BTE Website & Project Updates

September 22, 2026

BTE WebsiteFrom Wednesday, (9/23) to Tuesday, 9/29, the W. 72nd project BTE website will be undergoing some updates/upgrades. During this time, the project team will not be able to post project-related updates. However, the website will still be accessible for anyone visiting the website to view past updates.Project UpdatesWeek of 9/21

  • Posting to the BTE website will be unavailable starting Wednesday, 9/23
  • Utility work will continue in France Avenue
  • Roadway grading work from Cornelia to Bristol along W. 72nd will be completed
  • The sanitary sewer bypassing piping and generators are set up and will go online and run as necessary
Week of 9/28
  • Utility work will wrap up in the northbound lanes of France Avenue and continue progressing into the southbound lanes heading west
  • The BTE website will go back online on Tuesday, 9/29
  • France Avenue grading work will start in preparation for concrete
  • Concrete curbing and paving may occur towards the end of the week on France Avenue with the anticipation of re-opening the roadway the following week
  • Concrete curbing may be installed along W. 72nd from Cornelia to Bristol, residents with driveways on W. 72nd will be notified regarding access restrictions.
France Avenue Closure/Detour
  • The closure and detour of France Avenue will remain in-place until the concrete paving work is completed
  • The project team is actively making modifications to try and help facilitate any issues that are being experienced by businesses, drivers, pedestrians.
  • The project team would like to thank everyone for their continued patience and understanding as this work continues progressing.