Rolling Green Neighborhood Roadway Reconstruction

Share Rolling Green Neighborhood Roadway Reconstruction on Facebook Share Rolling Green Neighborhood Roadway Reconstruction on X (formerly Twitter) Share Rolling Green Neighborhood Roadway Reconstruction on Linkedin Email Rolling Green Neighborhood Roadway Reconstruction link

Rolling Green Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

The proposed 2027 reconstruction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Installation of concrete curb and gutter,
  • Replacement of a portion of the watermain and water services,
  • Improvements to the storm sewer systems, and
  • The project is funded by a combination of special assessments, property taxes, and respective utility funds.

Rolling Green Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

The proposed 2027 reconstruction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Installation of concrete curb and gutter,
  • Replacement of a portion of the watermain and water services,
  • Improvements to the storm sewer systems, and
  • The project is funded by a combination of special assessments, property taxes, and respective utility funds.
  • Welcome!

    Share Welcome! on Facebook Share Welcome! on X (formerly Twitter) Share Welcome! on Linkedin Email Welcome! link

    Welcome to Better Together Edina. This web page will be the hub for sharing information related to roadway reconstruction scheduled for 2027 in the Rolling Green neighborhood. Important updates will be posted on this web page at various points during the Engineering Study phase. Anticipate weekly updates during construction in 2027. Key project milestones include:

    • June 2026 – Begin Engineering Study preparation
    • Late summer 2026 – Informational Meeting / Video
    • Nov. 2026 – Engineering Study complete
    • Dec. 2026 – City Council / Public Hearing meeting to consider authorizing project design
    • Mar. 2027 – City Council meeting to consider authorizing construction
    • Apr. 2027 – Construction begins
    • Oct. 2027 – Construction substantial completion

    A series of short videos on the City's street reconstruction program can be found here.

    Feel free to call or email me with your project questions, or you can post questions on this website.

    We look forward to assisting and keeping you informed with this project.

    Aaron Ditzler

    Welcome to Better Together Edina. This web page will be the hub for sharing information related to roadway reconstruction scheduled for 2027 in the Rolling Green neighborhood. Important updates will be posted on this web page at various points during the Engineering Study phase. Anticipate weekly updates during construction in 2027. Key project milestones include:

    • June 2026 – Begin Engineering Study preparation
    • Late summer 2026 – Informational Meeting / Video
    • Nov. 2026 – Engineering Study complete
    • Dec. 2026 – City Council / Public Hearing meeting to consider authorizing project design
    • Mar. 2027 – City Council meeting to consider authorizing construction
    • Apr. 2027 – Construction begins
    • Oct. 2027 – Construction substantial completion

    A series of short videos on the City's street reconstruction program can be found here.

    Feel free to call or email me with your project questions, or you can post questions on this website.

    We look forward to assisting and keeping you informed with this project.