Presidents A & B Neighborhood Roadway Reconstruction

Share Presidents A & B Neighborhood Roadway Reconstruction on Facebook Share Presidents A & B Neighborhood Roadway Reconstruction on Twitter Share Presidents A & B Neighborhood Roadway Reconstruction on Linkedin Email Presidents A & B Neighborhood Roadway Reconstruction link
Map showing the Presidents neighborhood and the project limit boundaries.

Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2025 construction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete reconstruction of two alleys west of Madison Avenue,
  • Complete replacement of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Proposed construction of multi-modal facilities along:
    • Monroe Avenue (5' sidewalk)
    • Belmore Lane (8' shared use path)
    • Washington Avenue (8' shared use path)
  • The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
  • A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
  • An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
  • If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.

Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2025 construction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete reconstruction of two alleys west of Madison Avenue,
  • Complete replacement of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Proposed construction of multi-modal facilities along:
    • Monroe Avenue (5' sidewalk)
    • Belmore Lane (8' shared use path)
    • Washington Avenue (8' shared use path)
  • The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
  • A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
  • An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
  • If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
  • Construction Update - 5/15/2026

    Share Construction Update - 5/15/2026 on Facebook Share Construction Update - 5/15/2026 on Twitter Share Construction Update - 5/15/2026 on Linkedin Email Construction Update - 5/15/2026 link

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Sump drain installation will continue into the week of 5/18.
    • Roadway excavation and soil corrections are scheduled to begin the week of 5/18.
    • The watermain and storm sewer related improvements are complete.
    • Check your front door daily for notification of temporary driveway access.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Remaining sod and sod replacement is complete.
    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Sump drain installation will continue into the week of 5/18.
    • Roadway excavation and soil corrections are scheduled to begin the week of 5/18.
    • The watermain and storm sewer related improvements are complete.
    • Check your front door daily for notification of temporary driveway access.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Remaining sod and sod replacement is complete.
    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
  • Construction Update - 5/8/2026

    Share Construction Update - 5/8/2026 on Facebook Share Construction Update - 5/8/2026 on Twitter Share Construction Update - 5/8/2026 on Linkedin Email Construction Update - 5/8/2026 link

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Water service replacement and storm sewer installation is scheduled to be completed the week of 5/11.
    • Sump drain installation is scheduled to begin the week of 5/11.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Remaining sod and sod replacement is expected to be installed the week of 5/11.
    • Sod watering has resumed. Residents will receive a letter in the mail when the sod watering period has concluded.

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Water service replacement and storm sewer installation is scheduled to be completed the week of 5/11.
    • Sump drain installation is scheduled to begin the week of 5/11.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Remaining sod and sod replacement is expected to be installed the week of 5/11.
    • Sod watering has resumed. Residents will receive a letter in the mail when the sod watering period has concluded.
  • Construction Update - 5/1/2026

    Share Construction Update - 5/1/2026 on Facebook Share Construction Update - 5/1/2026 on Twitter Share Construction Update - 5/1/2026 on Linkedin Email Construction Update - 5/1/2026 link

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Watermain installation is scheduled to be complete the week of 5/4.
    • Water service replacement is expected to begin on Harrison Ave the week of 5/4.
    • Storm sewer installation is scheduled to begin the week of 5/4.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Sod watering has resumed. Residents will receive a letter in the mail when the sod watering period has concluded and replacement sod has been installed.
    • Replacement of landscaping, retaining walls, and trees is complete. If you have any outstanding issues, please reach out to project manager Chris Moore.

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Watermain installation is scheduled to be complete the week of 5/4.
    • Water service replacement is expected to begin on Harrison Ave the week of 5/4.
    • Storm sewer installation is scheduled to begin the week of 5/4.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Sod watering has resumed. Residents will receive a letter in the mail when the sod watering period has concluded and replacement sod has been installed.
    • Replacement of landscaping, retaining walls, and trees is complete. If you have any outstanding issues, please reach out to project manager Chris Moore.
  • Construction Update - 4/24/2026

    Share Construction Update - 4/24/2026 on Facebook Share Construction Update - 4/24/2026 on Twitter Share Construction Update - 4/24/2026 on Linkedin Email Construction Update - 4/24/2026 link

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Watermain installation is scheduled for the week of 4/27.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Please park on the street if you have an alley. Alley access will be limited due to restoration work.
    • Retaining wall installation is ongoing and is scheduled to be completed by mid July.
    • Replacement of landscaping and trees is ongoing and is scheduled to be completed by mid July.

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Watermain installation is scheduled for the week of 4/27.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Please park on the street if you have an alley. Alley access will be limited due to restoration work.
    • Retaining wall installation is ongoing and is scheduled to be completed by mid July.
    • Replacement of landscaping and trees is ongoing and is scheduled to be completed by mid July.
  • Construction Update – 4/17/2026

    Share Construction Update – 4/17/2026 on Facebook Share Construction Update – 4/17/2026 on Twitter Share Construction Update – 4/17/2026 on Linkedin Email Construction Update – 4/17/2026 link

    Project Area

    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • The roads are scheduled to be reclaimed on 4/20. Reclaiming is the process of grinding the existing asphalt into a gravel base.
    • Removals including curb and gutter, driveways, and landscaping are expected to begin the week of 4/20.
    • Temporary watermain setup will continue into the week of 4/20.
      • The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Retaining wall installation is ongoing and is scheduled to be completed by mid July.
    • Replacement of landscaping and trees is ongoing and is scheduled to be completed by mid July.


    Project Area

    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • The roads are scheduled to be reclaimed on 4/20. Reclaiming is the process of grinding the existing asphalt into a gravel base.
    • Removals including curb and gutter, driveways, and landscaping are expected to begin the week of 4/20.
    • Temporary watermain setup will continue into the week of 4/20.
      • The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Retaining wall installation is ongoing and is scheduled to be completed by mid July.
    • Replacement of landscaping and trees is ongoing and is scheduled to be completed by mid July.


  • Construction Update - 4/10/26

    Share Construction Update - 4/10/26 on Facebook Share Construction Update - 4/10/26 on Twitter Share Construction Update - 4/10/26 on Linkedin Email Construction Update - 4/10/26 link

    Project Area

    Phase 4

    • Vehicles cannot be parked on the street during construction.
    • Temporary watermain setup will continue into the week of 4/13.
    • The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.

    Phases 1, 2, 3

    • Retaining wall installation is ongoing and is scheduled to be completed by mid July.
    • Replacement of landscaping and trees is ongoing and is scheduled to be completed by mid July.

    Project Area

    Phase 4

    • Vehicles cannot be parked on the street during construction.
    • Temporary watermain setup will continue into the week of 4/13.
    • The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.

    Phases 1, 2, 3

    • Retaining wall installation is ongoing and is scheduled to be completed by mid July.
    • Replacement of landscaping and trees is ongoing and is scheduled to be completed by mid July.
  • Construction Update - 3/30/26

    Share Construction Update - 3/30/26 on Facebook Share Construction Update - 3/30/26 on Twitter Share Construction Update - 3/30/26 on Linkedin Email Construction Update - 3/30/26 link
    supporting image

    Construction is scheduled to resume during the week of 3/30 and be substantially complete by mid-July. Chris Moore is the project manager for the remainder of the project. Please contact him at 952-826-0444 or CMoore@EdinaMN.gov with questions or concerns. You may also visit with him onsite.

    Project Area

    Phase 4

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • Setup of temporary watermain will begin in preparation for watermain improvements the week of 3/30.

    Phases 1, 2, 3

    • Retaining wall installation is scheduled to be completed by mid July.
    • The landscape contractor will finish replacing landscaping and trees by mid July.

    Construction is scheduled to resume during the week of 3/30 and be substantially complete by mid-July. Chris Moore is the project manager for the remainder of the project. Please contact him at 952-826-0444 or CMoore@EdinaMN.gov with questions or concerns. You may also visit with him onsite.

    Project Area

    Phase 4

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • Setup of temporary watermain will begin in preparation for watermain improvements the week of 3/30.

    Phases 1, 2, 3

    • Retaining wall installation is scheduled to be completed by mid July.
    • The landscape contractor will finish replacing landscaping and trees by mid July.
  • Sidewalk Snow Removal

    Share Sidewalk Snow Removal on Facebook Share Sidewalk Snow Removal on Twitter Share Sidewalk Snow Removal on Linkedin Email Sidewalk Snow Removal link
    supporting image

    Property owners are responsible for snow removal on the sidewalks adjoining their property as shown here.


    To keep pedestrians safe, sidewalks must be cleared of all ice and snow during the winter. According to Edina City Code 1200.03, "All snow and ice shall be removed from a sidewalk by the owner of the property adjoining the sidewalk within 48 hours of the cessation of the precipitation." This means property owners must clear sidewalks of all snow or ice within two days of the end of a snowfall. Any snow removed from walkways, driveways or sidewalks must remain on the property. Snow cannot be plowed into City streets or onto a neighboring property.


    If snow and ice are not removed within seven days after receiving a written notice from the City, residents may be charged for the cost of removal by the City.


    Property owners are responsible for snow removal on the sidewalks adjoining their property as shown here.


    To keep pedestrians safe, sidewalks must be cleared of all ice and snow during the winter. According to Edina City Code 1200.03, "All snow and ice shall be removed from a sidewalk by the owner of the property adjoining the sidewalk within 48 hours of the cessation of the precipitation." This means property owners must clear sidewalks of all snow or ice within two days of the end of a snowfall. Any snow removed from walkways, driveways or sidewalks must remain on the property. Snow cannot be plowed into City streets or onto a neighboring property.


    If snow and ice are not removed within seven days after receiving a written notice from the City, residents may be charged for the cost of removal by the City.


  • Construction Update - 11/28/2025

    Share Construction Update - 11/28/2025 on Facebook Share Construction Update - 11/28/2025 on Twitter Share Construction Update - 11/28/2025 on Linkedin Email Construction Update - 11/28/2025 link

    Construction Update – 11/28/2025


    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Sanitary Sewer Lining – Phases 1 and 2

    Visu-Sewer will be lining the City’s sanitary sewer main via access through manholes in the street. The lining is scheduled to begin in the project area on Monday, 12/1 and is anticipated to be complete by late December.

    • Limiting major water use is required to avoid a sewer backup.
    • Avoid running your washing machine or dishwasher during this 8-12 hour period of work or you risk your sewer backing up.
    • Pungent odors from the lining process are common.
    • To prevent odors in your home, pour a gallon of water into floor drains and any infrequently used sinks.
    • Check your front door daily for details and notice of this work occurring on your street.
    • The notice will include information on the process, and approximate length of time your water usage should be minimized.
    • See example door notice here.


    Phases 1, 2, 3

    • Retaining wall installation is ongoing as long as weather permits.
    • Landscape restoration is complete for the season. Any remaining work will be completed when the project resumes in the spring of 2026.


    Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue

    The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.


    Construction Update – 11/28/2025


    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Sanitary Sewer Lining – Phases 1 and 2

    Visu-Sewer will be lining the City’s sanitary sewer main via access through manholes in the street. The lining is scheduled to begin in the project area on Monday, 12/1 and is anticipated to be complete by late December.

    • Limiting major water use is required to avoid a sewer backup.
    • Avoid running your washing machine or dishwasher during this 8-12 hour period of work or you risk your sewer backing up.
    • Pungent odors from the lining process are common.
    • To prevent odors in your home, pour a gallon of water into floor drains and any infrequently used sinks.
    • Check your front door daily for details and notice of this work occurring on your street.
    • The notice will include information on the process, and approximate length of time your water usage should be minimized.
    • See example door notice here.


    Phases 1, 2, 3

    • Retaining wall installation is ongoing as long as weather permits.
    • Landscape restoration is complete for the season. Any remaining work will be completed when the project resumes in the spring of 2026.


    Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue

    The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.


  • Construction Update – 11/20/2025

    Share Construction Update – 11/20/2025 on Facebook Share Construction Update – 11/20/2025 on Twitter Share Construction Update – 11/20/2025 on Linkedin Email Construction Update – 11/20/2025 link

    Construction Update – 11/21/2025


    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Sanitary Sewer Lining – Phases 1 and 2

    Visu-Sewer will be lining the City’s sanitary sewer main via access through manholes in the street. The lining is scheduled to begin in the project area on Monday, 12/1 and is anticipated to be complete by late December.

    • Limiting major water use is required to avoid a sewer backup.
    • Avoid running your washing machine or dishwasher during this 8-12 hour period of work or you risk your sewer backing up.
    • Pungent odors from the lining process are common.
    • To prevent odors in your home, pour a gallon of water into floor drains and any infrequently used sinks.
    • Check your front door daily for details and notice of this work occurring on your street.
    • The notice will include information on the process, and approximate length of time your water usage should be minimized.
    • See example door notice here.


    Phases 1, 2, 3

    • Temporary pavement striping will be placed on Washington Ave.
    • Retaining wall installation is scheduled to be completed by late November.
    • The landscape contractor will be replacing impacted landscaping as long as weather permits. Any remaining work will be completed when the project resumes in the spring of 2026.
    • The final layer of asphalt is complete.
    • Street sign installation is complete.


    Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue

    The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.


    Construction Update – 11/21/2025


    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Sanitary Sewer Lining – Phases 1 and 2

    Visu-Sewer will be lining the City’s sanitary sewer main via access through manholes in the street. The lining is scheduled to begin in the project area on Monday, 12/1 and is anticipated to be complete by late December.

    • Limiting major water use is required to avoid a sewer backup.
    • Avoid running your washing machine or dishwasher during this 8-12 hour period of work or you risk your sewer backing up.
    • Pungent odors from the lining process are common.
    • To prevent odors in your home, pour a gallon of water into floor drains and any infrequently used sinks.
    • Check your front door daily for details and notice of this work occurring on your street.
    • The notice will include information on the process, and approximate length of time your water usage should be minimized.
    • See example door notice here.


    Phases 1, 2, 3

    • Temporary pavement striping will be placed on Washington Ave.
    • Retaining wall installation is scheduled to be completed by late November.
    • The landscape contractor will be replacing impacted landscaping as long as weather permits. Any remaining work will be completed when the project resumes in the spring of 2026.
    • The final layer of asphalt is complete.
    • Street sign installation is complete.


    Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue

    The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.