72nd Street Improvements
France Avenue Closure Between West 69th and West 76th Streets Begins Sept. 16
France Avenue will be closed to thru traffic between W. 69th and W. 76th Streets starting Wednesday, Sept. 16 for approximately 3 weeks. Drivers should use York Avenue to travel around the closure. Drivers can still use France Avenue to access businesses and residences within the work area. From either direction, France Avenue will remain open for local traffic up to the full closure between Hazelton Road and Gallagher Drive.
About the Project
The project is the first segment of the South Trunk Sanitary Sewer Improvements project, a major, multi-year effort in the South Cornelia and Lake Edina neighborhoods to increase capacity and ensure long-term service reliability of the more than 70-year-old South Trunk sanitary sewer. The sewer runs beneath southern Edina and collects wastewater from two-thirds of the city.
This year’s work replaces and upsizes 0.36 mile of sewer line from just west of Cornelia Drive to France Avenue and builds on the recent replacement of Lift Station 6, which laid the groundwork for the trunk line improvements. As part of the project, West 72nd Street is also being fully reconstructed.
France Avenue Closure Between West 69th and West 76th Streets Begins Sept. 16
France Avenue will be closed to thru traffic between W. 69th and W. 76th Streets starting Wednesday, Sept. 16 for approximately 3 weeks. Drivers should use York Avenue to travel around the closure. Drivers can still use France Avenue to access businesses and residences within the work area. From either direction, France Avenue will remain open for local traffic up to the full closure between Hazelton Road and Gallagher Drive.
About the Project
The project is the first segment of the South Trunk Sanitary Sewer Improvements project, a major, multi-year effort in the South Cornelia and Lake Edina neighborhoods to increase capacity and ensure long-term service reliability of the more than 70-year-old South Trunk sanitary sewer. The sewer runs beneath southern Edina and collects wastewater from two-thirds of the city.
This year’s work replaces and upsizes 0.36 mile of sewer line from just west of Cornelia Drive to France Avenue and builds on the recent replacement of Lift Station 6, which laid the groundwork for the trunk line improvements. As part of the project, West 72nd Street is also being fully reconstructed.
-
Friday (8/28) Access
Share Friday (8/28) Access on Facebook Share Friday (8/28) Access on X (formerly Twitter) Share Friday (8/28) Access on Linkedin Email Friday (8/28) Access linkThe intersection of W. 72nd/Glouchester will be closed again tomorrow (8/28). All other intersections along W. 72nd, including Cornelia Drive will be open/accessible.
The intersection of W. 72nd/Glouchester will be closed again tomorrow (8/28). All other intersections along W. 72nd, including Cornelia Drive will be open/accessible.
-
Thursday (8/27) Access
Share Thursday (8/27) Access on Facebook Share Thursday (8/27) Access on X (formerly Twitter) Share Thursday (8/27) Access on Linkedin Email Thursday (8/27) Access linkThe intersection of W. 72nd/Glouchester will be closed tomorrow (8/27). All other intersections along W. 72nd, including Cornelia Drive will be open/accessible tomorrow (8/27).
The intersection of W. 72nd/Glouchester will be closed tomorrow (8/27). All other intersections along W. 72nd, including Cornelia Drive will be open/accessible tomorrow (8/27).
-
Wednesday (8/26) Access
Share Wednesday (8/26) Access on Facebook Share Wednesday (8/26) Access on X (formerly Twitter) Share Wednesday (8/26) Access on Linkedin Email Wednesday (8/26) Access linkThe contractor will be continuing with watermain installation heading west on W. 72nd. The intersection of W. 72nd/Bristol will be getting closed tomorrow (8/26). If you live in Bristol Circle, please have your vehicles parked on the north side of W. 72nd if needing access throughout the workday.
The contractor will be continuing with watermain installation heading west on W. 72nd. The intersection of W. 72nd/Bristol will be getting closed tomorrow (8/26). If you live in Bristol Circle, please have your vehicles parked on the north side of W. 72nd if needing access throughout the workday.
-
Tuesday (8/25) Construction Update
Share Tuesday (8/25) Construction Update on Facebook Share Tuesday (8/25) Construction Update on X (formerly Twitter) Share Tuesday (8/25) Construction Update on Linkedin Email Tuesday (8/25) Construction Update linkTemporary Water Outage - This morning the temporary water piping that feeds the Heatherton Circle cul-de-sac broke. The contractor worked to get it repaired as quickly as possible. Apologies for the inconvenience.
Heatherton Circle Access - There was some miscommunication regarding when the intersection of W. 72nd/Heatherton would be getting closed. The contractor work schedule was modified late yesterday. Apologies for the inconvenience. W. 72nd/Heatherton is closed today for watermain work.
Temporary Water Outage - This morning the temporary water piping that feeds the Heatherton Circle cul-de-sac broke. The contractor worked to get it repaired as quickly as possible. Apologies for the inconvenience.
Heatherton Circle Access - There was some miscommunication regarding when the intersection of W. 72nd/Heatherton would be getting closed. The contractor work schedule was modified late yesterday. Apologies for the inconvenience. W. 72nd/Heatherton is closed today for watermain work.
-
Tuesday (8/25) Access
Share Tuesday (8/25) Access on Facebook Share Tuesday (8/25) Access on X (formerly Twitter) Share Tuesday (8/25) Access on Linkedin Email Tuesday (8/25) Access linkThe contractor will be continuing with watermain installation on the east side of W. 72nd/Glouchester heading west. The intersection of W. 72nd/Heatherton will be getting closed tomorrow (8/25). If you live in Heatherton Circle, please have your vehicles parked on the north side of W. 72nd if needing access throughout the workday.
The contractor will be continuing with watermain installation on the east side of W. 72nd/Glouchester heading west. The intersection of W. 72nd/Heatherton will be getting closed tomorrow (8/25). If you live in Heatherton Circle, please have your vehicles parked on the north side of W. 72nd if needing access throughout the workday.
-
Monday (8/24) Access Update
Share Monday (8/24) Access Update on Facebook Share Monday (8/24) Access Update on X (formerly Twitter) Share Monday (8/24) Access Update on Linkedin Email Monday (8/24) Access Update linkThe contractor has decided to start watermain work on the east side of Cornelia heading west. The intersection of W. 72nd/Glouchester is expected to be closed in the next few hours (around 11:00), please plan to utilize the W. 72nd/Cornelia intersection today if you live on either Cornelia or Glouchester south of W. 72nd.
The contractor has decided to start watermain work on the east side of Cornelia heading west. The intersection of W. 72nd/Glouchester is expected to be closed in the next few hours (around 11:00), please plan to utilize the W. 72nd/Cornelia intersection today if you live on either Cornelia or Glouchester south of W. 72nd.
-
Weekend & Monday (8/24) Access
Share Weekend & Monday (8/24) Access on Facebook Share Weekend & Monday (8/24) Access on X (formerly Twitter) Share Weekend & Monday (8/24) Access on Linkedin Email Weekend & Monday (8/24) Access linkWeekend Access
- All intersections will be open and accessible over the weekend.
- Travel along W. 72nd Street is still not advised, please access the open intersections from either the north or the south
Monday (8/24) Access
- The intersection of Bristol & W. 72nd Street will be closed Monday (8/24) to finish the watermain work within the intersection, please plan on using alternate routes and parking north of W. 72nd if you live in Bristol Circle
- The other intersections within the project area will remain accessible
Weekend Access
- All intersections will be open and accessible over the weekend.
- Travel along W. 72nd Street is still not advised, please access the open intersections from either the north or the south
Monday (8/24) Access
- The intersection of Bristol & W. 72nd Street will be closed Monday (8/24) to finish the watermain work within the intersection, please plan on using alternate routes and parking north of W. 72nd if you live in Bristol Circle
- The other intersections within the project area will remain accessible
- All intersections will be open and accessible over the weekend.
-
Weekly Construction Update #7
Share Weekly Construction Update #7 on Facebook Share Weekly Construction Update #7 on X (formerly Twitter) Share Weekly Construction Update #7 on Linkedin Email Weekly Construction Update #7 linkWork Completed the Week of August 17th
- Utility work continued on Phase 1 (W. 72nd, from Cornelia Drive to Glouchester Avenue) with watermain, storm sewer and sanitary sewer replacement
- Roadway grading work began on Phase 1
- Phase 2 (W. 72nd, from Glouchester Avenue to Lynmar Lane) started with roadway removals
- Temporary water piping system was installed at Heatherton & Bristol that will supply the cul-de-sacs with water during Phase 2 utility work
- Multiple water shutdowns occurred affecting multiple properties within the project area as part of the Phase 2 start up utility work
Work Planned for the Week of August 24th
- Utility work will wrap up on Phase 1 (W. 72nd, from Cornelia Drive to Glouchester Avenue)
- Roadway grading work will wrap up on Phase 1
- Concrete curbing may get poured later in the week on Phase 1
- Utility work will continue on Phase 2 (W. 72nd, from Glouchester Avenue to Lynmar Lane)
- Cornelia Drive will be reopened prior to Cornelia Elementary school activities beginning, the roadway surface will be graveled but fully accessible from the south and from the west
Residential Access
- As the work continues to progress the project website will be updated regularly regarding access. The project team appreciates the patience and understanding during the moving operations of construction activity
Work Completed the Week of August 17th
- Utility work continued on Phase 1 (W. 72nd, from Cornelia Drive to Glouchester Avenue) with watermain, storm sewer and sanitary sewer replacement
- Roadway grading work began on Phase 1
- Phase 2 (W. 72nd, from Glouchester Avenue to Lynmar Lane) started with roadway removals
- Temporary water piping system was installed at Heatherton & Bristol that will supply the cul-de-sacs with water during Phase 2 utility work
- Multiple water shutdowns occurred affecting multiple properties within the project area as part of the Phase 2 start up utility work
Work Planned for the Week of August 24th
- Utility work will wrap up on Phase 1 (W. 72nd, from Cornelia Drive to Glouchester Avenue)
- Roadway grading work will wrap up on Phase 1
- Concrete curbing may get poured later in the week on Phase 1
- Utility work will continue on Phase 2 (W. 72nd, from Glouchester Avenue to Lynmar Lane)
- Cornelia Drive will be reopened prior to Cornelia Elementary school activities beginning, the roadway surface will be graveled but fully accessible from the south and from the west
Residential Access
- As the work continues to progress the project website will be updated regularly regarding access. The project team appreciates the patience and understanding during the moving operations of construction activity
-
Friday (8/21) Access & Bristol Closure
Share Friday (8/21) Access & Bristol Closure on Facebook Share Friday (8/21) Access & Bristol Closure on X (formerly Twitter) Share Friday (8/21) Access & Bristol Closure on Linkedin Email Friday (8/21) Access & Bristol Closure linkResidential Access
- Residents living on Cornelia Drive or Glouchester Avenue south of W. 72nd Street should use Glouchester Avenue on Friday August 21st
- Cornelia Drive will have limited access as grading work progresses on Friday August 21st
Bristol Circle Closure
- The intersection of Bristol & W. 72nd Street will be closed tomorrow (8/21) to complete watermain work within the intersection, please plan on using alternate routes and parking north of W. 72nd if you live in Bristol Circle
Residential Access
- Residents living on Cornelia Drive or Glouchester Avenue south of W. 72nd Street should use Glouchester Avenue on Friday August 21st
- Cornelia Drive will have limited access as grading work progresses on Friday August 21st
Bristol Circle Closure
- The intersection of Bristol & W. 72nd Street will be closed tomorrow (8/21) to complete watermain work within the intersection, please plan on using alternate routes and parking north of W. 72nd if you live in Bristol Circle
-
Thursday (8/20) Access & Heatherton Closure
Share Thursday (8/20) Access & Heatherton Closure on Facebook Share Thursday (8/20) Access & Heatherton Closure on X (formerly Twitter) Share Thursday (8/20) Access & Heatherton Closure on Linkedin Email Thursday (8/20) Access & Heatherton Closure linkResidential Access
- Residents living on Cornelia Drive or Glouchester Avenue south of W. 72nd Street should use Glouchester Avenue on Thursday August 20th
- Cornelia Drive will have limited access as grading work progresses on Thursday August 20th
Heatherton Circle Closure
- The intersection of Heatherton & W. 72nd Street will be closed tomorrow (8/20) to complete watermain work within the intersection, please plan on using alternate routes and parking north of W. 72nd if you live in Heatherton Circle
Residential Access
- Residents living on Cornelia Drive or Glouchester Avenue south of W. 72nd Street should use Glouchester Avenue on Thursday August 20th
- Cornelia Drive will have limited access as grading work progresses on Thursday August 20th
Heatherton Circle Closure
- The intersection of Heatherton & W. 72nd Street will be closed tomorrow (8/20) to complete watermain work within the intersection, please plan on using alternate routes and parking north of W. 72nd if you live in Heatherton Circle
Online Project Talk: 11 a.m. Monday, Sept. 14![]()
City staff will host an online Project Talk at 11 a.m. Monday, Sept. 14, to share construction updates and answer questions about the upcoming France Avenue closure. Anyone interested in the project is welcome to attend.
How to Join:
When it’s time for the Project Talk, visit EdinaMN.gov/FranceMeeting to participate. The talk will be held online through Microsoft Teams. No account is required, and participants can join as guests.
Date & Time:
11 a.m. Monday, Sept. 14
-
Phone 952-903-5713 Email RBintner@EdinaMN.gov -
Phone 612-756-3427 Email sarah.lloyd@bolton-menk.com -
JH
Phone 612-965-2473 Email josh.hrabe@bolton-menk.com -
FK
Phone 763-353-2524 Email francis.killen@bolton-menk.com
Sign Up for Emailed Project Updates
PRIVACY NOTICE: Under M.S. 13.356, your email address is private data. If you do not provide an email address you will not receive requested updates. Your email address will be available to anyone with a work assignment that reasonably require access.
- What is the West 72nd Street Improvements project and why is it needed?
- What improvements are included in the project?
- Who can do private sewer inspection if I want to review my sewer condition ahead of the work?
- When will the project be complete?
- Why does France Avenue need to close?
- What should I know about the France Avenue closure and detours?
- How is the project funded?
- Is it possible that any property specific special assessments might fund this work?
- What happens after the West 72nd Street project?
- Who can I contact with questions?