Prospect Knolls A/C/D Neighborhood Roadway Reconstruction

Share Prospect Knolls A/C/D Neighborhood Roadway Reconstruction on Facebook Share Prospect Knolls A/C/D Neighborhood Roadway Reconstruction on X (formerly Twitter) Share Prospect Knolls A/C/D Neighborhood Roadway Reconstruction on Linkedin Email Prospect Knolls A/C/D Neighborhood Roadway Reconstruction link
Map showing the Prospect Knolls neighborhood and the project limits.

Prospect Knolls A/C/D Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

The proposed 2026 reconstruction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Installation or replacement of concrete curb and gutter,
  • Replacement of a portion of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • The project is funded by a combination of special assessments, property taxes, and respective utility funds.
  • Based on the assessment policy, 52.6% of the roadway project costs will be assessed to Prospect Knolls A/C/D property owners, and 47.4% of the roadway project costs will be paid for by property taxes. Estimated preliminary assessment amounts, by district, are:
    • District 1 - $19,000 per Residential Equivalent Unit (REU)
    • District 2 - $9,700 per REU
    • District 3 - $1,700 per multi-family residential unit (condominium)

Prospect Knolls A/C/D Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

The proposed 2026 reconstruction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Installation or replacement of concrete curb and gutter,
  • Replacement of a portion of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • The project is funded by a combination of special assessments, property taxes, and respective utility funds.
  • Based on the assessment policy, 52.6% of the roadway project costs will be assessed to Prospect Knolls A/C/D property owners, and 47.4% of the roadway project costs will be paid for by property taxes. Estimated preliminary assessment amounts, by district, are:
    • District 1 - $19,000 per Residential Equivalent Unit (REU)
    • District 2 - $9,700 per REU
    • District 3 - $1,700 per multi-family residential unit (condominium)
  • Construction Update- 9/18/26

    Share Construction Update- 9/18/26 on Facebook Share Construction Update- 9/18/26 on X (formerly Twitter) Share Construction Update- 9/18/26 on Linkedin Email Construction Update- 9/18/26 link

    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
      • Tree replacements will happen later in the fall.
      • The final layer of asphalt will be installed later in the fall.


    Phase 1:

    • Ongoing Work (week of 9/21)
      • Lanham Lane, Kemrich Drive (East of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
        • Backfilling behind curb in preparation for topsoil installation
        • Landscape restoration
        • Sod installation


    Phase 2:

    • Upcoming Work (week of 9/21)
      • Dublin Circle, Dublin Road, Antrim Road, and 70th St
        • Restoring access to driveways
        • Paving the base layer of asphalt
    • Ongoing Work
      • Tralee Drive
        • Backfilling behind curb in preparation for topsoil installation
        • Irrigation and landscape restoration

    Phase 3:

    • Upcoming Work (week of 9/21)
      • Down Road, Lee Valley Road, Kemrich Drive (West of Lanham Lane)
        • Water service replacement
        • Fire hydrant and gate valve replacement
        • Removal of existing curb and gutter on Kemrich Drive
    • Completed Work
      • Mailbox removals. The temporary mail bank is located at W 69th adjacent to Calvary Lutheran Church.

    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
      • Tree replacements will happen later in the fall.
      • The final layer of asphalt will be installed later in the fall.


    Phase 1:

    • Ongoing Work (week of 9/21)
      • Lanham Lane, Kemrich Drive (East of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
        • Backfilling behind curb in preparation for topsoil installation
        • Landscape restoration
        • Sod installation


    Phase 2:

    • Upcoming Work (week of 9/21)
      • Dublin Circle, Dublin Road, Antrim Road, and 70th St
        • Restoring access to driveways
        • Paving the base layer of asphalt
    • Ongoing Work
      • Tralee Drive
        • Backfilling behind curb in preparation for topsoil installation
        • Irrigation and landscape restoration

    Phase 3:

    • Upcoming Work (week of 9/21)
      • Down Road, Lee Valley Road, Kemrich Drive (West of Lanham Lane)
        • Water service replacement
        • Fire hydrant and gate valve replacement
        • Removal of existing curb and gutter on Kemrich Drive
    • Completed Work
      • Mailbox removals. The temporary mail bank is located at W 69th adjacent to Calvary Lutheran Church.
  • Construction Update - 9/11/2026

    Share Construction Update - 9/11/2026 on Facebook Share Construction Update - 9/11/2026 on X (formerly Twitter) Share Construction Update - 9/11/2026 on Linkedin Email Construction Update - 9/11/2026 link

    Project Area

    • Crews will onsite Saturday, 9/12.
    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map.
      • A revision was made to include the entirety of Shannon Drive in Phase 3.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1:

    • Upcoming Work (week of 9/14, unless otherwise noted)
      • Village Drive sod installation
      • Weston Circle and Lee Valley Circle tree replacements will happen later in the fall
    • Ongoing Work
      • Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
        • Backfilling behind curb in preparation for topsoil installation
        • Landscape restoration
        • Sod installation


    Phase 2:

    • Upcoming Work (week of 9/14)
      • Fleetwood Drive and Tralee Drive
        • Backfilling behind curb in preparation for topsoil installation
        • Irrigation and landscape restoration
      • Dublin Circle, Dublin Road, Antrim Road, and 70th St
        • Curb and gutter installation
        • Concrete driveway installation
    • Ongoing Work
      • Fleetwood Drive and Tralee Drive
        • Backfilling behind curb in preparation for topsoil installation
        • Irrigation and landscape restoration
    • Completed Work
      • Dublin Circle
        • Sump line installation continues

    Project Area

    • Crews will onsite Saturday, 9/12.
    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map.
      • A revision was made to include the entirety of Shannon Drive in Phase 3.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1:

    • Upcoming Work (week of 9/14, unless otherwise noted)
      • Village Drive sod installation
      • Weston Circle and Lee Valley Circle tree replacements will happen later in the fall
    • Ongoing Work
      • Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
        • Backfilling behind curb in preparation for topsoil installation
        • Landscape restoration
        • Sod installation


    Phase 2:

    • Upcoming Work (week of 9/14)
      • Fleetwood Drive and Tralee Drive
        • Backfilling behind curb in preparation for topsoil installation
        • Irrigation and landscape restoration
      • Dublin Circle, Dublin Road, Antrim Road, and 70th St
        • Curb and gutter installation
        • Concrete driveway installation
    • Ongoing Work
      • Fleetwood Drive and Tralee Drive
        • Backfilling behind curb in preparation for topsoil installation
        • Irrigation and landscape restoration
    • Completed Work
      • Dublin Circle
        • Sump line installation continues
  • Construction Update - 9/4/2026

    Share Construction Update - 9/4/2026 on Facebook Share Construction Update - 9/4/2026 on X (formerly Twitter) Share Construction Update - 9/4/2026 on Linkedin Email Construction Update - 9/4/2026 link

    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map.
    • A revision was made to include the entirety of Shannon Drive in Phase 3.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1:

    • Upcoming Work (week of 9/7)
      • Village Drive sod installation.
      • Weston Circle and Lee Valley Circle tree replacements will happen later in the fall.
    • Ongoing Work
      • Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
        • Backfilling behind curb in preparation for topsoil installation.
        • Irrigation and landscape restoration
        • Paver driveway reinstallation


    Phase 2:

    • Upcoming Work (week of 9/7)
      • Fleetwood Drive and Tralee Drive
        • Backfilling behind curb in preparation for topsoil installation.
        • Irrigation and landscape restoration.
        • Mailbox reinstallation
    • Kerry Road, Dublin Road, Antrim Road and Wexford Road
      • Removal of poor soils in preparation for curb and gutter installation
      • Curb and Gutter installation
    • Ongoing Work
      • Dublin Circle
        • Sump line installation continues.

    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map.
    • A revision was made to include the entirety of Shannon Drive in Phase 3.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1:

    • Upcoming Work (week of 9/7)
      • Village Drive sod installation.
      • Weston Circle and Lee Valley Circle tree replacements will happen later in the fall.
    • Ongoing Work
      • Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
        • Backfilling behind curb in preparation for topsoil installation.
        • Irrigation and landscape restoration
        • Paver driveway reinstallation


    Phase 2:

    • Upcoming Work (week of 9/7)
      • Fleetwood Drive and Tralee Drive
        • Backfilling behind curb in preparation for topsoil installation.
        • Irrigation and landscape restoration.
        • Mailbox reinstallation
    • Kerry Road, Dublin Road, Antrim Road and Wexford Road
      • Removal of poor soils in preparation for curb and gutter installation
      • Curb and Gutter installation
    • Ongoing Work
      • Dublin Circle
        • Sump line installation continues.
  • Construction Update - 8/28/2026

    Share Construction Update - 8/28/2026 on Facebook Share Construction Update - 8/28/2026 on X (formerly Twitter) Share Construction Update - 8/28/2026 on Linkedin Email Construction Update - 8/28/2026 link

    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map.
      • A revision was made to include the entirety of Shannon Drive in Phase 3.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • Crews will be onsite continuing restoration Saturday, 8/29.
    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1:

    • Upcoming Work (week of 8/31 unless otherwise noted)
      • Village Drive sod installation is tentatively scheduled for the week of 9/7.
      • Weston Circle and Lee Valley Circle tree replacements will happen at a later date.
      • Lanham Lane mailbox reinstallation
      • Ongoing Work
        • Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
          • Backfilling behind curb in preparation for topsoil installation.
          • Irrigation and landscape restoration
          • Asphalt driveway paving
          • Paver driveway reinstallation


    Phase 2:

    • Upcoming Work (week of 8/31)
      • Fleetwood Drive and Tralee Drive
        • Backfilling behind curb in preparation for topsoil installation
        • Irrigation and landscape restoration
        • Asphalt driveway replacements
        • Mailbox reinstallation
      • Dublin Circle
        • Sump drain installation
        • Curb and gutter removal
      • Kerry Road, Dublin Road and Wexford Road
        • Water service installation
    • Completed Work
      • Dublin Circle storm sewer installation.
      • Dublin Circle and Antrim Road water service installation
      • 70th Street sanitary sewer main installation
      • Antrim Road storm sewer installation

    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map.
      • A revision was made to include the entirety of Shannon Drive in Phase 3.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • Crews will be onsite continuing restoration Saturday, 8/29.
    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1:

    • Upcoming Work (week of 8/31 unless otherwise noted)
      • Village Drive sod installation is tentatively scheduled for the week of 9/7.
      • Weston Circle and Lee Valley Circle tree replacements will happen at a later date.
      • Lanham Lane mailbox reinstallation
      • Ongoing Work
        • Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
          • Backfilling behind curb in preparation for topsoil installation.
          • Irrigation and landscape restoration
          • Asphalt driveway paving
          • Paver driveway reinstallation


    Phase 2:

    • Upcoming Work (week of 8/31)
      • Fleetwood Drive and Tralee Drive
        • Backfilling behind curb in preparation for topsoil installation
        • Irrigation and landscape restoration
        • Asphalt driveway replacements
        • Mailbox reinstallation
      • Dublin Circle
        • Sump drain installation
        • Curb and gutter removal
      • Kerry Road, Dublin Road and Wexford Road
        • Water service installation
    • Completed Work
      • Dublin Circle storm sewer installation.
      • Dublin Circle and Antrim Road water service installation
      • 70th Street sanitary sewer main installation
      • Antrim Road storm sewer installation
  • Construction Update - 8/21/2026

    Share Construction Update - 8/21/2026 on Facebook Share Construction Update - 8/21/2026 on X (formerly Twitter) Share Construction Update - 8/21/2026 on Linkedin Email Construction Update - 8/21/2026 link

    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations
    • All work dates below are weather permitting


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours
      • Check your front door daily for notification of temporary water loss
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1:

    • Upcoming Work (Week of 8/24)
      • Lee Valley Circle, Weston Circle and Village Drive sod installation is tentatively scheduled for the week of 8/24.
      • Lanham Lane
        • Asphalt driveway paving
        • Paver driveway reinstallation
        • Mailbox installation
      • Dublin Circle storm sewer installation
    • Ongoing Work
      • Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
        • Backfilling behind curb in preparation for topsoil installation.
        • Irrigation and landscape restoration


    Phase 2:

    • Upcoming Work(Week of 8/24)
      • Fleetwood Drive and Tralee Drive
        • Backfilling behind curb in preparation for topsoil installation
        • Irrigation and landscape restoration
        • Asphalt driveway replacements
        • Mailbox installation
      • Antrim Road storm sewer installation
    • Ongoing Work
      • Kerry Road, Dublin Road and Wexford Road water service installation
      • 70th Street sanitary sewer main installation
    • Completed Work
      • Dublin Circle and Antrim Road water service installation

    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations
    • All work dates below are weather permitting


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours
      • Check your front door daily for notification of temporary water loss
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1:

    • Upcoming Work (Week of 8/24)
      • Lee Valley Circle, Weston Circle and Village Drive sod installation is tentatively scheduled for the week of 8/24.
      • Lanham Lane
        • Asphalt driveway paving
        • Paver driveway reinstallation
        • Mailbox installation
      • Dublin Circle storm sewer installation
    • Ongoing Work
      • Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
        • Backfilling behind curb in preparation for topsoil installation.
        • Irrigation and landscape restoration


    Phase 2:

    • Upcoming Work(Week of 8/24)
      • Fleetwood Drive and Tralee Drive
        • Backfilling behind curb in preparation for topsoil installation
        • Irrigation and landscape restoration
        • Asphalt driveway replacements
        • Mailbox installation
      • Antrim Road storm sewer installation
    • Ongoing Work
      • Kerry Road, Dublin Road and Wexford Road water service installation
      • 70th Street sanitary sewer main installation
    • Completed Work
      • Dublin Circle and Antrim Road water service installation
  • Construction Update - 8/14/2026

    Share Construction Update - 8/14/2026 on Facebook Share Construction Update - 8/14/2026 on X (formerly Twitter) Share Construction Update - 8/14/2026 on Linkedin Email Construction Update - 8/14/2026 link

    Project Area

    • Kerry Road between Dublin Road and Wexford Road will have limited access due to watermain installation during the week of 8/17. Expect delays and use alternate routes if you can.
    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1:

    • Upcoming Work
      • Lanham Lane and Kemrich Drive (east of Lanham Lane):
        • driveway access will be restored by the end of the day on Monday, 8/17.
        • The first layer of asphalt paving is scheduled for the week of 8/17, weather permitting.
      • Lee Valley Circle, Weston Circle and Village Drive sod installation is tentatively scheduled for the week of 8/17.
    • Ongoing Work
      • Tara Road, Antrim Court, and Antrim Terrace backfilling behind curb in preparation for topsoil installation.

    Phase 2:

    • Upcoming Work
      • Fleetwood Drive and Tralee Drive
        • driveway access will be restored by the end of the day on Monday, 8/17.
        • The first layer of asphalt paving is scheduled for the week of 8/17, weather permitting.
      • Dublin Circle and Antrim Road water service installation is scheduled for the week of 8/17.
      • 70th Street sanitary sewer main installation is scheduled for the week of 8/17.
    • Ongoing Work
      • Kerry Road, Dublin Road, Wexford Road water main installation continues the week of 8/17.
    • Completed Work
      • Tralee Drive and Kerry Road sanitary sewer main lining is complete.

    Project Area

    • Kerry Road between Dublin Road and Wexford Road will have limited access due to watermain installation during the week of 8/17. Expect delays and use alternate routes if you can.
    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1:

    • Upcoming Work
      • Lanham Lane and Kemrich Drive (east of Lanham Lane):
        • driveway access will be restored by the end of the day on Monday, 8/17.
        • The first layer of asphalt paving is scheduled for the week of 8/17, weather permitting.
      • Lee Valley Circle, Weston Circle and Village Drive sod installation is tentatively scheduled for the week of 8/17.
    • Ongoing Work
      • Tara Road, Antrim Court, and Antrim Terrace backfilling behind curb in preparation for topsoil installation.

    Phase 2:

    • Upcoming Work
      • Fleetwood Drive and Tralee Drive
        • driveway access will be restored by the end of the day on Monday, 8/17.
        • The first layer of asphalt paving is scheduled for the week of 8/17, weather permitting.
      • Dublin Circle and Antrim Road water service installation is scheduled for the week of 8/17.
      • 70th Street sanitary sewer main installation is scheduled for the week of 8/17.
    • Ongoing Work
      • Kerry Road, Dublin Road, Wexford Road water main installation continues the week of 8/17.
    • Completed Work
      • Tralee Drive and Kerry Road sanitary sewer main lining is complete.
  • Construction Update - 8/7/2026

    Share Construction Update - 8/7/2026 on Facebook Share Construction Update - 8/7/2026 on X (formerly Twitter) Share Construction Update - 8/7/2026 on Linkedin Email Construction Update - 8/7/2026 link

    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1

    • Upcoming Work
      • Lanham Lane and Kemrich Drive (east of Lanham Lane) concrete driveway installation is scheduled for Monday, 8/10.
    • Ongoing Work
      • Lee Valley Circle, Weston Circle and Village Drive sod installation is tentatively scheduled for the week of 8/17.
      • Tara Road, Antrim Court, and Antrim Terrace irrigation repairs are scheduled to continue the week of 8/10.
      • Antrim Court/Terrace paver driveway replacements will continue the week of 8/10.


    Phase 2:

    • Upcoming Work
      • Fleetwood Drive and Tralee Drive curb and gutter installation is scheduled for the week of 8/10.
      • Dublin Circle water service installation is scheduled for the week of 8/10.
      • Crews will be onsite Saturday, 8/8 reclaiming the existing road surface on Kerry Road and W 70th Street.
    • Ongoing Work
      • Kerry Road, Dublin Road, Wexford Road water main installation resumes.

    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1

    • Upcoming Work
      • Lanham Lane and Kemrich Drive (east of Lanham Lane) concrete driveway installation is scheduled for Monday, 8/10.
    • Ongoing Work
      • Lee Valley Circle, Weston Circle and Village Drive sod installation is tentatively scheduled for the week of 8/17.
      • Tara Road, Antrim Court, and Antrim Terrace irrigation repairs are scheduled to continue the week of 8/10.
      • Antrim Court/Terrace paver driveway replacements will continue the week of 8/10.


    Phase 2:

    • Upcoming Work
      • Fleetwood Drive and Tralee Drive curb and gutter installation is scheduled for the week of 8/10.
      • Dublin Circle water service installation is scheduled for the week of 8/10.
      • Crews will be onsite Saturday, 8/8 reclaiming the existing road surface on Kerry Road and W 70th Street.
    • Ongoing Work
      • Kerry Road, Dublin Road, Wexford Road water main installation resumes.
  • Construction Update - 7/31/2026

    Share Construction Update - 7/31/2026 on Facebook Share Construction Update - 7/31/2026 on X (formerly Twitter) Share Construction Update - 7/31/2026 on Linkedin Email Construction Update - 7/31/2026 link

    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1

    • Upcoming Work
      • Lanham Lane and Kemrich Drive east of Lanham Lane curb and gutter installation is tentatively scheduled to begin on Wednesday, 8/5.
    • Ongoing Work
      • Lee Valley Circle and Weston Circle sod installation will begin when weather permits.
      • Tara Road, Antrim Court, and Antrim Terrace irrigation repairs are scheduled to continue the week of 8/3


    Phase 2:

    • Upcoming Work
      • Fleetwood Drive and Tralee Drive curb and gutter installation is tentatively scheduled for the week of 8/10.
    • Ongoing Work
      • Fleetwood Drive sump drain installation will continue during the week of 8/3.

    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Please see the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1

    • Upcoming Work
      • Lanham Lane and Kemrich Drive east of Lanham Lane curb and gutter installation is tentatively scheduled to begin on Wednesday, 8/5.
    • Ongoing Work
      • Lee Valley Circle and Weston Circle sod installation will begin when weather permits.
      • Tara Road, Antrim Court, and Antrim Terrace irrigation repairs are scheduled to continue the week of 8/3


    Phase 2:

    • Upcoming Work
      • Fleetwood Drive and Tralee Drive curb and gutter installation is tentatively scheduled for the week of 8/10.
    • Ongoing Work
      • Fleetwood Drive sump drain installation will continue during the week of 8/3.
  • Construction Update - 7/24/2026

    Share Construction Update - 7/24/2026 on Facebook Share Construction Update - 7/24/2026 on X (formerly Twitter) Share Construction Update - 7/24/2026 on Linkedin Email Construction Update - 7/24/2026 link

    Gleason Road Closure Notice

    Gleason Road between Schey Drive and Tupa Drive will be closed for utility improvements until approximately Monday, 7/27. The detour route will be Hilary Lane and Valley View Road.


    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Work will occur on Saturday, July 25.
    • Please see the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1

    • Upcoming Work
      • Tara Road, Antrim Court, and Antrim Terrace mailbox installation is scheduled for the week of 7/27. The contractor will notify you when mail delivery will be restored. Until that time, please continue to collect your mail at the temporary mail bank location.
    • Ongoing Work
      • Lanham Lane and Kemrich Drive roadway and soil corrections is scheduled to continue into the week of 7/27. Crews will be onsite continuing work on Kemrich Drive Saturday, 7/25.
      • Lee Valley Circle and Weston Circle sod installation will begin when weather permits.
      • Tara Road, Antrim Court, and Antrim Terrace irrigation repairs are scheduled to continue the week of 7/27.


    Phase 2:

    • Upcoming Work
      • Fleetwood Drive and Tralee Drive roadway excavation and soil corrections is scheduled to begin the week of 7/27.
    • Ongoing Work
      • Fleetwood Drive sump drain installation will continue during the week of 7/27.
    • Completed Work
      • Dublin Circle watermain replacement is complete.
      • Tralee Drive storm sewer improvements are complete.

    Gleason Road Closure Notice

    Gleason Road between Schey Drive and Tupa Drive will be closed for utility improvements until approximately Monday, 7/27. The detour route will be Hilary Lane and Valley View Road.


    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Work will occur on Saturday, July 25.
    • Please see the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1

    • Upcoming Work
      • Tara Road, Antrim Court, and Antrim Terrace mailbox installation is scheduled for the week of 7/27. The contractor will notify you when mail delivery will be restored. Until that time, please continue to collect your mail at the temporary mail bank location.
    • Ongoing Work
      • Lanham Lane and Kemrich Drive roadway and soil corrections is scheduled to continue into the week of 7/27. Crews will be onsite continuing work on Kemrich Drive Saturday, 7/25.
      • Lee Valley Circle and Weston Circle sod installation will begin when weather permits.
      • Tara Road, Antrim Court, and Antrim Terrace irrigation repairs are scheduled to continue the week of 7/27.


    Phase 2:

    • Upcoming Work
      • Fleetwood Drive and Tralee Drive roadway excavation and soil corrections is scheduled to begin the week of 7/27.
    • Ongoing Work
      • Fleetwood Drive sump drain installation will continue during the week of 7/27.
    • Completed Work
      • Dublin Circle watermain replacement is complete.
      • Tralee Drive storm sewer improvements are complete.
  • Construction Update - 7/17/2026

    Share Construction Update - 7/17/2026 on Facebook Share Construction Update - 7/17/2026 on X (formerly Twitter) Share Construction Update - 7/17/2026 on Linkedin Email Construction Update - 7/17/2026 link

    Gleason Road Closure Notice

    Gleason Road between Schey Drive and Tupa Drive will be closed for utility improvements until approximately Friday, 7/24. The detour route will be Hilary Lane and Valley View Road.


    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Minor work will occur on Saturday, July 18.
    • Please see the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1

    • Upcoming Work
      • Tara Road, Antrim Court, and Antrim Terrace roadway grading in preparation of asphalt paving is scheduled to begin the week of 7/20.
        • The first layer of asphalt paving is tentatively scheduled for the end of the week of 7/20.
      • Lanham Lane and Kemrich Drive roadway and soil corrections is scheduled to begin the week of 7/20.
      • Lee Valley Circle and Weston Circle sod installation will begin when weather permits.


    Phase 2:

    • Upcoming Work
      • Fleetwood Drive roadway excavation and soil corrections is scheduled to begin the week of 7/20.
      • Dublin Circle watermain installation is scheduled to begin the week of 7/20.
      • Tralee Drive storm sewer installation is scheduled to begin the week of 7/20.
    • Ongoing Work
      • Fleetwood Drive storm sewer and sump drain installation will continue during the week of 7/20.
      • Dublin Road, Kerry Road, and Wexford Road watermain installation will continue the week of 7/20.
    • Completed Work
      • 70th St and Dublin Circle watermain valve replacement is complete.

    Gleason Road Closure Notice

    Gleason Road between Schey Drive and Tupa Drive will be closed for utility improvements until approximately Friday, 7/24. The detour route will be Hilary Lane and Valley View Road.


    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Minor work will occur on Saturday, July 18.
    • Please see the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary water loss.
      • Driveway Accessibility
        • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.


    Phase 1

    • Upcoming Work
      • Tara Road, Antrim Court, and Antrim Terrace roadway grading in preparation of asphalt paving is scheduled to begin the week of 7/20.
        • The first layer of asphalt paving is tentatively scheduled for the end of the week of 7/20.
      • Lanham Lane and Kemrich Drive roadway and soil corrections is scheduled to begin the week of 7/20.
      • Lee Valley Circle and Weston Circle sod installation will begin when weather permits.


    Phase 2:

    • Upcoming Work
      • Fleetwood Drive roadway excavation and soil corrections is scheduled to begin the week of 7/20.
      • Dublin Circle watermain installation is scheduled to begin the week of 7/20.
      • Tralee Drive storm sewer installation is scheduled to begin the week of 7/20.
    • Ongoing Work
      • Fleetwood Drive storm sewer and sump drain installation will continue during the week of 7/20.
      • Dublin Road, Kerry Road, and Wexford Road watermain installation will continue the week of 7/20.
    • Completed Work
      • 70th St and Dublin Circle watermain valve replacement is complete.
Page last updated: 18 Sep 2026, 12:37 PM