Weekly Update #16

November 4, 2026

Work Completed the Week of November 2nd

  • Due to the rainy weather, there was not much work completed early in the week
  • Boulevard grading and topsoil placement will continue along W. 72nd
  • Irrigation repairs will continue on various properties
  • Manhole castings and water valves will begin getting installed to final elevations in preparation for final paving
  • Retaining Wall work will begin at various properties

Work Planned for the Week of November 9th

  • Boulevard grading and topsoil placement will wrap up along W. 72nd
  • Irrigation repairs will wrap up along W. 72nd
  • Retaining wall work will continue at various properties
  • Sod and mulch restoration efforts may occur later in the week

Final Paving - Paving of the final layer of asphalt is still planned to occur this year. A date is yet to be determined.