Construction Update - 9/25/2026

September 25, 2026

Shannon Drive

  • The Shannon Drive roadway and utility reconstruction work will not begin until spring 2027. The extended timeline is primarily due to the pace of utility work.We understand that extending construction to 2027 is frustrating and an inconvenience and sincerely appreciate the patience of residents in the project area. Crews remain on-site and are committed to completing the remaining neighborhood work as quickly as possible

Road Closures

  • Kemrich Drive and Down Road will be closed during daytime working hours for utility improvements through October 2.The contractor will make accommodations for property owners within the closure locations.See locations in the following exhibit.

Project Area

  • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
  • Please see the construction phasing map.
  • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
  • All work dates below are weather permitting.

Phases 1, 2 & 3:

  • General Notes
    • Vehicles cannot be parked on the street during construction working hours
    • Check your front door daily for notification of temporary water loss
    • Driveway Accessibility
      • You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in
    • Tree replacements will happen later in the fall
    • The final layer of asphalt will be installed later in the fall

Phase 1:

  • Ongoing Work (week of 9/28)
    • Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
      • Landscape restoration
      • Sod installation

Phase 2:

  • Upcoming Work (week of 9/28)
  • Dublin Circle, Dublin Road, Antrim Road, and 70th Street
    • Asphalt driveway replacements
    • Backfilling behind curb in preparation for topsoil installation
  • Ongoing Work
    • Kemrich Drive (west of Lanham Lane)
  • Tralee Drive
    • Irrigation and landscape restoration
    • Sod installation

Phase 3:

  • Upcoming Work (week of 9/28)
    • Down Road, Lee Valley Road
      • Reclaiming the existing asphalt pavement from Kerry Road to Shannon Drive
    • Water service replacement
      • Please watch for a door notification regarding potential short term loss of power and water for this work.
    • Fire hydrant and gate valve replacement
    • Removal of existing curb and gutter
    • Reclaiming the existing asphalt pavement from Lanham Lane to Shannon Drive
  • Completed Work
    • Down Road/Lee Valley Road
      • Water service and storm sewer replacement
    • Mailbox removals.
      • The temporary mail bank is located at W 69th St adjacent to Calvary Lutheran Church

Phase 4 (Shannon Drive):

  • Mailbox reinstallation begins Monday, 9/28