Weekly Update #17

November 13, 2026

Work Completed the Week of November 9th

  • Boulevard grading and topsoil placement continued along W. 72nd
  • Irrigation repairs continued on various properties
  • Retaining Wall work will continued at various properties
  • Paver placement and other miscellaneous landscaping work occurred

Work Planned for the Week of November 16th

  • Boulevard grading and topsoil placement will wrap up along W. 72nd
  • Irrigation repairs will wrap up along W. 72nd
  • Retaining wall work will wrap up at various properties
  • Sod placement will occur on Tuesday, 11/17
  • Final paving will occur on Wednesday, 11/20