Morningside C Neighborhood Roadway Reconstruction

Share Morningside C Neighborhood Roadway Reconstruction on Facebook Share Morningside C Neighborhood Roadway Reconstruction on Twitter Share Morningside C Neighborhood Roadway Reconstruction on Linkedin Email Morningside C Neighborhood Roadway Reconstruction link

Morningside C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project is scheduled for construction in 2023. The work typically includes:

  • Complete reconstruction of the asphalt pavement,
  • Full replacement of concrete curb and gutter is anticipated,
  • Complete replacement of watermain and water services is anticipated,
  • Replacement of fire hydrants and watermain gate valves,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Construction of concrete sidewalks along Kipling Avenue (west side), Monterey Avenue (west side), Inglewood Avenue (south / east side), West 40th Street (south side) as well as Lynn Avenue (east side) and Grimes Avenue where gaps in the sidewalk network exist on the east side.
  • A preliminary assessment amount of $13,800 per Residential Equivalent Unit was approved by the Council at the December 2022 public hearing. This $13,800 per REU amount has been recorded with Hennepin County as pending assessments for all impacted properties. Favorable bids were received. If unforeseen changes do not occur during construction, an assessment cost savings of up to 30% could occur.

Morningside C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project is scheduled for construction in 2023. The work typically includes:

  • Complete reconstruction of the asphalt pavement,
  • Full replacement of concrete curb and gutter is anticipated,
  • Complete replacement of watermain and water services is anticipated,
  • Replacement of fire hydrants and watermain gate valves,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Construction of concrete sidewalks along Kipling Avenue (west side), Monterey Avenue (west side), Inglewood Avenue (south / east side), West 40th Street (south side) as well as Lynn Avenue (east side) and Grimes Avenue where gaps in the sidewalk network exist on the east side.
  • A preliminary assessment amount of $13,800 per Residential Equivalent Unit was approved by the Council at the December 2022 public hearing. This $13,800 per REU amount has been recorded with Hennepin County as pending assessments for all impacted properties. Favorable bids were received. If unforeseen changes do not occur during construction, an assessment cost savings of up to 30% could occur.
  • Construction Update - 9/22/2023

    Share Construction Update - 9/22/2023 on Facebook Share Construction Update - 9/22/2023 on Twitter Share Construction Update - 9/22/2023 on Linkedin Email Construction Update - 9/22/2023 link

    Phase 1: Grimes Ave and Inglewood Ave

    • Topsoil installation, seeding, and hydro mulch is complete. The contractor will begin watering to support seed growth.
    • Irrigation system repairs are complete, except for a select few corner lots where additional construction remains. Please contact Nina if you have issues with your system.
    • The final layer of asphalt will be completed once all 3 phases of the project are complete, tentatively scheduled for mid-late October.


    Phase 2: Monterey Ave and Lynn Ave

    • The base layer of asphalt is complete.
    • Asphalt driveway tie-ins will be complete by 9/22.
      • New asphalt driveways can be driven on after about one hour once final rolling is completed.
    • The remaining sidewalk installation is tentatively scheduled for early October but could occur sooner.
    • If you had landscaping plantings, rock etc. impacted by construction, we need your help providing an itemized list of replacement landscaping items so the contractor can place the order with their supplier. Please reach out to Nina with details.


    Phase 3: Kipling Ave and W 40th St

    • Water service replacements are complete. All properties have been restored to permanent water main service.
    • Storm improvements on Kipling Ave are complete. Sump drain installation work began late this week, and may continue into the week of 9/25.
    • Roadway excavation on W 40thSt is complete. Roadway excavation on Kipling Ave is tentatively scheduled to begin the week of 9/25.
      • Roadway excavation on the south half of Kipling Ave is expected to be deep. Please check your front door daily for roadway impacts and temporary loss of driveway access.
    • Concrete curb and gutter is scheduled for the week of 10/2.
    • The base layer of asphalt is tentatively scheduled for mid to late October.


  • Construction Update - 9/15/2023

    Share Construction Update - 9/15/2023 on Facebook Share Construction Update - 9/15/2023 on Twitter Share Construction Update - 9/15/2023 on Linkedin Email Construction Update - 9/15/2023 link

    Phase 1: Grimes Ave and Inglewood Ave

    • Topsoil installation is complete. Seeding, hydro mulch and watering is scheduled to begin the week of 9/18.
    • Irrigation system repairs are complete, except for a select few corner lots where additional construction remains. Please contact Nina if you have issues with your system.
    • The final layer of asphalt will be completed once all 3 phases of the project are complete.


    Phase 2: Monterey Ave and Lynn Ave

    • The base layer of asphalt is tentatively scheduled to be paved 9/18.
    • Asphalt driveway tie-ins are scheduled for mid-week of 9/18.
    • The remaining sidewalk installation is tentatively scheduled for late September or early October.
    • Concrete driveways, aprons, and select sidewalk work is complete.
    • Final roadway grading is complete.
    • If you had landscaping plantings, rock etc. impacted by construction, we need your help providing an itemized list of replacement landscaping items so the contractor can place the order with their supplier. Please reach out to Nina with details.


    Phase 3: Kipling Ave and W 40th St

    • Water service replacements began and will continue the week of 9/18.
    • Storm sewer on W 40th St is complete.
    • Sump drain installation and storm sewer improvements on Kipling Ave will begin following the completion of water services.
    • Roadway excavation on W 40thSt is nearly complete. Roadway excavation on Kipling Ave is tentatively scheduled to begin the week of 9/25.
      • Roadway excavation on the south half of Kipling Ave is expected to be deep. Please check your front door daily for roadway impacts and temporary loss of driveway access.


  • Construction Update - 9/8/2023

    Share Construction Update - 9/8/2023 on Facebook Share Construction Update - 9/8/2023 on Twitter Share Construction Update - 9/8/2023 on Linkedin Email Construction Update - 9/8/2023 link

    Phase 1: Grimes Ave and Inglewood Ave

    • Irrigation system repairs are complete, except for a select few corner lots where additional construction remains. Please contact Nina if you have issues with your system.
    • Topsoil installation is complete. Seeding, hydro mulch and watering is scheduled to begin the week of 9/11.
    • The final layer of asphalt will be completed once all 3 phases of the project are complete.


    Phase 2: Monterey Ave and Lynn Ave

    • Concrete curb and gutter is complete.
    • Concrete driveways, aprons, and select sidewalk work began the week of 9/4.
      • Work will continue on Saturday, 9/9.
    • Final roadway grading is scheduled to begin the week of 9/11.
    • The base layer of asphalt is tentatively scheduled to be paved the week of 9/18, but could occur sooner.
      • Check your front door daily for on-street parking impacts.
    • If you had landscaping plantings, rock etc. impacted by construction, we need your help providing an itemized list of replacement landscaping items so the contractor can place the order with their supplier. Please reach out to Nina with details.


    Phase 3: Kipling Ave and W 40th St

    • Water service replacements are scheduled to begin the week of 9/11.
    • Storm sewer on W 40th St will be completed the week of 9/4.
    • Sump drain installation and storm sewer improvements on Kipling Ave will begin following the completion of water services.
    • Remaining curb and gutter removal on the south side of W 40th St will occur as needed to perform work.


  • Construction Update - 9/1/2023

    Share Construction Update - 9/1/2023 on Facebook Share Construction Update - 9/1/2023 on Twitter Share Construction Update - 9/1/2023 on Linkedin Email Construction Update - 9/1/2023 link
    supporting image

    NO WORK WILL OCCUR ON LABOR DAY, MONDAY 9/4.


    Phase 1: Grimes Ave and Inglewood Ave

    • Irrigation system repairs are complete, except for a select few corner lots where additional construction remains. Please contact Nina if you have issues with your system.
    • Topsoil installation is complete. Seeding, hydromulch and watering is scheduled to begin the week of 9/4.
    • If you had landscaping plantings, rock etc. impacted by construction, we need your help providing an itemized list of replacement landscaping items so the contractor can place the order with their supplier. Please reach out to Nina with details if you have not already done so.
    • The final layer of asphalt will be completed once all 3 phases of the project are complete.


    Phase 2: Monterey Ave and Lynn Ave

    • Sump drain installation near the City’s sanitary sewer lift station between Lynn Ave and Monterey Ave will occur the week of 9/4.
    • Roadway excavation and gravel installation is nearly complete.
    • Concrete curb and gutter and driveway apron work is scheduled to begin the week of 9/4.
      • Check your front door for loss of driveway access and appropriate parking locations.
    • The base layer of asphalt is tentatively scheduled to be paved in mid-September.
    • If you had landscaping plantings, rock etc. impacted by construction, we need your help providing an itemized list of replacement landscaping items so the contractor can place the order with their supplier. Please reach out to Nina with details.


    Phase 3: Kipling Ave and W 40th St

    • Dewatering is complete. The generator and pump will be removed the week of 9/4.
    • Water main improvements will continue the week of 9/4.
    • Water service replacements are tentatively scheduled to begin the week of 9/11.
    • Storm sewer and sump drain installation will begin following the completion of water main improvements.
    • Curb and gutter removal on the south side of W 40th St will occur prior to storm sewer improvements.


  • Construction Update 8/25/2023

    Share Construction Update 8/25/2023 on Facebook Share Construction Update 8/25/2023 on Twitter Share Construction Update 8/25/2023 on Linkedin Email Construction Update 8/25/2023 link

    Phase 1: Grimes Ave and Inglewood Ave

    • Concrete sidewalk installation and the base layer of asphalt paving is complete.
    • Irrigation system repairs will begin the week of 8/28. Please contact Nina if you have a system that needs to be restored.
    • Topsoil installation is scheduled to begin the week of 8/28.
    • If you had landscaping plantings, rock etc. impacted by construction, we need your help providing an itemized list of replacement landscaping items so the contractor can place the order with their supplier. Please reach out to Nina with details.


    Phase 2: Monterey Ave and Lynn Ave

    • Roadway excavation and gravel installation began and will continue the week of 8/28.
    • Excavation is anticipated to be deep on the south half of Lynn Ave and Monterey Ave. This work will take approximately 2-3 days to complete once the contractor begins in this area. Temporary loss of driveway access and traffic delays are to be expected. Driveway access will be restored at the end of each workday. Please contact Nina if you need special assistance or concerns during this work.
    • Concrete curb and gutter, driveway aprons, and sidewalk work is scheduled to begin soon after the Labor Day holiday.


    Phase 3: Kipling Ave and W 40th St

    • Dewatering began the week of 8/21. Dewatering is the process of lowering the underground water table which is needed to complete the underground utility installations.
      • This process requires the use of a generator which will run 24 hours a day, 7 days a week until the work is completed. This work will take approximately 2 weeks to complete.
    • Following temporary water setup, the utility subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service. They will need access to the home to finalize the transition to the temporary water main.
    • Water main improvements will begin the week of 8/28.
    • Water service installation will begin following the completion of water main installation.
    • Storm sewer and sump drain installation will begin following the completion of water main improvements.
  • Construction Update - 8/18/2023

    Share Construction Update - 8/18/2023 on Facebook Share Construction Update - 8/18/2023 on Twitter Share Construction Update - 8/18/2023 on Linkedin Email Construction Update - 8/18/2023 link

    Phase 1: Grimes Ave and Inglewood Ave

    • Installation of concrete curb and gutter and driveway aprons, as well as concrete driveway replacements are complete.
    • Concrete sidewalk installation is scheduled for 8/22.
    • Roadway grading in preparation for paving began and will continue the week of 8/21.
    • The base layer of asphalt paving is scheduled for 8/23, ahead of school resuming.
    • Irrigation system repairs will begin following the installation of asphalt paving. Please contact Nina if you have a system that needs to be restored.
    • If you had landscaping plantings, rock etc. impacted by construction, we need your help providing an itemized list of replacement landscaping items so the contractor can place the order with their supplier. Please reach out to Nina with details.


    Phase 2: Monterey Ave and Lynn Ave

    • Properties on Lynn Ave who were placed on temporary water main service were restored to permanent service.
    • Sump drain and storm sewer installation is complete.
    • Roadway excavation and gravel installation is tentatively scheduled to begin the week of 8/21, following completion of final roadway grading in Phase 1.
    • Concrete curb and gutter, driveway aprons, and sidewalk work is scheduled to begin after Labor Day.


    Phase 3: Kipling Ave and W 40th St

    • Dewatering will begin the week of 8/21. Dewatering is the process of lowering the underground water table which is needed to complete the underground utility installations.
      • This process requires the use of a generator which will run 24 hours a day, 7 days a week until the work is completed. This work will take approximately 2 weeks to complete. We're sorry for the inconvenience of this noise.
    • Roadway reclaiming is complete.
    • Temporary water main set up began and will continue the week of 8/21.
    • Following temporary water setup, the utility subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service. They will need access to the home to finalize the transition to the temporary water main.
    • Utility work will follow driveway apron, and landscaping removals.


  • Construction Update - 8/11/2023

    Share Construction Update - 8/11/2023 on Facebook Share Construction Update - 8/11/2023 on Twitter Share Construction Update - 8/11/2023 on Linkedin Email Construction Update - 8/11/2023 link

    Phase 1: Grimes Ave and Inglewood Ave

    • Roadway excavation and gravel installation complete.
    • Concrete curb and gutter installation occurred on 8/10 and 8/11.
    • Driveway aprons and concrete driveway replacements are scheduled to begin the week of 8/14. Check your front door for a notification on this work. You will be asked to park on an adjacent street while work is occurring on your driveway.
    • Final roadway grading is scheduled to occur the week of 8/14, and the base layer of asphalt paving is tentatively scheduled for the week of 8/21.
    • If you had landscaping plantings, rock etc. impacted by construction, we need your help providing an itemized list of replacement landscaping items so the contractor can place the order with their supplier. Please reach out to Nina with details.


    Phase 2: Monterey Ave and Lynn Ave

    • Water service installation is complete.
    • Properties on Lynn Ave who were placed on temporary water main service were restored to permanent service.
    • Sump drain installation is complete on Lynn Ave. Sump installation will continue on Monterey Ave into the week of 8/14.
    • Roadway excavation and gravel installation is tentatively scheduled to begin on Lynn Ave following completion of the utility work and Phase 1 excavation.


    Phase 3: Kipling Ave and W 40th St

    • Roadway reclaiming is tentatively scheduled for the week of 8/14. Reclaiming is the process of grinding the existing asphalt into a gravel base and is anticipated to take 1-2 days to complete.
    • Utility work will follow reclaiming, driveway apron, and landscaping removals.


  • Construction Update - 8/4/2023

    Share Construction Update - 8/4/2023 on Facebook Share Construction Update - 8/4/2023 on Twitter Share Construction Update - 8/4/2023 on Linkedin Email Construction Update - 8/4/2023 link

    Phase 1: Grimes Ave and Inglewood Ave

    • Roadway excavation and gravel installation began 8/2 and will continue into the week of 8/7.
    • Excavation to replace poor soils with stable soils under the roadway and gravel is expected to be significant on the south half of Phase 1. Check your front door daily for temporary loss of driveway access.
    • Concrete curb and gutter, sidewalk, and driveway apron installation is tentatively scheduled to begin late in the week of 8/7.
    • The base layer of asphalt is tentatively scheduled to be placed the week of 8/21.
    • If you had landscaping plantings, rock etc. impacted by construction, we need your help providing an itemized list of replacement landscaping items so the contractor can place the order with their supplier. Please reach out to Nina with details.


    Phase 2: Monterey Ave and Lynn Ave

    • Water service installation began and will continue the week of 8/7.
    • Properties on Lynn Ave who were placed on temporary water main service will be restored to permanent service upon completion of water service installation.
    • Storm sewer installation is complete.
    • Sump drain installation will follow water service installation.
    • Roadway excavation and gravel installation is tentatively scheduled to begin on Lynn Ave following completion of the utility work and Phase 1 excavation.
    • Check your front door daily for temporary loss of driveway access.


    Phase 3: Kipling Ave and W 40th St – Work tentatively scheduled to begin in early/mid-August

    • Roadway reclaiming is expected to take place in early to mid-August. Reclaiming is the process of grinding the existing asphalt into a gravel base and is anticipated to take 1-2 days to complete.
    • Utility work will follow reclaiming, driveway apron, and landscaping removals.


  • Construction Update - 7/28/2023

    Share Construction Update - 7/28/2023 on Facebook Share Construction Update - 7/28/2023 on Twitter Share Construction Update - 7/28/2023 on Linkedin Email Construction Update - 7/28/2023 link

    It’s come to our attention that the USPS has stopped delivering mail to parts of the project area due to construction. We apologize for this inconvenience. At the request of the USPS, the contractor will be installing a temporary mailbox bank for the USPS to deliver mail to. Please check your front door for details on where to pick up your mail.

    Phase 1: Grimes Ave and Inglewood Ave

    • Roadway excavation and gravel installation is scheduled to begin the week of 7/31.
    • Excavation to replace poor soils with stable soils under the roadway and gravel is expected to be significant on the south half of Phase 1. Check your front door daily for temporary loss of driveway access.
    • Concrete curb and gutter, sidewalk, and driveway apron installation is tentatively scheduled to begin the week of 8/7.
    • If you had landscaping plantings, rock etc. impacted by construction, we need your help providing an itemized list of replacement landscaping items so the contractor can place the order with their supplier. Please reach out to Nina with details.

    Phase 2: Monterey Ave and Lynn Ave

    • Removal of concrete curb and gutter and driveway aprons will continue into week of 7/31.
    • Watermain installation is complete on Lynn Ave and the south half of Monterey Ave. Water service installation will begin the week of 7/31.
    • Storm sewer installation began and will continue into the week of 7/31. Sump drain installation will follow water service installation and storm sewer improvements.
    • Roadway excavation and gravel installation is tentatively scheduled to begin on Monterey Ave following completion of the utility work and Phase 1 excavation.
    • Check your front door daily for temporary loss of driveway access.

    Phase 3: Kipling Ave and W 40th St – Work tentatively scheduled to begin in early/mid-August

    • Roadway reclaiming is expected to take place in early August. Reclaiming is the process of grinding the existing asphalt into a gravel base and is anticipated to take 1-2 days to complete.
    • Utility work will follow reclaiming, driveway apron, and landscaping removals.


  • Construction Update - 7/21/2023

    Share Construction Update - 7/21/2023 on Facebook Share Construction Update - 7/21/2023 on Twitter Share Construction Update - 7/21/2023 on Linkedin Email Construction Update - 7/21/2023 link

    Phase 1: Grimes Ave and Inglewood Ave

    • All utility work is complete.
    • Roadway excavation and gravel installation is scheduled to begin the week of 7/31.
    • Excavation to replace poor soils with stable soils under the roadway and gravel is expected to be significant on the south half of Phase 1. Check your front door daily for temporary loss of driveway access.


    Phase 2: Monterey Ave and Lynn Ave

    • Removal of concrete curb and gutter and driveway aprons will continue into week of 7/24.
    • Please recall the watermain and water services will not be replaced along the north half of Monterey Avenue. The main and services are owned by the City of St. Louis Park.
    • Temporary water setup is complete for homes on the north half of Lynn Avenue. Homes have been transferred to temporary watermain service.
    • The south half of Lynn Ave and all of Monterey Ave will not be placed on temporary water service. However, properties in this area will experience short term shut offs ranging from 4-8 hours. Check your front door daily for date and duration of shut off.
    • Water main improvements will continue the week of 7/24.
    • Storm sewer and sump drain installation will follow water main improvements.
    • Check your front door daily for temporary loss of driveway access.


    Phase 3: Kipling Ave and W 40th St – Work tentatively scheduled to begin in early/mid-August