Bristol & Mavelle Park/Lynmar Basin Stormwater Project
Consultation has concluded.
The Lynmar Basin is a low-lying, open space that currently briefly detains stormwater before it makes its way to Lake Edina and eventually Nine Mile Creek through storm sewer pipes. The location was identified as an opportunity to better manage stormwater as part of a larger effort to improve downstream water resources.
The retrofit project will better utilize the space to capture and clean more stormwater than it already does today. The existing dry pond area will be expanded and deepened to promote stormwater infiltration. The infiltration basin will be planted with native trees, shrubs, and forbs.
The project benefits include;
- Less polluted water entering Lake Edina and downstream water resources
- Reduced flooding in the South Cornelia neighborhood
- Enhanced natural resources, including improving pollinator habitat
- A portion of the space kept open for passive recreation, and a new walking path
This project is done in partnership with the Nine Mile Creek Watershed District.
The Lynmar Basin is a low-lying, open space that currently briefly detains stormwater before it makes its way to Lake Edina and eventually Nine Mile Creek through storm sewer pipes. The location was identified as an opportunity to better manage stormwater as part of a larger effort to improve downstream water resources.
The retrofit project will better utilize the space to capture and clean more stormwater than it already does today. The existing dry pond area will be expanded and deepened to promote stormwater infiltration. The infiltration basin will be planted with native trees, shrubs, and forbs.
The project benefits include;
- Less polluted water entering Lake Edina and downstream water resources
- Reduced flooding in the South Cornelia neighborhood
- Enhanced natural resources, including improving pollinator habitat
- A portion of the space kept open for passive recreation, and a new walking path
This project is done in partnership with the Nine Mile Creek Watershed District.
Consultation has concluded.
-
Spring work begins
Share Spring work begins on Facebook Share Spring work begins on Twitter Share Spring work begins on Linkedin Email Spring work begins linkCrews are eager to get on site as soon as the weather allows
You'll see some equipment and limestone blocks arriving on site in the next week or two for the crew to set stepping stones through the basin and some rock outcroppings.
Plugs and trees will be delivered and installed before the end of May.
-
Construction Update - November 23
Share Construction Update - November 23 on Facebook Share Construction Update - November 23 on Twitter Share Construction Update - November 23 on Linkedin Email Construction Update - November 23 linkThe site has been closed up and cleaned up for the year. Crews will be back in spring to do restoration and planting. The limestone outcroppings and stepping stones installations have been delayed to spring.
-
Construction Update - November 9
Share Construction Update - November 9 on Facebook Share Construction Update - November 9 on Twitter Share Construction Update - November 9 on Linkedin Email Construction Update - November 9 linkCrews are working this week to get concrete poured before the weather turns.
-
Construction Update - October 27
Share Construction Update - October 27 on Facebook Share Construction Update - October 27 on Twitter Share Construction Update - October 27 on Linkedin Email Construction Update - October 27 linkConstruction of the sand trenches is complete. Crews are transitioning to the storm pipe work in the street at Lynmar Lane.
In the first part of November Lynmar Lane will be restored and a concrete sidewalk will be installed. You'll also see the limestone stepping stones and outcroppings at the basin going in.
-
Construction Update - October 5
Share Construction Update - October 5 on Facebook Share Construction Update - October 5 on Twitter Share Construction Update - October 5 on Linkedin Email Construction Update - October 5 linkThe majority of excavation is complete. Crews are now working on installing the sand trenches at the bottom of the basin for stormwater infiltration.
-
Construction Update - September 22
Share Construction Update - September 22 on Facebook Share Construction Update - September 22 on Twitter Share Construction Update - September 22 on Linkedin Email Construction Update - September 22 linkThis week
Tree clearing will be completed. Trees in the basin were removed to accommodate lowering the basin and installing a sand trench for infiltrating stormwater. Ash trees along Mavelle Drive were removed as part of the City's plan to slow the spread of Emerald Ash Borer.
Next week
Earthwork and initial soil disturbance begins.
-
Construction Schedule Update - Mobilizing Next Week
Share Construction Schedule Update - Mobilizing Next Week on Facebook Share Construction Schedule Update - Mobilizing Next Week on Twitter Share Construction Schedule Update - Mobilizing Next Week on Linkedin Email Construction Schedule Update - Mobilizing Next Week linkThe construction crew will begin mobilizing early next week - expect to see equipment and people on site as early as Monday.
They also plan to begin work next week. The first step is tree removal in the basin.
-
Construction Schedule Update
Share Construction Schedule Update on Facebook Share Construction Schedule Update on Twitter Share Construction Schedule Update on Linkedin Email Construction Schedule Update linkThe contractor is eager to get started and plans to mobilize and begin work in September.
-
Construction Schedule
Share Construction Schedule on Facebook Share Construction Schedule on Twitter Share Construction Schedule on Linkedin Email Construction Schedule linkGrading and storm sewer work is expected to start in October and continue for approximately 2 months
Seeding and planting will occur in spring 2023
-
Contractor Selected
Share Contractor Selected on Facebook Share Contractor Selected on Twitter Share Contractor Selected on Linkedin Email Contractor Selected linkEight responses to the request for bid were received with several coming in below what Engineers estimated.
The Nine Mile Creek Watershed District Board has awarded the contract to U.S. SiteWork.
August 17, 2022 Nine Mile Creek Watershed District Board Meeting Agenda
Next steps include getting more detailed information on the construction schedule.
Signup Banner
Who's Listening
-
Phone 952-826-0445 Email JWilson@EdinaMN.gov -
Phone 952-903-5713 Email RBintner@EdinaMN.gov -
Phone 952-826-0317 Email TSwenson@EdinaMN.gov -
Phone 952-835-2078 Email RAnhorn@ninemilecreek.org
Key Dates
-
September 2022
-
August 17 2022
-
June 21 2022
Lifecycle
-
Introduce Project
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageApril 2021
We will introduce the project and seek input on current open space use and measures to control stormwater.
-
Develop Initial Concepts
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageMay - July 2021
We will share initial concepts and let you know how your input influenced the design concepts.
-
Refine Concepts
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageJuly - September 2021
We will consider input, refine concepts, and share the outcome.
-
Make a Decision
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageSeptember 2021
Staff will make a recommendation to the City Council and Nine Mile Creek Watershed District Board of Managers. City Council will make a decision. Nine Mile Creek Watershed District Board of Managers will authorize staff to undertake a feasibility study to be considered to order the project.
-
Close the Loop
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageLate September 2021
We will tell people what decision was made. The public input portion of the concept design development process ends.
-
Make a Decision
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageMarch 2022
The Nine Mile Creek Watershed District Board will hold a public hearing, consider the feasibility study and make a decision.
-
Added: Detailed Engineering and Landscape Design Begins
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageSummer 2022
The Nine Mile Creek Watershed District Board approved the concept plan at their March Board meeting. This moved the project from the concept design phase to the detailed engineering and landscape design phase.
-
Added: Cooperative Agreement Decision
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageSummer 2022
City Council and Nine Mile Creek Watershed District consider entering into a cooperative agreement which describes how the two will work together.
-
Added: Design and Bid
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageSummer 2022
Staff will complete the design and prepare construction bid documents. A contractor will be selected through a competitive process.
-
Added: Construction
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageFall 2022
Construction begins.
-
Added: Restoration and Maintenance
Bristol & Mavelle Park/Lynmar Basin Stormwater Project is currently at this stage2023 and Beyond
Disturbed turf areas will be restored and natural areas will be planted.
Photos
Documents
-
Lynmar Basin Rendering_Sept 2022.pdf (3.53 MB) (pdf)
-
Lynmar Basin Rendering_90%_June2022.pdf (7.59 MB) (pdf)
-
Sept 21 2021 Presentation.pdf (1.55 MB) (pdf)
-
Lynmar Basin_ConceptPlan_SummaryReport_090921.pdf (4.77 MB) (pdf)
-
Initial Concepts Layouts_July 2021 (2.71 MB) (pdf)
-
Participation Plan.pdf (182 KB) (pdf)
-
Lake Cornelia and Lake Edina Feasibility Study Report (7.95 MB) (pdf)
-
Feasibility Study_February 2022.pdf (5.54 MB) (pdf)