Vernon Avenue & Highway 100 Interchange Project

The City of Edina partnering with Hennepin County in coordination with Minnesota Department of Transportation, is replacing the bridge over Highway 100 and the Vernon Avenue Bridge (County Road 158) over the Canadian Pacific (CP) Railroad. The overall project will also improve the intersections at Interlachen Boulevard, Gus Young Lane, Arcadia Avenue and the Highway 100 on- and off-ramps.
The size of the existing sidewalk and the lack of separation from heavy traffic make this street uncomfortable for many pedestrians, creating a significant barrier within the Grandview District. Additionally, the interchange with TH 100 is a complicated and redundant system of six unique access ramps that connect to four different streets within the district.
This project would improve safety and mobility for all users and eliminate redundant access ramps. Construction is anticipated to begin April 21.
Project goals
o Improve safety and mobility for all users
o Create new separated pedestrian routes
o Improve traffic operations
o Consolidate TH 100 access points
o Improve connectivity between residential and commercial areas of the district
o Replace Vernon Ave bridge meeting CP Rail clearance requirements
o Limit construction impacts to the public and create greater funding efficiency by combining city
and county projects
o Enhance economic viability with improved access
Changes to be made
Arcadia Avenue
- Addition of 10-foot-wide sidewalk and ADA-compliant pedestrian ramps
- New streetlights
Minnesota Highway 100
- Removal of redundant on- and off ramps and the creation of a tight diamond interchange
- New noise wall along northbound on-ramp
Interlachen Boulevard and Gus Young Lane
- Addition of 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
- New left turn lanes
- New traffic signal with ADA-compliant audible crossings
- New ADA-compliant entrance into Edina Liquor
Vernon Avenue and W. 50th St.
Two new bridges:
- New Vernon Avenue Bridge that is widened and raised to meet railroad height requirements
- New Highway 100 Bridge that creates space for the below improvements:
- 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
- Pedestrian refuge islands
- New dual left-turn lanes in both east and west directions
- New traffic signals with ADA-compliant audible crossings
The City of Edina partnering with Hennepin County in coordination with Minnesota Department of Transportation, is replacing the bridge over Highway 100 and the Vernon Avenue Bridge (County Road 158) over the Canadian Pacific (CP) Railroad. The overall project will also improve the intersections at Interlachen Boulevard, Gus Young Lane, Arcadia Avenue and the Highway 100 on- and off-ramps.
The size of the existing sidewalk and the lack of separation from heavy traffic make this street uncomfortable for many pedestrians, creating a significant barrier within the Grandview District. Additionally, the interchange with TH 100 is a complicated and redundant system of six unique access ramps that connect to four different streets within the district.
This project would improve safety and mobility for all users and eliminate redundant access ramps. Construction is anticipated to begin April 21.
Project goals
o Improve safety and mobility for all users
o Create new separated pedestrian routes
o Improve traffic operations
o Consolidate TH 100 access points
o Improve connectivity between residential and commercial areas of the district
o Replace Vernon Ave bridge meeting CP Rail clearance requirements
o Limit construction impacts to the public and create greater funding efficiency by combining city
and county projects
o Enhance economic viability with improved access
Changes to be made
Arcadia Avenue
- Addition of 10-foot-wide sidewalk and ADA-compliant pedestrian ramps
- New streetlights
Minnesota Highway 100
- Removal of redundant on- and off ramps and the creation of a tight diamond interchange
- New noise wall along northbound on-ramp
Interlachen Boulevard and Gus Young Lane
- Addition of 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
- New left turn lanes
- New traffic signal with ADA-compliant audible crossings
- New ADA-compliant entrance into Edina Liquor
Vernon Avenue and W. 50th St.
Two new bridges:
- New Vernon Avenue Bridge that is widened and raised to meet railroad height requirements
- New Highway 100 Bridge that creates space for the below improvements:
- 10-foot-wide sidewalks and ADA-compliant pedestrian ramps
- Pedestrian refuge islands
- New dual left-turn lanes in both east and west directions
- New traffic signals with ADA-compliant audible crossings
-
April 15, 2025 Update
Share April 15, 2025 Update on Facebook Share April 15, 2025 Update on Twitter Share April 15, 2025 Update on Linkedin Email April 15, 2025 Update linkRoad Closure beginning April 23: Vernon Avenue and 50th Street between Interlachen Blvd and Grange Road with the exception of the on- and off-ramps to Highway 100 will close on April 23. The Grandview Businesses and the 50th & France Business District are open and accessible during the project. The local detours are shown here. Remember to log in April 17 at 11 am here to learn more about the project. Thanks, Chad Millner, City Engineer.
-
April 3, 2025 Update
Share April 3, 2025 Update on Facebook Share April 3, 2025 Update on Twitter Share April 3, 2025 Update on Linkedin Email April 3, 2025 Update linkThe Vernon Avenue and Highway 100 Interchange Project is scheduled to start April 21. The contractor is targeting April 23 to close Vernon Avenue and 50th Street between Interlachen Blvd and Grange Road with the exception of the on and off-ramps to Highway 100. Remember to log in April 17 at 11 am to learn more about the project at EdinaMN.gov/Highway100Talks or EdinaMN.gov/highway100talks. This is a re-occurring meeting Thursday mornings every other week during the project. A recap of the April 3 meeting can be found here.
Recap: Vernon / 50th Interchange Project Bi-Weekly Public Meeting Thursday, April 3.
Thanks, Chad Millner, City Engineer.
PowerPoint Slides can be found in the document area linked here.
https://www.bettertogetheredina.org/20963/widgets/69150/documents/66396
-
April 2, 2025 Update
Share April 2, 2025 Update on Facebook Share April 2, 2025 Update on Twitter Share April 2, 2025 Update on Linkedin Email April 2, 2025 Update linkTree removals for the project have been completed. Staff provided a project update at the April 1 City Council Works Session. We discussed schedule, management of traffic, communications, and funding. We will be asking council to award a contract to Ames Construction on April 16. The exact schedule is still being developed but will be available soon. Remember to log in tomorrow at 11 am to learn more about the project at EdinaMN.gov/Highway100Talks or EdinaMN.gov/highway100talks. This is the first of many Thursday morning meetings available every other week during the project. Thanks, Chad Millner, City Engineer.
-
March 26, 2025 Invite to Virtual Meeting
Share March 26, 2025 Invite to Virtual Meeting on Facebook Share March 26, 2025 Invite to Virtual Meeting on Twitter Share March 26, 2025 Invite to Virtual Meeting on Linkedin Email March 26, 2025 Invite to Virtual Meeting linkCome learn about the upcoming Vernon Avenue & Highway 100 Interchange Project. City Engineer Chad Millner will host a virtual public meeting. All are welcome to join this 30-minute meeting. The first meeting will occur on April 3 at 11 am. This meeting will re-occur every 2-weeks until the project is completed on Thursdays at 11 am. To participate, type either of the following addresses into a web browser.
EdinaMN.gov/Highway100Talks
EdinaMN.gov/highway100talks
-
March 18, 2025 Update
Share March 18, 2025 Update on Facebook Share March 18, 2025 Update on Twitter Share March 18, 2025 Update on Linkedin Email March 18, 2025 Update linkA big milestone was completed on Thursday, March 13, construction bids were received. We received two bids for construction of the project. They were from Ames Construction at $22.06 million and C.S. McCrossan at $22.45 million. These were at the engineers estimate. The state is reviewing the required contracting paperwork. If everything meets the requirements, we will ask the City Council to award a contract on April 16. The schedule that was included in the bid documents required Vernon Ave and 50th Street to be re-opened to traffic by November 15, 2025. We are still discussing schedule with the contractor.
-
March 5, 2025 Update
Share March 5, 2025 Update on Facebook Share March 5, 2025 Update on Twitter Share March 5, 2025 Update on Linkedin Email March 5, 2025 Update linkThe City Council awarded a tree removal contract last night. Removals are tentatively planned for the last two weeks of March. Due to the delay caused by CPKS Railroad in signing an easement agreement, a separate contract for tree removals is required. The trees need to be removed before March 31. This contract will remove all the necessary trees to make space for the new bridges, highway interchange and noise walls. The highway interchange project is out to bid now with an anticipated award date of April 16. Trees are located along Highway 100 near City Hall, adjacent to the northbound Highway 100 on-ramp, around both the Highway 100 and Vernon Ave bridges and near CPKC Railroad tracks. A copy of the tree removal plans is posted to the documents area of this website. Thanks, Chad Millner, City Engineer
-
February 27, 2025 Update
Share February 27, 2025 Update on Facebook Share February 27, 2025 Update on Twitter Share February 27, 2025 Update on Linkedin Email February 27, 2025 Update linkDue to the delay caused by CPKS Railroad in signing an easement agreement, a separate contract for tree removals is required. The trees need to be removed before March 31 to ensure no protected species have nested yet. This contract will remove all the necessary trees to make space for the new bridges, highway interchange and noise walls. The highway interchange project is out to bid now with an anticipated award date of April 16. Trees are located along Highway 100 near City Hall, adjacent to the northbound Highway 100 on-ramp, around both the Highway 100 and Vernon Ave bridges and near CPKC Railroad tracks. Council will consider awarding this contract on March 4. Work will start soon afterwards. Thanks
-
February 10, 2025 Update
Share February 10, 2025 Update on Facebook Share February 10, 2025 Update on Twitter Share February 10, 2025 Update on Linkedin Email February 10, 2025 Update linkThe bid documents will be posted later this week or early next week soliciting a contractor. The bid opening is scheduled for March 6. The contract award is scheduled for April 16 City Council Meeting. Construction can start as soon as April 21. The selected contractor will provide a detailed construction schedule with major milestones. This schedule will allow us to communicate construction specifics with the public. There is still a possibility the project is completed this year. Thanks, Chad Millner, City Engineer.
-
January 23, 2025 Project Update
Share January 23, 2025 Project Update on Facebook Share January 23, 2025 Project Update on Twitter Share January 23, 2025 Project Update on Linkedin Email January 23, 2025 Project Update linkThe project has received the signed easement agreement from CPKC Railroad. The project can now move forward. The team is developing bidding and construction schedules. Federal money is a large portion of the project funding and it comes with rules on the timing of the project. Private utility companies are starting relocations now. Tree clearing work is also required to be done before the end of March. Thanks for your patience with the unknown schedule. More details will be coming soon.
-
Nov. 19, 2024 Staging Narrative
Share Nov. 19, 2024 Staging Narrative on Facebook Share Nov. 19, 2024 Staging Narrative on Twitter Share Nov. 19, 2024 Staging Narrative on Linkedin Email Nov. 19, 2024 Staging Narrative linkThe recent article has generated lots of questions related to traffic during the project. Staff created a staging narrative memo during the design process. That memo has been uploaded to the document section of this site. Please note this staging narrative is draft and without a contractor yet. Thanks, Chad Millner, City Engineer.
Email Signup
Sign Up for Emailed Project Updates
PRIVACY NOTICE: Under M.S. 13.356, your email address is private data. If you do not provide an email address you will not receive requested updates. Your email address will be available to anyone with a work assignment that reasonably require access.
Online Project Talks
Online Project Talks
Join City of Edina Director of Engineering Chad Millner for online project talks every other Thursday at 11 a.m. until the project is complete. These talks provide an opportunity for City staff to share construction updates and for the public to ask questions. Anyone interested in the project, including residents, businesses and visitors, is welcome to attend.
How to Join:
When it’s time for a project talk, visit EdinaMN.gov/Highway100Talks to participate. The talks will be held online through Microsoft Teams. No account is required, and you can join as a guest.
Dates:
April 3 & 17;
May 1, 15 & 29;
June 12 & 26;
July 10 & 24;
Aug. 7 & 21;
Sept. 4 & 18;
Oct. 2, 16 & 30;
Nov. 13
Meeting Recordings:
Couldn’t make a meeting? View recordings of past project talks on YouTube.
Worth the Detour Program
Support Local Businesses This Fall & Win Prizes!
During the construction project, your support of local businesses in Grandview and 50th & France makes a big difference. The Worth the Detour Edina campaign highlights the unique shops, restaurants and experiences these districts offer. This fall, you can participate by collecting stamps in the Worth the Detour Passport program, joining the Restaurant Week social media contest and enjoying free movies at the Edina Theatre on select Saturday mornings, all while continuing to support your favorite local businesses.
Who's Listening
-
Phone 952-826-0318 Email cmillner@EdinaMN.gov -
Phone 651-392-9263 Email derek.huston@tkda.com
Key Dates
-
December 2022 → July 2023
-
July 2023 → June 2024
-
April 21 → November 15 2025
Important Links
Documents
-
Stage 3A Detour Maps (July 28-Sept. 14, 2025)
-
Stage 3B Detour Maps (Sept. 15-Mid-November 2025)
-
Detour Maps - September 15 to Mid-November 2025 (Stage 3B).pdf (800 KB) (pdf)
-
Grandview Access Map - September 15 to Mid-November 2025 (Stage 3B).jpg (1.51 MB) (jpg)
-
Northbound Hwy 100 On-Ramp Detour Map - September 15 to Mid-November 2025 (Stage 3B).jpg (3.02 MB) (jpg)
-
Northbound Hwy 100 Exit Ramp Detour Map - September 15 to Mid-November 2025 (Stage 3B).jpg (3.11 MB) (jpg)
-
Southbound Hwy 100 Exit Ramp Detour Map - September 15 to Mid-November 2025 (Stage 3B).jpg (3.04 MB) (jpg)
-
-
Resources for Businesses (Flyers, Signs & Social Media Graphics)
-
50th France Business Directions – Social Graphic (Landscape) 1920x1080 – Stage 3B.jpg (654 KB) (jpg)
-
50th France Business Directions – Social Graphic (Square) 1080x1080 – Stage 3B.jpg (537 KB) (jpg)
-
50th France Business Directions – Social Graphic (Vertical) 1080x1350 – Stage 3B.jpg (581 KB) (jpg)
-
Grandview Business Directions – Social Graphic (Landscape) 1920x1080 – Stage 3B.jpg (684 KB) (jpg)
-
Grandview Business Directions – Social Graphic (Square) 1080x1080 – Stage 3B.jpg (544 KB) (jpg)
-
Grandview Business Directions – Social Graphic (Vertical) 1080x1350 – Stage 3B.jpg (597 KB) (jpg)
-
Ramp Closures – Social Graphic (Square) 1080x1080 – Stage 3B.jpg (646 KB) (jpg)
-
Open During Construction Sign (Ready to Print) - Design 1.pdf (25.3 KB) (pdf)
-
Open During Construction Sign (Ready to Print) - Design 2.pdf (25.6 KB) (pdf)
-
Open During Construction Sign (Ready to Print) - Design 3.pdf (25 KB) (pdf)
-
Open During Construction Sign (with Custom Message Space) - Design 1.pdf (35.3 KB) (pdf)
-
Open During Construction Sign (with Custom Message Space) - Design 2.pdf (25.3 KB) (pdf)
-
Open During Construction Sign (with Custom Message Space) - Design 3.pdf (34.3 KB) (pdf)
-
Project Overview Flyer - Design 1.pdf (2.63 MB) (pdf)
-
Project Overview Flyer - Design 2.pdf (2.64 MB) (pdf)
-
-
Project Update Mtg14 October 2.pdf (5.72 MB) (pdf)
-
Project Update Mtg13 September 18.pdf (3.83 MB) (pdf)
-
Project Update Mtg12 September 4.pdf (4.77 MB) (pdf)
-
Project Update Mtg11 August 21.pdf (4.19 MB) (pdf)
-
Project Update Mtg10 August 7.pdf (3.13 MB) (pdf)
-
Project Update Mtg9 July 24.pdf (3.63 MB) (pdf)
-
Project Update Mtg8 July 10.pdf (4.46 MB) (pdf)
-
Project Update Mtg7 June 26.pdf (2.8 MB) (pdf)
-
Project Update Mtg 6 June 12.pdf (1.81 MB) (pdf)
-
Project Update Mtg5 May 29.pdf (2.52 MB) (pdf)
-
Project Update Mtg4 May 15.pdf (2 MB) (pdf)
-
Project Update Mtg3 May 1.pdf (1.57 MB) (pdf)
-
Project Update Mtg2 April 17 (1.32 MB) (pdf)
-
Project Update Mtg1 April 3 (872 KB) (pdf)
-
Tree Removal Plans (1.06 MB) (pdf)
-
Staging Concepts Memo (7.6 MB) (pdf)
-
Evaluation of Alternatives Summary Memo (4.43 MB) (pdf)
-
Regional Solicitation Document (39.5 MB) (pdf)
-
Funding Application (5.43 MB) (pdf)
-
Visualization - On the Bridge View (1.56 MB) (jpg)
-
Visualization - Northbound 100 Highway View (1.72 MB) (jpg)
FAQs
- What is the Vernon Avenue & Highway 100 Interchange Project?
- How much does the project cost and how is it funded?
- What improvements are being made?
- When is construction happening?
- How will traffic be affected during the project?
- Will access to businesses be maintained?
- What resources are available for area businesses?
- How can I stay informed about the project?
- What are Online Project Talks and how can I join?
- Who can I contact with questions?