Presidents A & B Neighborhood Roadway Reconstruction

Share Presidents A & B Neighborhood Roadway Reconstruction on Facebook Share Presidents A & B Neighborhood Roadway Reconstruction on X (formerly Twitter) Share Presidents A & B Neighborhood Roadway Reconstruction on Linkedin Email Presidents A & B Neighborhood Roadway Reconstruction link
Map showing the Presidents neighborhood and the project limit boundaries.

Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2025 construction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete reconstruction of two alleys west of Madison Avenue,
  • Complete replacement of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Proposed construction of multi-modal facilities along:
    • Monroe Avenue (5' sidewalk)
    • Belmore Lane (8' shared use path)
    • Washington Avenue (8' shared use path)
  • The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
  • A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
  • An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
  • If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.

Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2025 construction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete reconstruction of two alleys west of Madison Avenue,
  • Complete replacement of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Proposed construction of multi-modal facilities along:
    • Monroe Avenue (5' sidewalk)
    • Belmore Lane (8' shared use path)
    • Washington Avenue (8' shared use path)
  • The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
  • A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
  • An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
  • If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
  • Construction Update - 6/26/2026

    Share Construction Update - 6/26/2026 on Facebook Share Construction Update - 6/26/2026 on X (formerly Twitter) Share Construction Update - 6/26/2026 on Linkedin Email Construction Update - 6/26/2026 link

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until early July. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction working hours.
    • Sod installation, irrigation repairs and replacement of impacted landscaping is scheduled to begin during the week of 6/29.
    • Paving the final layer of asphalt is tentatively scheduled for Monday, 7/6.
    • Check your front door daily for notifications.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Any outstanding landscaping and sod issues are scheduled to occur the week of 6/29.
    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until early July. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction working hours.
    • Sod installation, irrigation repairs and replacement of impacted landscaping is scheduled to begin during the week of 6/29.
    • Paving the final layer of asphalt is tentatively scheduled for Monday, 7/6.
    • Check your front door daily for notifications.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Any outstanding landscaping and sod issues are scheduled to occur the week of 6/29.
    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
  • Construction Update - 6/19/2026

    Share Construction Update - 6/19/2026 on Facebook Share Construction Update - 6/19/2026 on X (formerly Twitter) Share Construction Update - 6/19/2026 on Linkedin Email Construction Update - 6/19/2026 link

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until late June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction working hours.
    • Asphalt driveway paving is scheduled to occur the week of 6/22.
    • Concrete sidewalk installation on Belmore Ln is scheduled to occur the week of 6/22.
    • Topsoil installation is scheduled to begin the week of 6/22.
    • Check your front door daily for notification of temporary driveway access loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until late June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction working hours.
    • Asphalt driveway paving is scheduled to occur the week of 6/22.
    • Concrete sidewalk installation on Belmore Ln is scheduled to occur the week of 6/22.
    • Topsoil installation is scheduled to begin the week of 6/22.
    • Check your front door daily for notification of temporary driveway access loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
  • Construction Update - 6/12/2026

    Share Construction Update - 6/12/2026 on Facebook Share Construction Update - 6/12/2026 on X (formerly Twitter) Share Construction Update - 6/12/2026 on Linkedin Email Construction Update - 6/12/2026 link

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until late June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction working hours.
    • Roadway grading in preparation for the first layer of paving will occur during the week of 6/15.
    • Paving of the first layer of asphalt on the streets is scheduled to occur late during the week of 6/15.
    • Asphalt driveway paving is scheduled to occur soon after the first layer of asphalt street paving occurs, likely during the week of 6/15.
    • Check your front door daily for notification of temporary driveway access loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until late June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction working hours.
    • Roadway grading in preparation for the first layer of paving will occur during the week of 6/15.
    • Paving of the first layer of asphalt on the streets is scheduled to occur late during the week of 6/15.
    • Asphalt driveway paving is scheduled to occur soon after the first layer of asphalt street paving occurs, likely during the week of 6/15.
    • Check your front door daily for notification of temporary driveway access loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
  • Construction Update - 6/5/2026

    Share Construction Update - 6/5/2026 on Facebook Share Construction Update - 6/5/2026 on X (formerly Twitter) Share Construction Update - 6/5/2026 on Linkedin Email Construction Update - 6/5/2026 link

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until late June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Concrete curb and driveway apron installation will continue into the week of 6/8.
    • Concrete driveway installation is scheduled to begin during the week of 6/8.
    • Following concrete curing, roadway grading in preparation for the first layer of paving will occur.
    • Check your front door daily for notification of temporary driveway access loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until late June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Concrete curb and driveway apron installation will continue into the week of 6/8.
    • Concrete driveway installation is scheduled to begin during the week of 6/8.
    • Following concrete curing, roadway grading in preparation for the first layer of paving will occur.
    • Check your front door daily for notification of temporary driveway access loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
  • Construction Update - 5/29/2026

    Share Construction Update - 5/29/2026 on Facebook Share Construction Update - 5/29/2026 on X (formerly Twitter) Share Construction Update - 5/29/2026 on Linkedin Email Construction Update - 5/29/2026 link

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Work will occur on Saturday, 5/30.
    • Roadway excavation and soil corrections will continue into the week of 6/1.
    • Concrete curb and driveway apron installation is scheduled to begin late during the week of 6/1.
    • Check your front door daily for notification of temporary driveway access loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Please check your front door daily the week of 6/1 for notifications of driveway access loss due to concrete warranty work.
    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Work will occur on Saturday, 5/30.
    • Roadway excavation and soil corrections will continue into the week of 6/1.
    • Concrete curb and driveway apron installation is scheduled to begin late during the week of 6/1.
    • Check your front door daily for notification of temporary driveway access loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Please check your front door daily the week of 6/1 for notifications of driveway access loss due to concrete warranty work.
    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
  • Construction Update - 5/22/2026

    Share Construction Update - 5/22/2026 on Facebook Share Construction Update - 5/22/2026 on X (formerly Twitter) Share Construction Update - 5/22/2026 on Linkedin Email Construction Update - 5/22/2026 link

    Project Area

    • No work will occur on Memorial Day, Monday, 5/25.
    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Roadway excavation and soil corrections will continue through the week of 5/26.
    • Concrete curb and driveway apron installation is scheduled to begin the week of 6/2.
    • Sump drain installation is complete.
    • Check your front door daily for notification of temporary driveway access.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Please check your front door daily the week of 5/26 for notifications of driveway access loss due to concrete warranty work.
    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.

    Project Area

    • No work will occur on Memorial Day, Monday, 5/25.
    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Roadway excavation and soil corrections will continue through the week of 5/26.
    • Concrete curb and driveway apron installation is scheduled to begin the week of 6/2.
    • Sump drain installation is complete.
    • Check your front door daily for notification of temporary driveway access.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Please check your front door daily the week of 5/26 for notifications of driveway access loss due to concrete warranty work.
    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
  • Construction Update - 5/15/2026

    Share Construction Update - 5/15/2026 on Facebook Share Construction Update - 5/15/2026 on X (formerly Twitter) Share Construction Update - 5/15/2026 on Linkedin Email Construction Update - 5/15/2026 link

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Sump drain installation will continue into the week of 5/18.
    • Roadway excavation and soil corrections are scheduled to begin the week of 5/18.
    • The watermain and storm sewer related improvements are complete.
    • Check your front door daily for notification of temporary driveway access.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Remaining sod and sod replacement is complete.
    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Sump drain installation will continue into the week of 5/18.
    • Roadway excavation and soil corrections are scheduled to begin the week of 5/18.
    • The watermain and storm sewer related improvements are complete.
    • Check your front door daily for notification of temporary driveway access.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Remaining sod and sod replacement is complete.
    • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
  • Construction Update - 5/8/2026

    Share Construction Update - 5/8/2026 on Facebook Share Construction Update - 5/8/2026 on X (formerly Twitter) Share Construction Update - 5/8/2026 on Linkedin Email Construction Update - 5/8/2026 link

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Water service replacement and storm sewer installation is scheduled to be completed the week of 5/11.
    • Sump drain installation is scheduled to begin the week of 5/11.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Remaining sod and sod replacement is expected to be installed the week of 5/11.
    • Sod watering has resumed. Residents will receive a letter in the mail when the sod watering period has concluded.

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Water service replacement and storm sewer installation is scheduled to be completed the week of 5/11.
    • Sump drain installation is scheduled to begin the week of 5/11.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Remaining sod and sod replacement is expected to be installed the week of 5/11.
    • Sod watering has resumed. Residents will receive a letter in the mail when the sod watering period has concluded.
  • Construction Update - 5/1/2026

    Share Construction Update - 5/1/2026 on Facebook Share Construction Update - 5/1/2026 on X (formerly Twitter) Share Construction Update - 5/1/2026 on Linkedin Email Construction Update - 5/1/2026 link

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Watermain installation is scheduled to be complete the week of 5/4.
    • Water service replacement is expected to begin on Harrison Ave the week of 5/4.
    • Storm sewer installation is scheduled to begin the week of 5/4.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Sod watering has resumed. Residents will receive a letter in the mail when the sod watering period has concluded and replacement sod has been installed.
    • Replacement of landscaping, retaining walls, and trees is complete. If you have any outstanding issues, please reach out to project manager Chris Moore.

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Watermain installation is scheduled to be complete the week of 5/4.
    • Water service replacement is expected to begin on Harrison Ave the week of 5/4.
    • Storm sewer installation is scheduled to begin the week of 5/4.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Sod watering has resumed. Residents will receive a letter in the mail when the sod watering period has concluded and replacement sod has been installed.
    • Replacement of landscaping, retaining walls, and trees is complete. If you have any outstanding issues, please reach out to project manager Chris Moore.
  • Construction Update - 4/24/2026

    Share Construction Update - 4/24/2026 on Facebook Share Construction Update - 4/24/2026 on X (formerly Twitter) Share Construction Update - 4/24/2026 on Linkedin Email Construction Update - 4/24/2026 link

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Watermain installation is scheduled for the week of 4/27.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Please park on the street if you have an alley. Alley access will be limited due to restoration work.
    • Retaining wall installation is ongoing and is scheduled to be completed by mid July.
    • Replacement of landscaping and trees is ongoing and is scheduled to be completed by mid July.

    Project Area

    • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
    • See the construction phasing map.
    • All work dates below are weather permitting.


    Phase 4:

    • Vehicles cannot be parked on the street during construction.
    • Watermain installation is scheduled for the week of 4/27.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, 3

    • Please park on the street if you have an alley. Alley access will be limited due to restoration work.
    • Retaining wall installation is ongoing and is scheduled to be completed by mid July.
    • Replacement of landscaping and trees is ongoing and is scheduled to be completed by mid July.