Work Completed the Week of August 17th

  • Utility work continued on Phase 1 (W. 72nd, from Cornelia Drive to Glouchester Avenue) with watermain, storm sewer and sanitary sewer replacement
  • Roadway grading work began on Phase 1
  • Phase 2 (W. 72nd, from Glouchester Avenue to Lynmar Lane) started with roadway removals
  • Temporary water piping system was installed at Heatherton & Bristol that will supply the cul-de-sacs with water during Phase 2 utility work
  • Multiple water shutdowns occurred affecting multiple properties within the project area as part of the Phase 2 start up utility work
Work Planned for the Week of August 24th
  • Utility work will wrap up on Phase 1 (W. 72nd, from Cornelia Drive to Glouchester Avenue)
  • Roadway grading work will wrap up on Phase 1
  • Concrete curbing may get poured later in the week on Phase 1
  • Utility work will continue on Phase 2 (W. 72nd, from Glouchester Avenue to Lynmar Lane)
  • Cornelia Drive will be reopened prior to Cornelia Elementary school activities beginning, the roadway surface will be graveled but fully accessible from the south and from the west
Residential Access
  • As the work continues to progress the project website will be updated regularly regarding access. The project team appreciates the patience and understanding during the moving operations of construction activity