Bristol & Mavelle Park/Lynmar Basin Stormwater Project
The Lynmar Basin is a low-lying, open space that currently briefly detains stormwater before it makes its way to Lake Edina and eventually Nine Mile Creek through storm sewer pipes. The location was identified as an opportunity to better manage stormwater as part of a larger effort to improve downstream water resources.
The retrofit project will better utilize the space to capture and clean more stormwater than it already does today. The existing dry pond area will be expanded and deepened to promote stormwater infiltration. The infiltration basin will be planted with native trees, shrubs, and forbs.
The project benefits include;
- Less polluted water entering Lake Edina and downstream water resources
- Reduced flooding in the South Cornelia neighborhood
- Enhanced natural resources, including improving pollinator habitat
- A portion of the space kept open for passive recreation, and a new walking path
This project is done in partnership with the Nine Mile Creek Watershed District.
The Lynmar Basin is a low-lying, open space that currently briefly detains stormwater before it makes its way to Lake Edina and eventually Nine Mile Creek through storm sewer pipes. The location was identified as an opportunity to better manage stormwater as part of a larger effort to improve downstream water resources.
The retrofit project will better utilize the space to capture and clean more stormwater than it already does today. The existing dry pond area will be expanded and deepened to promote stormwater infiltration. The infiltration basin will be planted with native trees, shrubs, and forbs.
The project benefits include;
- Less polluted water entering Lake Edina and downstream water resources
- Reduced flooding in the South Cornelia neighborhood
- Enhanced natural resources, including improving pollinator habitat
- A portion of the space kept open for passive recreation, and a new walking path
This project is done in partnership with the Nine Mile Creek Watershed District.
-
July Blooms
Share July Blooms on Facebook Share July Blooms on Twitter Share July Blooms on Linkedin Email July Blooms link -
Native blooms abound
Share Native blooms abound on Facebook Share Native blooms abound on Twitter Share Native blooms abound on Linkedin Email Native blooms abound linkThe site is looking spectacular and exceeding our expectations. The restoration is only in it's second year and chock full of lovely blooms.
-
Late May rain water doesn't hang around long
Share Late May rain water doesn't hang around long on Facebook Share Late May rain water doesn't hang around long on Twitter Share Late May rain water doesn't hang around long on Linkedin Email Late May rain water doesn't hang around long linkThe basin had collected some water the morning of May 24th. Some light rain amounting to about 0.4 inches had come down over the course of a couple hours. The top image shows the basin with several inches of water that looked relatively clear at about 9:30am. The bottom image shows the site again at about 1:30 in the afternoon with nearly all the water infiltrated.
-
A rainy spring day
Share A rainy spring day on Facebook Share A rainy spring day on Twitter Share A rainy spring day on Linkedin Email A rainy spring day link -
Gobble gobble
Share Gobble gobble on Facebook Share Gobble gobble on Twitter Share Gobble gobble on Linkedin Email Gobble gobble linkTurkeys are checking out the basin stepping stones.
-
Grow in
Share Grow in on Facebook Share Grow in on Twitter Share Grow in on Linkedin Email Grow in linkPlants are growing in nicely.
-
Planting is nearly complete
Share Planting is nearly complete on Facebook Share Planting is nearly complete on Twitter Share Planting is nearly complete on Linkedin Email Planting is nearly complete linkThe planting is nearly complete. There are a few more perennial species to go in, and the trees that will go down the center of the berm are scheduled for early June.
-
Construction Update - May 2
Share Construction Update - May 2 on Facebook Share Construction Update - May 2 on Twitter Share Construction Update - May 2 on Linkedin Email Construction Update - May 2 linkStepping stone install.
-
Native seeding and planting extent
Share Native seeding and planting extent on Facebook Share Native seeding and planting extent on Twitter Share Native seeding and planting extent on Linkedin Email Native seeding and planting extent linkThe native vegetation will soon be going into the Lynmar Basin. We kept a 6’ strip of turf grass around the edges, but the other turf grass (within the native planting area) needed to be removed with herbicide in order to allow the native seed to grow. The native seeding area is shown in green in the drawing below. Everything outside of this green will stay as turf grass.
-
Spring work begins
Share Spring work begins on Facebook Share Spring work begins on Twitter Share Spring work begins on Linkedin Email Spring work begins linkCrews are eager to get on site as soon as the weather allows
You'll see some equipment and limestone blocks arriving on site in the next week or two for the crew to set stepping stones through the basin and some rock outcroppings.
Plugs and trees will be delivered and installed before the end of May.
Signup Banner
Who's Listening
-
Phone 952-826-0445 Email JWilson@EdinaMN.gov -
Phone 952-903-5713 Email RBintner@EdinaMN.gov -
Phone 952-826-0317 Email TSwenson@EdinaMN.gov -
Phone 952-835-2078 Email RAnhorn@ninemilecreek.org
Key Dates
-
September 2022
-
August 17 2022
-
June 21 2022
Lifecycle
-
Introduce Project
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageApril 2021
We will introduce the project and seek input on current open space use and measures to control stormwater.
-
Develop Initial Concepts
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageMay - July 2021
We will share initial concepts and let you know how your input influenced the design concepts.
-
Refine Concepts
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageJuly - September 2021
We will consider input, refine concepts, and share the outcome.
-
Make a Decision
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageSeptember 2021
Staff will make a recommendation to the City Council and Nine Mile Creek Watershed District Board of Managers. City Council will make a decision. Nine Mile Creek Watershed District Board of Managers will authorize staff to undertake a feasibility study to be considered to order the project.
-
Close the Loop
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageLate September 2021
We will tell people what decision was made. The public input portion of the concept design development process ends.
-
Make a Decision
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageMarch 2022
The Nine Mile Creek Watershed District Board will hold a public hearing, consider the feasibility study and make a decision.
-
Added: Detailed Engineering and Landscape Design Begins
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageSummer 2022
The Nine Mile Creek Watershed District Board approved the concept plan at their March Board meeting. This moved the project from the concept design phase to the detailed engineering and landscape design phase.
-
Added: Cooperative Agreement Decision
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageSummer 2022
City Council and Nine Mile Creek Watershed District consider entering into a cooperative agreement which describes how the two will work together.
-
Added: Design and Bid
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageSummer 2022
Staff will complete the design and prepare construction bid documents. A contractor will be selected through a competitive process.
-
Added: Construction
Bristol & Mavelle Park/Lynmar Basin Stormwater Project has finished this stageFall 2022
Construction begins.
-
Added: Restoration and Maintenance
Bristol & Mavelle Park/Lynmar Basin Stormwater Project is currently at this stage2023 and Beyond
Disturbed turf areas will be restored and natural areas will be planted.
Photos
Documents
- Lynmar Basin Rendering_Sept 2022.pdf (3.53 MB) (pdf)
- Lynmar Basin Rendering_90%_June2022.pdf (7.59 MB) (pdf)
- Sept 21 2021 Presentation.pdf (1.55 MB) (pdf)
- Lynmar Basin_ConceptPlan_SummaryReport_090921.pdf (4.77 MB) (pdf)
- Initial Concepts Layouts_July 2021 (2.71 MB) (pdf)
- Participation Plan.pdf (182 KB) (pdf)
- Lake Cornelia and Lake Edina Feasibility Study Report (7.95 MB) (pdf)
- Feasibility Study_February 2022.pdf (5.54 MB) (pdf)