitter
Share Prospect Knolls A/C/D Neighborhood Roadway Reconstruction on Linkedin
Email Prospect Knolls A/C/D Neighborhood Roadway Reconstruction link
Prospect Knolls A/C/D Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!
The proposed 2026 reconstruction project includes:
- Complete reconstruction of the roadway asphalt pavement,
- Installation or replacement of concrete curb and gutter,
- Replacement of a portion of the watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems, and
- The project is funded by a combination of special assessments, property taxes, and respective utility funds.
- Based on the assessment policy, 52.6% of the roadway project costs will be assessed to Prospect Knolls A/C/D property owners, and 47.4% of the roadway project costs will be paid for by property taxes. Estimated preliminary assessment amounts, by district, are:
- District 1 - $19,000 per Residential Equivalent Unit (REU)
- District 2 - $9,700 per REU
- District 3 - $1,700 per multi-family residential unit (condominium)