Work Completed the Week of October 12th

  • Roadway grading work was completed from Bristol to France Ave
  • W. 72nd Street concrete sidewalk work continued progressing
  • Private utility handholes were relocated out of proposed new sidewalk location

Work Planned for the Week of October 19th

  • Sidewalk work will wrap up along W. 72nd Street
  • Paving the first layer of asphalt from Cornelia Drive to Bristol will occur
  • Grading of yards and boulevards will begin