Vernon Avenue & Highway 100 Interchange Project

Share Vernon Avenue & Highway 100 Interchange Project on Facebook Share Vernon Avenue & Highway 100 Interchange Project on Twitter Share Vernon Avenue & Highway 100 Interchange Project on Linkedin Email Vernon Avenue & Highway 100 Interchange Project link
Map of proposed improvements at Vernon Avenue and Highway 100, including two new bridges and a redesigned interchange.

The City of Edina partnering with Hennepin County in coordination with Minnesota Department of Transportation, is replacing the bridge over Highway 100 and the Vernon Avenue Bridge (County Road 158) over the Canadian Pacific (CP) Railroad. The overall project will also improve the intersections at Interlachen Boulevard, Gus Young Lane, Arcadia Avenue and the Highway 100 on- and off-ramps.


The size of the existing sidewalk and the lack of separation from heavy traffic make this street uncomfortable for many pedestrians, creating a significant barrier within the Grandview District. Additionally, the interchange with TH 100 is a complicated and redundant system of six unique access ramps that connect to four different streets within the district.

This project improves safety and mobility for all users and eliminates redundant access ramps.

Project goals

o Improve safety and mobility for all users

o Create new separated pedestrian routes

o Improve traffic operations

o Consolidate TH 100 access points

o Improve connectivity between residential and commercial areas of the district

o Replace Vernon Ave bridge meeting CP Rail clearance requirements

o Limit construction impacts to the public and create greater funding efficiency by combining city

and county projects

o Enhance economic viability with improved access


Changes to be made

Arcadia Avenue

  • Addition of 10-foot-wide sidewalk and ADA-compliant pedestrian ramps
  • New streetlights

Minnesota Highway 100

  • Removal of redundant on- and off ramps and the creation of a tight diamond interchange
  • New noise wall along northbound on-ramp

Interlachen Boulevard and Gus Young Lane

  • Addition of 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
  • New left turn lanes
  • New traffic signal with ADA-compliant audible crossings
  • New ADA-compliant entrance into Edina Liquor

Vernon Avenue and W. 50th St.

Two new bridges:

  1. New Vernon Avenue Bridge that is widened and raised to meet railroad height requirements
  2. New Highway 100 Bridge that creates space for the below improvements:
    • 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
    • Pedestrian refuge islands
    • New dual left-turn lanes in both east and west directions
    • New traffic signals with ADA-compliant audible crossings

The City of Edina partnering with Hennepin County in coordination with Minnesota Department of Transportation, is replacing the bridge over Highway 100 and the Vernon Avenue Bridge (County Road 158) over the Canadian Pacific (CP) Railroad. The overall project will also improve the intersections at Interlachen Boulevard, Gus Young Lane, Arcadia Avenue and the Highway 100 on- and off-ramps.


The size of the existing sidewalk and the lack of separation from heavy traffic make this street uncomfortable for many pedestrians, creating a significant barrier within the Grandview District. Additionally, the interchange with TH 100 is a complicated and redundant system of six unique access ramps that connect to four different streets within the district.

This project improves safety and mobility for all users and eliminates redundant access ramps.

Project goals

o Improve safety and mobility for all users

o Create new separated pedestrian routes

o Improve traffic operations

o Consolidate TH 100 access points

o Improve connectivity between residential and commercial areas of the district

o Replace Vernon Ave bridge meeting CP Rail clearance requirements

o Limit construction impacts to the public and create greater funding efficiency by combining city

and county projects

o Enhance economic viability with improved access


Changes to be made

Arcadia Avenue

  • Addition of 10-foot-wide sidewalk and ADA-compliant pedestrian ramps
  • New streetlights

Minnesota Highway 100

  • Removal of redundant on- and off ramps and the creation of a tight diamond interchange
  • New noise wall along northbound on-ramp

Interlachen Boulevard and Gus Young Lane

  • Addition of 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
  • New left turn lanes
  • New traffic signal with ADA-compliant audible crossings
  • New ADA-compliant entrance into Edina Liquor

Vernon Avenue and W. 50th St.

Two new bridges:

  1. New Vernon Avenue Bridge that is widened and raised to meet railroad height requirements
  2. New Highway 100 Bridge that creates space for the below improvements:
    • 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
    • Pedestrian refuge islands
    • New dual left-turn lanes in both east and west directions
    • New traffic signals with ADA-compliant audible crossings
  • April 28 2026 Update

    Share April 28 2026 Update on Facebook Share April 28 2026 Update on Twitter Share April 28 2026 Update on Linkedin Email April 28 2026 Update link

    The contractor intends to pour the Vernon Avenue bridge deck on Thursday, April 30. There are lots of things left to do after that. They need the deck to cure for a specified amount of time. When the deck is ready, pour the sidewalk, median, and concrete barriers on the bridge. Finish utility work on the west side of the bridge. Install railings, lights, and pavement markings on the bridge. Install gravel base materials between the bridge and street, place bituminous, traffic signals, pedestrian ramps, sidewalks, lights, and other misc. items. Lots of items left to complete prior to the road opening by the end of June. Thanks for the patience.

    The contractor intends to pour the Vernon Avenue bridge deck on Thursday, April 30. There are lots of things left to do after that. They need the deck to cure for a specified amount of time. When the deck is ready, pour the sidewalk, median, and concrete barriers on the bridge. Finish utility work on the west side of the bridge. Install railings, lights, and pavement markings on the bridge. Install gravel base materials between the bridge and street, place bituminous, traffic signals, pedestrian ramps, sidewalks, lights, and other misc. items. Lots of items left to complete prior to the road opening by the end of June. Thanks for the patience.

  • April 16, 2026 Project Update

    Share April 16, 2026 Project Update on Facebook Share April 16, 2026 Project Update on Twitter Share April 16, 2026 Project Update on Linkedin Email April 16, 2026 Project Update link

    Beginning next week, the contractor will close Gus Young Lane near the Grandview Liquor Store. This will provide them enough space to safety work on the west side of the railroad bridge. Gus Young Lane and the alley behind Walgreens will still be open. This traffic control will match the configuration from last fall. The contractor continues to place framing and rebar on the beams and intends to pour the concrete bridge deck late April. Vernon Avenue is still scheduled to open to traffic by the end of June. The ramp closures for the noise wall work along the northbound Highway 100 on-ramp are complete. Thanks for your continued patience.

    Beginning next week, the contractor will close Gus Young Lane near the Grandview Liquor Store. This will provide them enough space to safety work on the west side of the railroad bridge. Gus Young Lane and the alley behind Walgreens will still be open. This traffic control will match the configuration from last fall. The contractor continues to place framing and rebar on the beams and intends to pour the concrete bridge deck late April. Vernon Avenue is still scheduled to open to traffic by the end of June. The ramp closures for the noise wall work along the northbound Highway 100 on-ramp are complete. Thanks for your continued patience.

  • April 6, 2026 Update - Southbound 100 Offramp Closing

    Share April 6, 2026 Update - Southbound 100 Offramp Closing on Facebook Share April 6, 2026 Update - Southbound 100 Offramp Closing on Twitter Share April 6, 2026 Update - Southbound 100 Offramp Closing on Linkedin Email April 6, 2026 Update - Southbound 100 Offramp Closing link

    On April 7, the contractor will close the southbound offramp of Highway 100 at Vernon and 50th Street from 6 am until later afternoon. This will allow delivery of the new bridge beams for placement on the railroad bridge. The detour is the southbound Highway 100 offramp at Benton Avenue and the frontage road. Thanks

    On April 7, the contractor will close the southbound offramp of Highway 100 at Vernon and 50th Street from 6 am until later afternoon. This will allow delivery of the new bridge beams for placement on the railroad bridge. The detour is the southbound Highway 100 offramp at Benton Avenue and the frontage road. Thanks

  • March 31, 2026 Update

    Share March 31, 2026 Update on Facebook Share March 31, 2026 Update on Twitter Share March 31, 2026 Update on Linkedin Email March 31, 2026 Update link

    Due to the weather forecast, the noise wall along the northbound Highway 100 onramp from 50th Street will continue to have sporadic daily closures between 9 am and 4 pm until April 10. The contractor is scheduled to place beams on the railroad bridge on April 7. This will require westbound 50th Street to be detoured to Eden Avenue except traffic using the northbound Highway 100 onramp. This will be a one day operation. Starting April 20, Gus Young Lane will be closed until late June to create enough space for construction access for underground utility, bridge, and street construction. Other than the Gus Young closure, traffic routing will remain approximately the same. Thanks, Chad Millner.

    Due to the weather forecast, the noise wall along the northbound Highway 100 onramp from 50th Street will continue to have sporadic daily closures between 9 am and 4 pm until April 10. The contractor is scheduled to place beams on the railroad bridge on April 7. This will require westbound 50th Street to be detoured to Eden Avenue except traffic using the northbound Highway 100 onramp. This will be a one day operation. Starting April 20, Gus Young Lane will be closed until late June to create enough space for construction access for underground utility, bridge, and street construction. Other than the Gus Young closure, traffic routing will remain approximately the same. Thanks, Chad Millner.

  • March 20, 2026 Update: Construction Restarting Soon

    Share March 20, 2026 Update: Construction Restarting Soon on Facebook Share March 20, 2026 Update: Construction Restarting Soon on Twitter Share March 20, 2026 Update: Construction Restarting Soon on Linkedin Email March 20, 2026 Update: Construction Restarting Soon link

    The contractor has provided anticipated dates to restart major construction operations. There were no updates on installation of the traffic signals are Highway 100.

    • Week of April 6: Northbound on-ramp noise wall planking complete. Daily 9 am to 4 pm closures complete.
    • Week of April 6: Placing beams on the railroad bridge
    • Week of April 20: Close Gus Young Lane
    • Week of April 27: Pouring bridge deck
    • Weeks of June 22 / 29: Open Gus Young Ln and Vernon Ave to traffic

    Thanks

    The contractor has provided anticipated dates to restart major construction operations. There were no updates on installation of the traffic signals are Highway 100.

    • Week of April 6: Northbound on-ramp noise wall planking complete. Daily 9 am to 4 pm closures complete.
    • Week of April 6: Placing beams on the railroad bridge
    • Week of April 20: Close Gus Young Lane
    • Week of April 27: Pouring bridge deck
    • Weeks of June 22 / 29: Open Gus Young Ln and Vernon Ave to traffic

    Thanks

  • March 6, 2026 Update

    Share March 6, 2026 Update on Facebook Share March 6, 2026 Update on Twitter Share March 6, 2026 Update on Linkedin Email March 6, 2026 Update link

    Questions are coming in when the contractor will resume work on the bridge. Recall they stopped working over the winter due to costs. They are monitoring the weather to determine when they can resume operations. Once they submit an updated schedule, we will share that out. Thanks.

    Questions are coming in when the contractor will resume work on the bridge. Recall they stopped working over the winter due to costs. They are monitoring the weather to determine when they can resume operations. Once they submit an updated schedule, we will share that out. Thanks.

  • January 26, 2026 Update: Northbound Onramp

    Share January 26, 2026 Update: Northbound Onramp on Facebook Share January 26, 2026 Update: Northbound Onramp on Twitter Share January 26, 2026 Update: Northbound Onramp on Linkedin Email January 26, 2026 Update: Northbound Onramp link

    Northbound Ramp Closure Update: The noise wall planking has been delivered. With the cold weather forecast, the contractor has again delayed starting installation. Work will start on Monday, February 2. This is different than the reported January 21 and January 26 dates. The contractor will start installing the noise wall planking on the northbound Highway 100 onramp from 50th Street. Temporary closures of the ramp will be required to create enough safe working space. The work will last 3 to 4 weeks. Closures of the ramp will be temporary between 9 am and 4 pm on weekdays. The detour route for northbound Highway 100 is the east frontage road to the northbound onramp at Benton Avenue. Thanks

    Northbound Ramp Closure Update: The noise wall planking has been delivered. With the cold weather forecast, the contractor has again delayed starting installation. Work will start on Monday, February 2. This is different than the reported January 21 and January 26 dates. The contractor will start installing the noise wall planking on the northbound Highway 100 onramp from 50th Street. Temporary closures of the ramp will be required to create enough safe working space. The work will last 3 to 4 weeks. Closures of the ramp will be temporary between 9 am and 4 pm on weekdays. The detour route for northbound Highway 100 is the east frontage road to the northbound onramp at Benton Avenue. Thanks

  • January 20, 2026 Update

    Share January 20, 2026 Update on Facebook Share January 20, 2026 Update on Twitter Share January 20, 2026 Update on Linkedin Email January 20, 2026 Update link

    Due to the forecasted, extreme cold weather, the contractor has decided to push the start date of the short term northbound Highway 100 on-ramp closures for noise wall plank installation to Monday, January 26. Thanks for the understanding.

    Due to the forecasted, extreme cold weather, the contractor has decided to push the start date of the short term northbound Highway 100 on-ramp closures for noise wall plank installation to Monday, January 26. Thanks for the understanding.

  • January 13, 2026 Update

    Share January 13, 2026 Update on Facebook Share January 13, 2026 Update on Twitter Share January 13, 2026 Update on Linkedin Email January 13, 2026 Update link

    The noise wall planking is scheduled for delivery late this week and early next week. The contractor will start installing the noise wall planking on the northbound Highway 100 onramp from 50th Street. Temporary closures of the ramp will be required to create enough safe working space. Work will start on January 21. The work will last 3 to 4 weeks. Closures of the ramp will be temporary between 9 am and 4 pm on weekdays. The detour route for northbound Highway 100 is the east frontage road to the northbound onramp at Benton Avenue.

    The noise wall planking is scheduled for delivery late this week and early next week. The contractor will start installing the noise wall planking on the northbound Highway 100 onramp from 50th Street. Temporary closures of the ramp will be required to create enough safe working space. Work will start on January 21. The work will last 3 to 4 weeks. Closures of the ramp will be temporary between 9 am and 4 pm on weekdays. The detour route for northbound Highway 100 is the east frontage road to the northbound onramp at Benton Avenue.

  • December 11, 2025 Update

    Share December 11, 2025 Update on Facebook Share December 11, 2025 Update on Twitter Share December 11, 2025 Update on Linkedin Email December 11, 2025 Update link
    supporting image

    Great News, the intersection of Interlachen Blvd, Vernon Ave and Gus Young Lane reopened to traffic on this week with the use of temporary signals. The temporary signals will be operating until the contractor resumes work in the spring. The exact date will be determined based on weather. The traffic signals and power to light the signals on the Highway 100 Bridge are tentatively scheduled for mid to late January. The noise wall planking is scheduled for delivery early January. After delivery, the contractor will provide an installation plan for us to share. There may be a couple northbound Highway 100 onramp closures next week to straighten noise wall posts. There is not enough room for the contractor to complete this work with the ramp open. It would be a temporary closure between 10 am – 2 pm over two days. Access to northbound Highway 100 would be from Benton Avenue for those durations. Please continue to visit https://www.bettertogetheredina.org/vernon-hwy100 for project updates. Thank you for your patience.

    Great News, the intersection of Interlachen Blvd, Vernon Ave and Gus Young Lane reopened to traffic on this week with the use of temporary signals. The temporary signals will be operating until the contractor resumes work in the spring. The exact date will be determined based on weather. The traffic signals and power to light the signals on the Highway 100 Bridge are tentatively scheduled for mid to late January. The noise wall planking is scheduled for delivery early January. After delivery, the contractor will provide an installation plan for us to share. There may be a couple northbound Highway 100 onramp closures next week to straighten noise wall posts. There is not enough room for the contractor to complete this work with the ramp open. It would be a temporary closure between 10 am – 2 pm over two days. Access to northbound Highway 100 would be from Benton Avenue for those durations. Please continue to visit https://www.bettertogetheredina.org/vernon-hwy100 for project updates. Thank you for your patience.