Construction Update - 6/19/2026

June 19, 2026

Project Area

  • Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until late June. Please see the attached detour map.
  • See the construction phasing map.
  • All work dates below are weather permitting.

Phase 4:

  • Vehicles cannot be parked on the street during construction working hours.
  • Asphalt driveway paving is scheduled to occur the week of 6/22.
  • Concrete sidewalk installation on Belmore Ln is scheduled to occur the week of 6/22.
  • Topsoil installation is scheduled to begin the week of 6/22.
  • Check your front door daily for notification of temporary driveway access loss.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.

Phases 1, 2, 3

  • Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.