Interlachen Blvd Roadway Reconstruction

Share Interlachen Blvd Roadway Reconstruction on Facebook Share Interlachen Blvd Roadway Reconstruction on Twitter Share Interlachen Blvd Roadway Reconstruction on Linkedin Email Interlachen Blvd Roadway Reconstruction link

Interlachen Boulevard reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2027 construction project includes work for Interlachen Blvd. from approximately 400' east of Blake Road to Mirror Lakes Drive.

The improvements include rehabilitation to the water main, storm sewer, and sanitary sewer systems, installation of concrete curb and gutter with on street bike lanes, bituminous street pavement, and concrete sidewalk construction along the south side of Interlachen Boulevard. These improvements are needed to provide the services expected of the roadway, public utilities, and for pedestrian safety.

The overall construction cost is estimated to be $6.1 million. This project will be funded using Municipal State Aid funds, local utility funds, and property owner assessments as well as a donation from Interlachen Country Club. Estimated assessments per REU are $4,500 to $6,500. There are 13 properties impacted by assessments.

Interlachen Boulevard reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2027 construction project includes work for Interlachen Blvd. from approximately 400' east of Blake Road to Mirror Lakes Drive.

The improvements include rehabilitation to the water main, storm sewer, and sanitary sewer systems, installation of concrete curb and gutter with on street bike lanes, bituminous street pavement, and concrete sidewalk construction along the south side of Interlachen Boulevard. These improvements are needed to provide the services expected of the roadway, public utilities, and for pedestrian safety.

The overall construction cost is estimated to be $6.1 million. This project will be funded using Municipal State Aid funds, local utility funds, and property owner assessments as well as a donation from Interlachen Country Club. Estimated assessments per REU are $4,500 to $6,500. There are 13 properties impacted by assessments.

  • Welcome!

    Share Welcome! on Facebook Share Welcome! on Twitter Share Welcome! on Linkedin Email Welcome! link
    supporting image

    Hello and welcome to Better Together Edina. This web page will be the hub for sharing information related to roadway reconstruction scheduled for 2027 on Interlachen Blvd. Important updates will be posted on this web page at various points during final design. Anticipate weekly updates during construction in 2027. Key project milestones include:

    • Nov. 2026 – Final design complete
    • Dec. 2026 – City Council / Public Hearing to consider special assessments and scope of project
    • Mar. 2027 – City Council meeting to consider authorizing construction
    • Apr. 2027 – Construction begins
    • Oct. 2027 – Construction substantial completion
    • Oct. 2028 – City Council approval of final special assessments

    A series of short videos on the City's street reconstruction program can be found here.

    Feel free to call or email me with your project questions, or you can post questions on this website.

    We look forward to assisting and keeping you informed with this project.

    Chad Millner

    Hello and welcome to Better Together Edina. This web page will be the hub for sharing information related to roadway reconstruction scheduled for 2027 on Interlachen Blvd. Important updates will be posted on this web page at various points during final design. Anticipate weekly updates during construction in 2027. Key project milestones include:

    • Nov. 2026 – Final design complete
    • Dec. 2026 – City Council / Public Hearing to consider special assessments and scope of project
    • Mar. 2027 – City Council meeting to consider authorizing construction
    • Apr. 2027 – Construction begins
    • Oct. 2027 – Construction substantial completion
    • Oct. 2028 – City Council approval of final special assessments

    A series of short videos on the City's street reconstruction program can be found here.

    Feel free to call or email me with your project questions, or you can post questions on this website.

    We look forward to assisting and keeping you informed with this project.

    Chad Millner

Page last updated: 29 Apr 2026, 10:33 AM