Prospect Knolls Construction Update - 11/13/2026

November 13, 2026

Assessments

  • Please note, the assessment hearing will still be in October 2027 even though the project will not be complete in 2026.

Project Area

  • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.

    Phases 1, 2 & 3:

    • The final layer of asphalt paving is scheduled to occur the week of 11/16 for the west half of the project area.
      • See link for details.
    • General Notes
      • Vehicles cannot be parked on the street during construction working hours
      • Check your front door daily for access notifications
      • Tree replacements and plantings will be planted in the spring of 2027.
      • Irrigation repairs/adjustments are ongoing. If your system has been winterized before these repairs have been made, repairs will be completed in the spring of 2027.

    Phase 1:

    • Ongoing Work (week of 11/16)
      • Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
        • Xcel Energy’s subcontractor Edison will be repairing any sod or landscaping that is disturbed during this work.

    Phase 2:

    • Ongoing Work (week of 11/16)
    • Dublin Circle, Dublin Road, Antrim Road, Kerry Road, Wexford Road and 70th Street
      • Landscape restoration
      • Seed installation in wooded areas.
    • Fleetwood Drive
      • Xcel Energy’s subcontractor Edison will be repairing any sod or landscaping that is disturbed during this work.

    Phase 3:

    • Upcoming Work (week of 11/16)
      • Down Road, Lee Valley Road and Kemrich Drive (West of Lanham)
        • Landscape restoration
        • Seed installation in wooded areas.
      • Xcel Energy’s subcontractor Edison is onsite updating and reinstalling street lighting on Kemrich Drive.

    Shannon Drive

    • The Shannon Drive roadway and utility reconstruction work will not begin until spring 2027. The extended timeline is primarily due to the pace of utility work.We understand that extending construction to 2027 is frustrating and an inconvenience and sincerely appreciate the patience of residents in the project area. Crews remain on-site and are committed to completing the remaining neighborhood work as quickly as possible.