Morningside C Neighborhood Roadway Reconstruction

Share Morningside C Neighborhood Roadway Reconstruction on Facebook Share Morningside C Neighborhood Roadway Reconstruction on Twitter Share Morningside C Neighborhood Roadway Reconstruction on Linkedin Email Morningside C Neighborhood Roadway Reconstruction link

Morningside C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project is scheduled for construction in 2023. The work typically includes:

  • Complete reconstruction of the asphalt pavement,
  • Full replacement of concrete curb and gutter is anticipated,
  • Complete replacement of watermain and water services is anticipated,
  • Replacement of fire hydrants and watermain gate valves,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Construction of concrete sidewalks along Kipling Avenue (west side), Monterey Avenue (west side), Inglewood Avenue (south / east side), West 40th Street (south side) as well as Lynn Avenue (east side) and Grimes Avenue where gaps in the sidewalk network exist on the east side.
  • A preliminary assessment amount of $13,800 per Residential Equivalent Unit was approved by the Council at the December 2022 public hearing. This $13,800 per REU amount has been recorded with Hennepin County as pending assessments for all impacted properties. Favorable bids were received. If unforeseen changes do not occur during construction, an assessment cost savings of up to 30% could occur.

Morningside C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project is scheduled for construction in 2023. The work typically includes:

  • Complete reconstruction of the asphalt pavement,
  • Full replacement of concrete curb and gutter is anticipated,
  • Complete replacement of watermain and water services is anticipated,
  • Replacement of fire hydrants and watermain gate valves,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Construction of concrete sidewalks along Kipling Avenue (west side), Monterey Avenue (west side), Inglewood Avenue (south / east side), West 40th Street (south side) as well as Lynn Avenue (east side) and Grimes Avenue where gaps in the sidewalk network exist on the east side.
  • A preliminary assessment amount of $13,800 per Residential Equivalent Unit was approved by the Council at the December 2022 public hearing. This $13,800 per REU amount has been recorded with Hennepin County as pending assessments for all impacted properties. Favorable bids were received. If unforeseen changes do not occur during construction, an assessment cost savings of up to 30% could occur.
  • Construction Update - 6/16/2023

    Share Construction Update - 6/16/2023 on Facebook Share Construction Update - 6/16/2023 on Twitter Share Construction Update - 6/16/2023 on Linkedin Email Construction Update - 6/16/2023 link

    As construction begins in your phase, we would like to stress the importance of checking your front door daily for time sensitive notifications. We invite you to review this document summarizing what to expect during construction.

    Phase 1: Grimes Ave and Inglewood Ave

    • Removals including curb and gutter, sidewalk and driveways is complete.
    • A select number of trees are scheduled to be removed during the week of 6/19.
    • The temporary above ground water main active.
    • Sanitary sewer repairs and water main pipe bursting began on 6/15. This work will continue through the week of 6/19.
    • Check your front door daily for temporary loss of driveway access.

    Phase 2: Monterey Ave and Lynn Ave – Work tentatively scheduled to begin in July

    • A select number of tree removals will be completed in concurrence with Phase 1 tree removals, scheduled to occur the week of 6/19.

    Phase 3: Kipling Ave and W 40th St – Work tentatively scheduled to begin in August

    • A select number of tree removals will be completed in concurrence with Phase 1 tree removals, scheduled to occur the week of 6/19.
  • Construction Update 6/9/2023

    Share Construction Update 6/9/2023 on Facebook Share Construction Update 6/9/2023 on Twitter Share Construction Update 6/9/2023 on Linkedin Email Construction Update 6/9/2023 link

    As construction begins in your phase, we would like to stress the importance of checking your front door daily for time sensitive notifications. We invite you to review this document summarizing what to expect during construction.


    Phase 1: Grimes Ave and Inglewood Ave

    • Removals including curb and gutter, sidewalk, driveways, and landscaping is complete. A select number of tree removals will be completed as well.
    • Setup of the temporary above ground water main began.
    • Following temporary water setup, the utility subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service. They will need access to the home to finalize the transition to the temporary watermain.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Utility work to begin the week of 6/12.


    Phase 2: Monterey Ave and Lynn Ave – Work tentatively scheduled to begin early July

    • A select number of tree removals will be completed in concurrence with Phase 1 tree removals.


    Phase 3: Kipling Ave and W 40th St – Work tentatively scheduled to begin early August

    • A select number of tree removals will be completed in concurrence with Phase 1 tree removals.


    Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.

  • Construction Kickoff!

    Share Construction Kickoff! on Facebook Share Construction Kickoff! on Twitter Share Construction Kickoff! on Linkedin Email Construction Kickoff! link

    As construction begins in your phase, we would like to stress the importance of checking your front door daily for time sensitive notifications. We invite you to review this document summarizing what to expect during construction.


    Phase 1: Grimes Ave and Inglewood Ave – Work beginning June 6

    • Grimes Ave and Inglewood Ave are scheduled to be reclaimed on June 6. Reclaiming is the process of grinding the existing asphalt into a gravel base.
    • In preparation for the underground utility work, removals including curb and gutter, sidewalk, driveways, and landscaping is scheduled to start June 7. A select number of tree removals will be completed as well.
    • Setup of the temporary above ground water main is scheduled to start the week of 6/5.
    • Following temporary water setup, the utility subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service. They will need access to the home to finalize the transition to the temporary watermain.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Utility work to begin following reclaim and removals.


    Phase 2: Monterey Ave and Lynn Ave – Work tentatively scheduled to begin early July

    • A select number of tree removals will be completed in concurrence with Phase 1 tree removals.


    Phase 3: Kipling Ave and W 40th St – Work tentatively scheduled to begin early August

    • A select number of tree removals will be completed in concurrence with Phase 1 tree removals.


    Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.

  • CenterPoint Energy Begins Construction May 3

    Share CenterPoint Energy Begins Construction May 3 on Facebook Share CenterPoint Energy Begins Construction May 3 on Twitter Share CenterPoint Energy Begins Construction May 3 on Linkedin Email CenterPoint Energy Begins Construction May 3 link

    Please see the following updates relating to CenterPoint Energy's gas main and service replacement project.

    1. CenterPoint Energy’s contractor, Michels Corporation, is scheduled to begin gas main and service replacements on May 3.
    2. CenterPoint Energy's work is not part of the City's Morningside C Neighborhood Roadway Reconstruction contract.
    3. This work is occurring to replace old steel gas main and services prior to the City’s roadway and utility reconstruction project.
    4. Gas main and service work will NOT occur on West 40th Street, Inglewood Avenue, the north half of Grimes Avenue or the north half of Kipling Avenue.
    5. City staff will only be onsite for this work periodically to ensure the gas main is not placed in the way of our future infrastructure.
    6. For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.

    CenterPoint Energy Morningside Website

  • Road and Utility Work Estimated Schedule

    Share Road and Utility Work Estimated Schedule on Facebook Share Road and Utility Work Estimated Schedule on Twitter Share Road and Utility Work Estimated Schedule on Linkedin Email Road and Utility Work Estimated Schedule link

    The contractor estimates beginning utility work in June in the Morningside C work north of W. 42nd Street. The contractor plans to complete the utility work in the Morningside D/E project area south of W. 42nd Street before beginning work in the Morningside C area.

  • Private Sewer, Water, Sump Upgrades - OPTIONAL

    Share Private Sewer, Water, Sump Upgrades - OPTIONAL on Facebook Share Private Sewer, Water, Sump Upgrades - OPTIONAL on Twitter Share Private Sewer, Water, Sump Upgrades - OPTIONAL on Linkedin Email Private Sewer, Water, Sump Upgrades - OPTIONAL link

    Consider upgrading your service pipes and connecting your sump pump to the City’s storm sewer system

    Service Pipes

    Now may be the time to upgrade your sanitary sewer and water service pipes. Homeowners are responsible for the sanitary sewer pipe from the main in the road to the house and the water service pipe from the water shut-off valve to the house. Upgrading private service pipes is not required as part of the project; however, the age and condition of the City-owned utilities suggests that your service pipes may be nearing the end of their useful life. To find more information on this topic, please see utility upgrade letter.

    Sump Drain Connection

    Sump drain pipes will be installed behind the new curbs where feasible. If you have a sump pump that discharges into the street or the boulevard, we encourage you to connect it to the new sump drain pipe after it is installed. To find more information on this topic, please see utility upgrade letter.

  • CenterPoint Energy Begins Construction April 24

    Share CenterPoint Energy Begins Construction April 24 on Facebook Share CenterPoint Energy Begins Construction April 24 on Twitter Share CenterPoint Energy Begins Construction April 24 on Linkedin Email CenterPoint Energy Begins Construction April 24 link

    Please see the following updates relating to CenterPoint Energy's gas main and service replacement project.

    1. CenterPoint Energy’s contractor, Michels Corporation, is scheduled to begin gas main and service replacements on April 24.
    2. CenterPoint Energy's work is not part of the City's Morningside C Neighborhood Roadway Reconstruction contract.
    3. This work is occurring to replace old steel gas main and services prior to the City’s roadway and utility reconstruction project.
    4. Gas main and service work will NOT occur on West 40th Street, Inglewood Avenue, the north half of Grimes Avenue or the north half of Kipling Avenue.
    5. City staff will only be onsite for this work periodically to ensure the gas main is not placed in the way of our future infrastructure.
    6. For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.


    CenterPoint Energy Morningside Website

  • Construction Contract Awarded

    Share Construction Contract Awarded on Facebook Share Construction Contract Awarded on Twitter Share Construction Contract Awarded on Linkedin Email Construction Contract Awarded link

    The City Council awarded the construction contract to GMH Asphalt on April 4, 2023. Stay tuned for further updates regarding a construction start date.

  • April 4 City Council Meeting - Construction Contract

    Share April 4 City Council Meeting - Construction Contract on Facebook Share April 4 City Council Meeting - Construction Contract on Twitter Share April 4 City Council Meeting - Construction Contract on Linkedin Email April 4 City Council Meeting - Construction Contract link

    The City Council will meet on on April 4, 2023 to consider awarding a construction contract to GMH Asphalt. Stay tuned for further updates regarding a construction start date.

  • Additional Sidewalks Approved

    Share Additional Sidewalks Approved on Facebook Share Additional Sidewalks Approved on Twitter Share Additional Sidewalks Approved on Linkedin Email Additional Sidewalks Approved link

    Based on public hearing testimony, petitions, survey results and staff recommendation, the City Council approved the addition of sidewalks on Kipling Avenue, Monterey Avenue and West 40th Street on January 17.

    The location of the sidewalks are proposed to be along the west sides of Kipling and Monterey Avenues, and the south side of West 40th Street. See the staff report to council here.