Construction Update - 10/02/2026
October 2, 2026
Shannon Drive
- The Shannon Drive roadway and utility reconstruction work will not begin until spring 2027. The extended timeline is primarily due to the pace of utility work.We understand that extending construction to 2027 is frustrating and an inconvenience and sincerely appreciate the patience of residents in the project area. Crews remain on-site and are committed to completing the remaining neighborhood work as quickly as possible
Road Closures
- Kemrich Drive and Down Road will have heavy construction traffic the week of 10/5.Please avoid these areas and use alternative routes if possible. See locations in the following exhibit.
Project Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phases 1, 2 & 3:
- Crews will be onsite installing topsoil and sod Saturday, 10/3.
- General Notes
- Vehicles cannot be parked on the street during construction working hours
- Check your front door daily for notification of temporary water loss
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in
- Tree replacements will happen later in the fall
- The final layer of asphalt will be installed later in the fall
Phase 1:
- Ongoing Work (week of 10/5)
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
- Landscape restoration
- Sod installation on the final few properties
- Xcel Energy’s subcontractor Edison is onsite updating and reinstalling street lighting.
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
Phase 2:
- Upcoming Work (week of 10/5)
- Dublin Circle, Dublin Road, Antrim Road, Kerry Road, Wexford Road and 70th Street
- Asphalt driveway replacements is tentatively scheduled for Monday
- Backfilling behind curb in preparation for topsoil installation
- Sod installation
- Retaining wall installation
- Fleetwood Drive
- Xcel Energy’s subcontractor Edison is onsite updating and reinstalling street lighting.
Phase 3:
- Upcoming Work (week of 10/5)
- Down Road, Lee Valley Road and Kemrich Drive (West of Lanham)
- Removal of poor soils in preparation of curb and gutter installation.
- Curb and gutter installation is tentatively scheduled for the week of 10/12.
- Down Road, Lee Valley Road and Kemrich Drive (West of Lanham)
- Completed Work
- Kemrich Drive
- Water service replacement
- Sump line installation
- Kemrich Drive