Blake Road - 2022 / 2023 Roadway Reconstruction

Share on Facebook Share on Twitter Share on Linkedin Email this link

Blake Road Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

The 2022 and 2023 project construction includes:

  • Complete reconstruction of the pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Partial replacement of watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems,
  • Construction of mini roundabout at the Interlachen Boulevard intersection,
  • Construction of two 5-foot on-street concrete bike lanes,
  • Construction of a 6-foot concrete sidewalk along the west side of the street south of Interlachen Boulevard, and
  • Construction of a 8-foot concrete shared use path along the west side of the street north of Interlachen Boulevard.
  • Assessments to property owners for the roadway project costs, estimated at $7,000 per residential equivalent unit.

Blake Road Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

The 2022 and 2023 project construction includes:

  • Complete reconstruction of the pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Partial replacement of watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems,
  • Construction of mini roundabout at the Interlachen Boulevard intersection,
  • Construction of two 5-foot on-street concrete bike lanes,
  • Construction of a 6-foot concrete sidewalk along the west side of the street south of Interlachen Boulevard, and
  • Construction of a 8-foot concrete shared use path along the west side of the street north of Interlachen Boulevard.
  • Assessments to property owners for the roadway project costs, estimated at $7,000 per residential equivalent unit.

  • 2024 Railing and Signs

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Later this week the contractor will be removing the sign mounts in the sidewalk and installing sign mounts to the walls. This removes an obstruction in the sidewalk during sidewalk snowplowing operations. The railings are being fabricated now. Railings have a very long lead time. They are tentatively scheduled for installation early June. Thanks

  • Nov. 9, 2023 Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The final layer of pavement was placed this week. Pavement markings and regulatory signs are scheduled towards the end of next week. If the remaining work goes as scheduled, the road will be open before Thanksgiving and potentially the weekend before. Thanks for all the patience with this project.

  • October 13, 2023 Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The area south of Mirror Lake is making great progress. The concrete curb was installed this week. The first two layers of blacktop is scheduled for next week along with concrete sidewalks. If everything goes as planned, the final layer of blacktop would occur the first week of November. Recall after the final layer of blacktop is placed, pavement markings and signs need to be installed before we can re-open the road to traffic. It is anticipated that it will re-open before Thanksgiving. The project team appreciates all the patience with the longer than expected project.

  • September 21, 2023 Project Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    As most people already know, the north half of the project is complete and open to traffic. The area south of Mirror Lake is still closed to traffic as the contractor finishes up. All underground utilities are complete, road grading is in process and concrete curb is tentatively scheduled for the first week of October. Progress also continues on the stone retaining walls. Of note is that the railings that will be placed on top of the wall near the sidewalks will be installed at a later date due to fabrication time.

  • Road Opening Update

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Interlachen Boulevard is open east of Blake Road, and Blake Road is open between the land bridge and the Edina / Hopkins city limits. Blake Road continues to be closed south of the land bridge. See the map for details.

  • Water Shutoff Interlachen Boulevard - 8/16/23

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Problems with the water system valves on Interlachen Boulevard require an emergency water shutoff today, 8/16. The contractor is working as quickly as possible to restore water service, but it’s anticipated that the shutdown will last until 6 PM. Affected streets include those on Interlachen Boulevard west of Blake Road.

  • Road Opening Schedule - Phase 1 2023

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    Phase 1 2023 of the Blake Road Street Reconstruction Project is nearing completion. The final layer of pavement is scheduled for the week of August 14 with pavement marking the week of August 21. Traffic signs and pavement markings need to be installed before we re-open Blake and Interlachen from Hopkins to the Grandview District. Looks like it will be open for the first day of school on August 28. Phase 2 of 2023 is meeting a major milestone this week. Sheet piling should be complete today. This is a very loud and disruptive operation. We thank the residents for the patience.

  • Phase 1 2023 Status

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The contractor continues to make progress north of the land bridge in Phase 1 2023. Forming and pouring all the concrete walls and slabs are taking a little longer than expected. It appears the road won't be ready for traffic until early August. For safety purposes, continue to stay out of the project area. Thanks

  • Road Closure - Duration and Phasing

    Share on Facebook Share on Twitter Share on Linkedin Email this link
    supporting image

    See the Road Closure Phasing and Phasing Graphic for reference.

  • Phase 2 Starting Early - June 12

    Share on Facebook Share on Twitter Share on Linkedin Email this link

    The Contractor continues to make good progress in the 2023 Phase 1, north of the land bridge. To keep the project moving towards completion, the contractor is going to start 2023 Phase 2, south of the land bridge. On June 12, 2023 Phase 2 will be closed to all traffic except local traffic. During the week of June 12, Phase 1 work includes concrete pours of the walls and sidewalks along with street grading. In Phase 2, the contractor will remove the guard rail and prep for sheet pile installation. During the week of June 19, Phase 2 work will include sheet pile installation. This work has vibrations and is loud. The contractor is required to monitor vibrations during this work. Thanks for your patience as we continue with this project.