Presidents A & B Neighborhood Roadway Reconstruction

Share Presidents A & B Neighborhood Roadway Reconstruction on Facebook Share Presidents A & B Neighborhood Roadway Reconstruction on X (formerly Twitter) Share Presidents A & B Neighborhood Roadway Reconstruction on Linkedin Email Presidents A & B Neighborhood Roadway Reconstruction link
Map showing the Presidents neighborhood and the project limit boundaries.

Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2025 construction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete reconstruction of two alleys west of Madison Avenue,
  • Complete replacement of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Proposed construction of multi-modal facilities along:
    • Monroe Avenue (5' sidewalk)
    • Belmore Lane (8' shared use path)
    • Washington Avenue (8' shared use path)
  • The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
  • A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
  • An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
  • If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.

Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2025 construction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete reconstruction of two alleys west of Madison Avenue,
  • Complete replacement of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Proposed construction of multi-modal facilities along:
    • Monroe Avenue (5' sidewalk)
    • Belmore Lane (8' shared use path)
    • Washington Avenue (8' shared use path)
  • The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
  • A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
  • An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
  • If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.

Ask a Question

Submit questions about the project here and city staff will get back to you!

If this is an emergency, please dial 911. If you have an after-hours, urgent, project related matter, please contact our after hours non-emergency line at 952-826-1600.

Email
loader image
Didn't receive confirmation?
Seems like you are already registered, please provide the password. Forgot your password? Create a new one now.
  • Share The new road work looks great, however there is still construction debris on the road in front of my house and I would like to know when that will be removed. It has been there several weeks post completion and seems as though it has been forgotten. It is also a hazard for those walking the neighborhood as this block does not have sidewalks. Items include a pile of dirt, bags of sand, concrete blocks, and blinking hazard lights. I live at 6521 Belmore Lane. Thank you. on Facebook Share The new road work looks great, however there is still construction debris on the road in front of my house and I would like to know when that will be removed. It has been there several weeks post completion and seems as though it has been forgotten. It is also a hazard for those walking the neighborhood as this block does not have sidewalks. Items include a pile of dirt, bags of sand, concrete blocks, and blinking hazard lights. I live at 6521 Belmore Lane. Thank you. on X (formerly Twitter) Share The new road work looks great, however there is still construction debris on the road in front of my house and I would like to know when that will be removed. It has been there several weeks post completion and seems as though it has been forgotten. It is also a hazard for those walking the neighborhood as this block does not have sidewalks. Items include a pile of dirt, bags of sand, concrete blocks, and blinking hazard lights. I live at 6521 Belmore Lane. Thank you. on Linkedin Email The new road work looks great, however there is still construction debris on the road in front of my house and I would like to know when that will be removed. It has been there several weeks post completion and seems as though it has been forgotten. It is also a hazard for those walking the neighborhood as this block does not have sidewalks. Items include a pile of dirt, bags of sand, concrete blocks, and blinking hazard lights. I live at 6521 Belmore Lane. Thank you. link

    The new road work looks great, however there is still construction debris on the road in front of my house and I would like to know when that will be removed. It has been there several weeks post completion and seems as though it has been forgotten. It is also a hazard for those walking the neighborhood as this block does not have sidewalks. Items include a pile of dirt, bags of sand, concrete blocks, and blinking hazard lights. I live at 6521 Belmore Lane. Thank you.

    Ginger asked 17 days ago

    The contractor will be doing clean up work on site over the next couple weeks.

  • Share I live on Jefferson Ave S. The sodded area of my lawn is full of mushrooms. It seems like the mushrooms are limited to the sodded area and I also see them in the sodded area of neighbors houses. Is this due to some material in the dirt that was put down under the sod? Will it be a recurring problem every year? Can anything be done about it? on Facebook Share I live on Jefferson Ave S. The sodded area of my lawn is full of mushrooms. It seems like the mushrooms are limited to the sodded area and I also see them in the sodded area of neighbors houses. Is this due to some material in the dirt that was put down under the sod? Will it be a recurring problem every year? Can anything be done about it? on X (formerly Twitter) Share I live on Jefferson Ave S. The sodded area of my lawn is full of mushrooms. It seems like the mushrooms are limited to the sodded area and I also see them in the sodded area of neighbors houses. Is this due to some material in the dirt that was put down under the sod? Will it be a recurring problem every year? Can anything be done about it? on Linkedin Email I live on Jefferson Ave S. The sodded area of my lawn is full of mushrooms. It seems like the mushrooms are limited to the sodded area and I also see them in the sodded area of neighbors houses. Is this due to some material in the dirt that was put down under the sod? Will it be a recurring problem every year? Can anything be done about it? link

    I live on Jefferson Ave S. The sodded area of my lawn is full of mushrooms. It seems like the mushrooms are limited to the sodded area and I also see them in the sodded area of neighbors houses. Is this due to some material in the dirt that was put down under the sod? Will it be a recurring problem every year? Can anything be done about it?

    mpb314 asked about 1 month ago

    Thank you for your question. The mushrooms are temporary.  They are a combination of organic topsoil, humidity and likely over-watering. The organic percentage in the topsoil is at 13 percent, which is within the specified organic range of 6-15 percent and good for growing.  Once the contractor watering period stops, the mushroom issue should cease.  

  • Share There has been minimal updates since the driveway aprons were completed on 6/10. Can homes that have gravel/blacktop use their driveways again, or do we need to continue to park on the street? on Facebook Share There has been minimal updates since the driveway aprons were completed on 6/10. Can homes that have gravel/blacktop use their driveways again, or do we need to continue to park on the street? on X (formerly Twitter) Share There has been minimal updates since the driveway aprons were completed on 6/10. Can homes that have gravel/blacktop use their driveways again, or do we need to continue to park on the street? on Linkedin Email There has been minimal updates since the driveway aprons were completed on 6/10. Can homes that have gravel/blacktop use their driveways again, or do we need to continue to park on the street? link

    There has been minimal updates since the driveway aprons were completed on 6/10. Can homes that have gravel/blacktop use their driveways again, or do we need to continue to park on the street?

    JDW asked 2 months ago

    Driveway aprons for asphalt driveways that were poured on 6/5 have already been ramped in as of last night. This includes properties on the south block of Harrison Ave, Tyler Ave, south side of Belmore Ln, and Tyler Ct. Properties that are ramped in are free to use their driveways. Properties with concrete driveways must continue to park on the street for 5 days after the pour on 6/9. 

    Driveways aprons for asphalt driveways that were poured on 6/8 are still curing. This includes properties on the north block of Harrison Ave and north side of Belmore Ln. Those properties must continue to park on the street to allow the concrete to cure for 5 days. Once the concrete is cured the asphalt driveways will be ramped in and are free to use their driveway. Concrete driveways are expected to be poured later this week as weather allows.

  • Share Why are there road construction signs either sideways or laying down for more than a month on the cemetery property making maintaining the cemetery grounds a pain in the arse on Facebook Share Why are there road construction signs either sideways or laying down for more than a month on the cemetery property making maintaining the cemetery grounds a pain in the arse on X (formerly Twitter) Share Why are there road construction signs either sideways or laying down for more than a month on the cemetery property making maintaining the cemetery grounds a pain in the arse on Linkedin Email Why are there road construction signs either sideways or laying down for more than a month on the cemetery property making maintaining the cemetery grounds a pain in the arse link

    Why are there road construction signs either sideways or laying down for more than a month on the cemetery property making maintaining the cemetery grounds a pain in the arse

    fred asked 2 months ago

    Thank you for your question. Please reach out to Chris Moore if the signs are laying down and he will coordinate with the contractor to ensure they are upright.  

  • Share When will we know if our sod is being replaced? Based on majority of the sod being installed in mid to late October 2025 the contractors were not watering it for 60 days and the city was unable to inspect it after 60 days to verify the install on Facebook Share When will we know if our sod is being replaced? Based on majority of the sod being installed in mid to late October 2025 the contractors were not watering it for 60 days and the city was unable to inspect it after 60 days to verify the install on X (formerly Twitter) Share When will we know if our sod is being replaced? Based on majority of the sod being installed in mid to late October 2025 the contractors were not watering it for 60 days and the city was unable to inspect it after 60 days to verify the install on Linkedin Email When will we know if our sod is being replaced? Based on majority of the sod being installed in mid to late October 2025 the contractors were not watering it for 60 days and the city was unable to inspect it after 60 days to verify the install link

    When will we know if our sod is being replaced? Based on majority of the sod being installed in mid to late October 2025 the contractors were not watering it for 60 days and the city was unable to inspect it after 60 days to verify the install

    BenSwen asked 4 months ago

    Sod watering is scheduled to resume some time during the week of 4/27. We will inspect the sod and make replacements if necessary. Once this process is complete, residents will get a letter in the mail saying the sod warranty period has concluded.

  • Share Since the streets east of Van Buren Avenue will not begin until spring 2026, how will this affect the preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements? on Facebook Share Since the streets east of Van Buren Avenue will not begin until spring 2026, how will this affect the preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements? on X (formerly Twitter) Share Since the streets east of Van Buren Avenue will not begin until spring 2026, how will this affect the preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements? on Linkedin Email Since the streets east of Van Buren Avenue will not begin until spring 2026, how will this affect the preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements? link

    Since the streets east of Van Buren Avenue will not begin until spring 2026, how will this affect the preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements?

    Patrice N asked 11 months ago

    Thank you for your question.  No changes to the assessment amount due to the project completion date extending to 2026.  At this point, we're still anticipating a final assessment less than $8,600 per REU. 

  • Share I’m curious as to why this project has required so much tearing up of the street repeatedly after parts of the project have been completed. I live at 301 Monroe Ave. S. and have witnessed multiple crews digging in the same place multiple times. I understand the complexity and . disregard of time and resources is frustrating to witness. Now after concert and asphalt have been poired there’s talk that the gutters need to be ripped out because a valve was put in the wrong place. This shows me that this project has not been managed well and that communication between different companies is not taking place. Given that this is not a project that anybody on my block asked for I’m very disappointed and fear that the work being done is not going to be high-quality and last very long. That I have no voice in something I will be paying for is not encouraging. I would approach a call from someone that will assure the work being done (and redone) will be of high lasting quality . on Facebook Share I’m curious as to why this project has required so much tearing up of the street repeatedly after parts of the project have been completed. I live at 301 Monroe Ave. S. and have witnessed multiple crews digging in the same place multiple times. I understand the complexity and . disregard of time and resources is frustrating to witness. Now after concert and asphalt have been poired there’s talk that the gutters need to be ripped out because a valve was put in the wrong place. This shows me that this project has not been managed well and that communication between different companies is not taking place. Given that this is not a project that anybody on my block asked for I’m very disappointed and fear that the work being done is not going to be high-quality and last very long. That I have no voice in something I will be paying for is not encouraging. I would approach a call from someone that will assure the work being done (and redone) will be of high lasting quality . on X (formerly Twitter) Share I’m curious as to why this project has required so much tearing up of the street repeatedly after parts of the project have been completed. I live at 301 Monroe Ave. S. and have witnessed multiple crews digging in the same place multiple times. I understand the complexity and . disregard of time and resources is frustrating to witness. Now after concert and asphalt have been poired there’s talk that the gutters need to be ripped out because a valve was put in the wrong place. This shows me that this project has not been managed well and that communication between different companies is not taking place. Given that this is not a project that anybody on my block asked for I’m very disappointed and fear that the work being done is not going to be high-quality and last very long. That I have no voice in something I will be paying for is not encouraging. I would approach a call from someone that will assure the work being done (and redone) will be of high lasting quality . on Linkedin Email I’m curious as to why this project has required so much tearing up of the street repeatedly after parts of the project have been completed. I live at 301 Monroe Ave. S. and have witnessed multiple crews digging in the same place multiple times. I understand the complexity and . disregard of time and resources is frustrating to witness. Now after concert and asphalt have been poired there’s talk that the gutters need to be ripped out because a valve was put in the wrong place. This shows me that this project has not been managed well and that communication between different companies is not taking place. Given that this is not a project that anybody on my block asked for I’m very disappointed and fear that the work being done is not going to be high-quality and last very long. That I have no voice in something I will be paying for is not encouraging. I would approach a call from someone that will assure the work being done (and redone) will be of high lasting quality . link

    I’m curious as to why this project has required so much tearing up of the street repeatedly after parts of the project have been completed. I live at 301 Monroe Ave. S. and have witnessed multiple crews digging in the same place multiple times. I understand the complexity and . disregard of time and resources is frustrating to witness. Now after concert and asphalt have been poired there’s talk that the gutters need to be ripped out because a valve was put in the wrong place. This shows me that this project has not been managed well and that communication between different companies is not taking place. Given that this is not a project that anybody on my block asked for I’m very disappointed and fear that the work being done is not going to be high-quality and last very long. That I have no voice in something I will be paying for is not encouraging. I would approach a call from someone that will assure the work being done (and redone) will be of high lasting quality .

    Jake K asked 11 months ago

    It can look like crews are digging in the same spot over and over, but each visit usually has a different purpose. One subcontractor might replace a watermain, another subcontractor comes back to connect water services, and later the street contractor re-opens the area to finish the road base. It may seem repetitive, but that sequence is normal — it allows the appropriate contractor to do each part of the job sequence, which ultimately leads to higher-quality, longer-lasting results. City staff is thoroughly inspecting the project and has no concerns about poor quality workmanship.  

     

    If you’d like more details, feel free to call us. Thank you.

  • Share The water is being done on Tyler court this year, are you also going to do the water on Harrison Ave and Tyler this year? on Facebook Share The water is being done on Tyler court this year, are you also going to do the water on Harrison Ave and Tyler this year? on X (formerly Twitter) Share The water is being done on Tyler court this year, are you also going to do the water on Harrison Ave and Tyler this year? on Linkedin Email The water is being done on Tyler court this year, are you also going to do the water on Harrison Ave and Tyler this year? link

    The water is being done on Tyler court this year, are you also going to do the water on Harrison Ave and Tyler this year?

    tfrandrup asked 11 months ago

    Thank you for your question. See our September 5 Fall Progress update for our current thoughts on this.

  • Share When will these huge dump trucks quit rolling both ways down my street Adams Avenue? They are damaging and dangerous on Facebook Share When will these huge dump trucks quit rolling both ways down my street Adams Avenue? They are damaging and dangerous on X (formerly Twitter) Share When will these huge dump trucks quit rolling both ways down my street Adams Avenue? They are damaging and dangerous on Linkedin Email When will these huge dump trucks quit rolling both ways down my street Adams Avenue? They are damaging and dangerous link

    When will these huge dump trucks quit rolling both ways down my street Adams Avenue? They are damaging and dangerous

    Larkin asked 12 months ago

    Thank you for your question.  Utility reconstruction work is occurring on Washington Avenue, therefore trucking routes will spill onto other streets for the next couple of weeks. 

    As noted in our weekly Better Together Edina posts, vehicles cannot be parked on the street during construction.  There is temporary parking allowed on Maloney Avenue.  If you need clarification or additional details, please reach out to the site inspector Brandon Freeman

  • Share Can you please clarify the following update provided on 7/11 for phase 1; "Asphalt driveways will be replaced at a later date." ? on Facebook Share Can you please clarify the following update provided on 7/11 for phase 1; "Asphalt driveways will be replaced at a later date." ? on X (formerly Twitter) Share Can you please clarify the following update provided on 7/11 for phase 1; "Asphalt driveways will be replaced at a later date." ? on Linkedin Email Can you please clarify the following update provided on 7/11 for phase 1; "Asphalt driveways will be replaced at a later date." ? link

    Can you please clarify the following update provided on 7/11 for phase 1; "Asphalt driveways will be replaced at a later date." ?

    CRV_05 asked about 1 year ago

    Thank you for your question.   Asphalt driveways are scheduled to be permanently restored sometime during the week of 7/21.   Temporary restoration with gravel will occur at the end of the day on Wednesday, 7/16.  

     Asphalt driveway work must occur after the roadway asphalt is complete and is a different paving machine than the roadway machine.   

Page last updated: 24 Jul 2026, 01:36 PM