News

Construction Update - 10/16/2026

October 16, 2026

Shannon Drive

  • The Shannon Drive roadway and utility reconstruction work will not begin until spring 2027. The extended timeline is primarily due to the pace of utility work.We understand that extending construction to 2027 is frustrating and an inconvenience and sincerely appreciate the patience of residents in the project area. Crews remain on-site and are committed to completing the remaining neighborhood work as quickly as possible.

Road Closures

  • Kemrich Drive, Lee Valley Road and Down Road will have heavy construction traffic during concrete installation, which is scheduled for Tuesday, 10/20 and Wednesday, 10/21. Please avoid these areas and use alternative routes if possible. See locations in the following exhibit.

Project Area

  • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
  • Please see the construction phasing map.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
  • All work dates below are weather permitting.

Phases 1, 2 & 3:

  • General Notes
    • Vehicles cannot be parked on the street during construction working hours
    • Check your front door daily for notification of temporary water loss
    • Driveway Accessibility
      • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in
    • Tree replacements and plantings will be planted in the spring of 2027.
    • The final layer of asphalt will be installed later in the fall
    • Irrigation repairs/adjustments are ongoing. If your system has been winterized before these repairs have been made, repairs will be completed in the spring of 2027.

Phase 1:

  • Ongoing Work (week of 10/19)
    • Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
      • Xcel Energy’s subcontractor Edison is onsite updating and reinstalling street lighting.
        • Xcel Energy’s subcontractor will be repairing any sod or landscaping that is disturbed during this work.
      • Landscape restoration
      • Sod installation on a few homes

Phase 2:

  • Ongoing Work (week of 10/19)
    • Dublin Circle, Dublin Road, Antrim Road, Kerry Road, Wexford Road and 70th Street
      • Landscape restoration
      • Sod/seed installation
    • Fleetwood Drive
      • Xcel Energy’s subcontractor Edison is onsite updating and reinstalling street lighting.
        • Xcel Energy’s subcontractor will be repairing any sod or landscaping that is disturbed during this work.

Phase 3:

  • Upcoming Work (week of 10/19)
    • Down Road, Lee Valley Road and Kemrich Drive (West of Lanham)
      • Curb and gutter installation has been rescheduled for Tuesday, 10/20 (Weather Permitting).
      • Xcel Energy’s subcontractor Edison is onsite updating and reinstalling street lighting.