Construction Progress 9.18.2026

September 18, 2026

Work continues this week with equipment working onsite to grade areas around the SE portion of the park. Next week excavators will be onsite digging the foundations and setting new utilities for the new pavilion building. Other work includes stump grinding and continued grading work near the existing building onsite. Possible disturbances include some periods of hauling or trucks in and out of the park onto Parklawn and 77th street. Materials are being imported for the foundation and materials from former golf course construction are being exported. Other sights and sounds will be equipment operating and some grinding from crews removing tree stumps.