Blake Road - 2022 / 2023 Roadway Reconstruction
Blake Road Roadway Reconstruction updates will be hosted on this project page. Check back for updates!
The 2022 and 2023 project construction includes:
- Complete reconstruction of the pavement,
- Full installation or replacement of concrete curb and gutter,
- Partial replacement of watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems,
- Construction of mini roundabout at the Interlachen Boulevard intersection,
- Construction of two 5-foot on-street concrete bike lanes,
- Construction of a 6-foot concrete sidewalk along the west side of the street south of Interlachen Boulevard, and
- Construction of a 8-foot concrete shared use path along the west side of the street north of Interlachen Boulevard.
- Assessments to property owners for the roadway project costs, estimated at $7,000 per residential equivalent unit.
Blake Road Roadway Reconstruction updates will be hosted on this project page. Check back for updates!
The 2022 and 2023 project construction includes:
- Complete reconstruction of the pavement,
- Full installation or replacement of concrete curb and gutter,
- Partial replacement of watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems,
- Construction of mini roundabout at the Interlachen Boulevard intersection,
- Construction of two 5-foot on-street concrete bike lanes,
- Construction of a 6-foot concrete sidewalk along the west side of the street south of Interlachen Boulevard, and
- Construction of a 8-foot concrete shared use path along the west side of the street north of Interlachen Boulevard.
- Assessments to property owners for the roadway project costs, estimated at $7,000 per residential equivalent unit.
-
Road Opening Schedule - Phase 1 2023
Share Road Opening Schedule - Phase 1 2023 on Facebook Share Road Opening Schedule - Phase 1 2023 on Twitter Share Road Opening Schedule - Phase 1 2023 on Linkedin Email Road Opening Schedule - Phase 1 2023 linkPhase 1 2023 of the Blake Road Street Reconstruction Project is nearing completion. The final layer of pavement is scheduled for the week of August 14 with pavement marking the week of August 21. Traffic signs and pavement markings need to be installed before we re-open Blake and Interlachen from Hopkins to the Grandview District. Looks like it will be open for the first day of school on August 28. Phase 2 of 2023 is meeting a major milestone this week. Sheet piling should be complete today. This is a very loud and disruptive operation. We thank the residents for the patience.
-
Phase 1 2023 Status
Share Phase 1 2023 Status on Facebook Share Phase 1 2023 Status on Twitter Share Phase 1 2023 Status on Linkedin Email Phase 1 2023 Status linkThe contractor continues to make progress north of the land bridge in Phase 1 2023. Forming and pouring all the concrete walls and slabs are taking a little longer than expected. It appears the road won't be ready for traffic until early August. For safety purposes, continue to stay out of the project area. Thanks
-
Road Closure - Duration and Phasing
Share Road Closure - Duration and Phasing on Facebook Share Road Closure - Duration and Phasing on Twitter Share Road Closure - Duration and Phasing on Linkedin Email Road Closure - Duration and Phasing linkSee the Road Closure Phasing and Phasing Graphic for reference.
-
Phase 2 Starting Early - June 12
Share Phase 2 Starting Early - June 12 on Facebook Share Phase 2 Starting Early - June 12 on Twitter Share Phase 2 Starting Early - June 12 on Linkedin Email Phase 2 Starting Early - June 12 linkThe Contractor continues to make good progress in the 2023 Phase 1, north of the land bridge. To keep the project moving towards completion, the contractor is going to start 2023 Phase 2, south of the land bridge. On June 12, 2023 Phase 2 will be closed to all traffic except local traffic. During the week of June 12, Phase 1 work includes concrete pours of the walls and sidewalks along with street grading. In Phase 2, the contractor will remove the guard rail and prep for sheet pile installation. During the week of June 19, Phase 2 work will include sheet pile installation. This work has vibrations and is loud. The contractor is required to monitor vibrations during this work. Thanks for your patience as we continue with this project.
-
April 7, 2023 Update
Share April 7, 2023 Update on Facebook Share April 7, 2023 Update on Twitter Share April 7, 2023 Update on Linkedin Email April 7, 2023 Update linkWe continue to get questions on completion dates. Please see the March 6 update to phasing details. Phase 1 is tentatively scheduled for completion mid-July. Phase 2 is tentatively schedule for completion mid-October. The contractor is making great progress on the sheet pile walls. The existing street will be recycled next week and underground utilities will be started. Please stay out of the road closure and the work zone. It is not safe to drive, walk, or bike. Thanks
-
March 21, 2023 Update
Share March 21, 2023 Update on Facebook Share March 21, 2023 Update on Twitter Share March 21, 2023 Update on Linkedin Email March 21, 2023 Update linkSheet piling operations are starting. Please note that the road is closed between Waterman Ave and the east entrance of Interlachen Country Club. This includes the land bridge over Mirror Lake. Please stay out of the work zone and away from equipment at all times. Thank you.
-
Garbage Pick-Up Times
Share Garbage Pick-Up Times on Facebook Share Garbage Pick-Up Times on Twitter Share Garbage Pick-Up Times on Linkedin Email Garbage Pick-Up Times linkTypically during construction, we allow the garbage vendors to do pick-ups earlier than normal. Please have your cans out near the street by 6 am on pick-up days. Thanks
-
March 6: Road Closure and Phasing Map
Share March 6: Road Closure and Phasing Map on Facebook Share March 6: Road Closure and Phasing Map on Twitter Share March 6: Road Closure and Phasing Map on Linkedin Email March 6: Road Closure and Phasing Map linkSee the Road Closure Phasing and Phasing Graphic for reference. Thanks
-
2023 Construction Update - March 3
Share 2023 Construction Update - March 3 on Facebook Share 2023 Construction Update - March 3 on Twitter Share 2023 Construction Update - March 3 on Linkedin Email 2023 Construction Update - March 3 linkThe Blake Road Project is resuming construction operations. Work will start on Monday, March 13. The 2023 work will be phased. Phase 1 is located from Waterman Avenue to along Interlachen Boulevard just west of the Interlachen Country Club driveway. This phase includes the land bridge across Mirror Lake and the roundabout. Phase 2 is Blake Road south of the land bridge to Scriver Road. There will be tree removals, dust, mud, equipment noise, and noise associated with sheet pile installation. Vibration monitoring will start with construction operations. Working hours are 7 am to 9 pm. Access for residents will be provided. Also note there is some work from last year to finish between Spruce Road and Waterman Avenue. Scheduled construction operations are the following.
Week of March 6: Advanced road closure notifications and detour signage. Delivery of equipment.
Week of March 13: Clear and grub trees for Phases 1 and 2 and start removals
Week of March 20: Begin sheet pile installation along Mirror Lake in Phase 1
-
Road Closures moved to Feb. 16 and Feb. 17
Share Road Closures moved to Feb. 16 and Feb. 17 on Facebook Share Road Closures moved to Feb. 16 and Feb. 17 on Twitter Share Road Closures moved to Feb. 16 and Feb. 17 on Linkedin Email Road Closures moved to Feb. 16 and Feb. 17 linkDue to the rain this week, the road closures noted earlier have been moved to Thursday, Feb. 16 and Friday, Feb 17.
Email Signup
Sign Up for Emailed Project Updates
PRIVACY NOTICE: Under M.S. 13.356, your email address is private data. If you do not provide an email address you will not receive requested updates. Your email address will be available to anyone with a work assignment that reasonably require access.
Road Closure Information
Click here for road closure information and duration. The detour route is Vernon Avenue and Interlachen Boulevard.
Who's Listening
-
Phone 612-741-7096 Email XKopp@wsbeng.com -
Phone 952-826-0443 Email aditzler@EdinaMN.gov -
Phone 952-826-0318 Email cmillner@EdinaMN.gov
Key Dates
-
March 13 2023
-
August 15 2022
-
July 2022
-
April 19 2022
-
April 11 2022
Text Notifications
During the project there may be unexpected resident impacts. In addition to providing those notices on the project page you may opt into receiving text notifications.
To sign up text BLAKE to 5-7-8-3-8.
Photos
Videos
Documents
-
Construction Kickoff Update and FAQ (140 KB) (pdf)
-
Detour Map 2022 (3.73 MB) (pdf)
-
2022 Local Traffic Access Map (3.83 MB) (pdf)
-
Optional Utility Upgrade Letter Blake (933 KB) (pdf)
-
Blake Rd Project Area (377 KB) (jpg)
-
Blake Road Proposed Layout (4.34 MB) (pdf)
-
Blake Road Typical Section - Scriver Rd to Interlachen Blvd (433 KB) (pdf)
-
Blake Road Typical Section Interlachen Blvd to Spruce Rd (436 KB) (pdf)
-
Engineering Study BA-463 (20.9 MB) (pdf)
-
Estimated Market Benefit - Blake Road (1.22 MB) (pdf)
-
September 26, 2019 Open House Presentation (6.11 MB) (pdf)
-
Pedestrian Facilities Master Plan (497 KB) (pdf)
-
Assessment History (102 KB) (pdf)
-
Final Landscaping Plans.pdf (7.62 MB) (pdf)
-
Blake Road Phasing & Closure 2023 08 28 (2.17 MB) (pdf)