Brook Drive Culvert Crossing

Share Brook Drive Culvert Crossing on Facebook Share Brook Drive Culvert Crossing on Twitter Share Brook Drive Culvert Crossing on Linkedin Email Brook Drive Culvert Crossing link

This project will replace the Brook Drive culverts at Nine Mile creek. The existing culverts and stormwater infrastructure has reached the end of its useful life. The project includes improvements to public utilities and stabilization of the creek bank.

Key Information:

  • Planned construction is October/November 2024
  • The project is funded by the stormwater utility fund, there is no special assessed cost to nearby residents.
  • The scope of the replacement includes;
    • Replacement of two culverts with a new box culvert
    • Repair of nearby large diameter concrete storm pipe
    • New sections of road, curb and catch basins
    • Temporary water and watermain replacement
    • Sanitary sewer lining

This project will replace the Brook Drive culverts at Nine Mile creek. The existing culverts and stormwater infrastructure has reached the end of its useful life. The project includes improvements to public utilities and stabilization of the creek bank.

Key Information:

  • Planned construction is October/November 2024
  • The project is funded by the stormwater utility fund, there is no special assessed cost to nearby residents.
  • The scope of the replacement includes;
    • Replacement of two culverts with a new box culvert
    • Repair of nearby large diameter concrete storm pipe
    • New sections of road, curb and catch basins
    • Temporary water and watermain replacement
    • Sanitary sewer lining
  • Final items

    Share Final items on Facebook Share Final items on Twitter Share Final items on Linkedin Email Final items link

    We've made it though the vast majority of construction, the final items include.

    1. Topsoils, seeding and restoration
    2. Guard Rail
    3. Tree planting

    We don't expect any further road impacts. Please let Owen or Ross know if you have any issues or questions with the project closeout.

  • 5/14 Schedule confirmation for 5/15

    Share 5/14 Schedule confirmation for 5/15 on Facebook Share 5/14 Schedule confirmation for 5/15 on Twitter Share 5/14 Schedule confirmation for 5/15 on Linkedin Email 5/14 Schedule confirmation for 5/15 link

    This post is updated with new information:

    Visu-sewer notes that today's work should take them until 9pm and that no night work will be required.

    Thursday 5/14 will be conducted with a modified closure time: A maximum 2-hour road closure around noon to 2pm for take down with crane

  • 5/13 Schedule Update for 5/14

    Share 5/13 Schedule Update for 5/14 on Facebook Share 5/13 Schedule Update for 5/14 on Twitter Share 5/13 Schedule Update for 5/14 on Linkedin Email 5/13 Schedule Update for 5/14 link

    Due to the heat that is predicted for tomorrow Visu-Sewer is moving up the lining operation of the 48” Storm Sewer. The Crane will be coming in at 5am tomorrow. Blocking the road at that time for 5 to 8 hours. If all goes well there will be no overnight work, but work may wrap late.

    Please move any vehicles that need to be used tomorrow outside of the work area to the west.

  • Night work and road closure - schedule update 5/12

    Share Night work and road closure - schedule update 5/12 on Facebook Share Night work and road closure - schedule update 5/12 on Twitter Share Night work and road closure - schedule update 5/12 on Linkedin Email Night work and road closure - schedule update 5/12 link

    5/12 - This post was updated, the schedule was moved back 1 day to Tuesday-Thursday.

    The contractors will begin work on relining the existing storm sewer pipe on Tuesday, 5/13. As part of this work, road closures will be required at the following dates and times:

    • Tuesday, 5/13: 2-hour road closure around 9-11 am for crane set up

    • Wednesday, 5/14: 5-8-hour road closure around 9 am-5 pm for crane work on the liner

    • Wednesday night: Overnight work with high engine idle noise levels and crew on site with lights

    • Thursday, 5/14: 2-hour road closure around 9-11 am for take down of crane

    Please consider parking your vehicle on Brook Drive between Limerick Ln and Hillside Ln if you anticipate needing vehicle access on these days, especially on Tuesday. Thank you for your patience as we wrap up this project.


  • Storm sewer lining - night work and road closures

    Share Storm sewer lining - night work and road closures on Facebook Share Storm sewer lining - night work and road closures on Twitter Share Storm sewer lining - night work and road closures on Linkedin Email Storm sewer lining - night work and road closures link

    As a result of our design change last year caused by the gas company's delay, we choose to install a lining pipe inside the existing concrete sewer pipe. This work is tentatively schedule for the week of 5/12 and needs 72 hours without rain in the forecast.

    The following interruptions are expected as part of this work.

    • Day 1: Approximately 2 hour road closure around 9-11am for set up of tower with crane
    • Day 2: Approximately 5-8 hour road closure around 9am-5pm for crane work for liner
    • Night of Day 2: Overnight work with high engine idle noise levels and crew on site with lights
    • Day 3: Approximately 2 hour road closure around 9-11am for take down of tower with crane

    We'll go door to door to the closest neighbors and those without road access and update this message with details as the schedule develops.

  • Schedule for week of 4/28, 5/5, 5/12

    Share Schedule for week of 4/28, 5/5, 5/12 on Facebook Share Schedule for week of 4/28, 5/5, 5/12 on Twitter Share Schedule for week of 4/28, 5/5, 5/12 on Linkedin Email Schedule for week of 4/28, 5/5, 5/12 link

    The week of 4/21 we are seeing storm manhole, curb and driveway concrete installed.

    Week of 4/28 schedule includes;

    • Grading
    • Topsoil
    • Blacktop driveway

    Week of 5/5 we are scheduled to see

    • Sawcutting and Blacktop patching
    • Sign install
    • Irrigation repair
    • Possible this week include
      • Tree planting
      • guard rail install
      • Final paving

    Week of 5/12

    • Storm Sewer Lining
      • We are working with the contractor to understand the impacts of this activity to traffic and nighttime work and will provide more details in a separate post



  • Sanitary Sewer Lining 4-17 / Schedule for wrap up Week of 4/21

    Share Sanitary Sewer Lining 4-17 / Schedule for wrap up Week of 4/21 on Facebook Share Sanitary Sewer Lining 4-17 / Schedule for wrap up Week of 4/21 on Twitter Share Sanitary Sewer Lining 4-17 / Schedule for wrap up Week of 4/21 on Linkedin Email Sanitary Sewer Lining 4-17 / Schedule for wrap up Week of 4/21 link

    Crews from Visu-Sewer will be on site tomorrow to line the sanitary sewer crossing of the creek.

    Week of 4/21 will the remaining manhole installation, milling of temporary curb and pavement preparation, curb and select driveway work.

  • Winter wrap up, spring planning

    Share Winter wrap up, spring planning on Facebook Share Winter wrap up, spring planning on Twitter Share Winter wrap up, spring planning on Linkedin Email Winter wrap up, spring planning link

    As we close out for the winter, here are the issues we're closing and those that will wait until the Spring;

    Closed out

    • Culvert, utilities, and road base
    • Soil filled rock riprap
    • Seeding and erosion control blanket is in place
    • Temporary barriers and marking at creek crossing
    • Base
    • Temporary pavement on the road and at 3 driveways

    Still to close

    • Street light repair (working with Xcel)

    Spring list

    • Manhole grouting & pipe lining or manhole replacement and new 48"
      pipe
    • Sign installation
    • Curb, 2nd layer of pavement
    • Remove temporary barriers and install guard rail
    • Minor restoration, minor yard / rut repair
    • Tree planting
    • Irrigation repair

    Please review the list and let us know if you are seeing anything else that might be missing.

  • 11/20 Construction Update

    Share 11/20 Construction Update on Facebook Share 11/20 Construction Update on Twitter Share 11/20 Construction Update on Linkedin Email 11/20 Construction Update link

    Paving will begin between 9:00 and 10:00 am on Wednesday. There may be 10-15 minute traffic delays during the paving process. Please consider parking on Brook Drive between McGuire Road and Hillside Lane if you anticipate needing quick access to your vehicle after this time. Thank you for your patience.

  • 11/19 Construction Update

    Share 11/19 Construction Update on Facebook Share 11/19 Construction Update on Twitter Share 11/19 Construction Update on Linkedin Email 11/19 Construction Update link

    This week, the crew is focusing on wrapping up for the winter. Site cleanup and restoration is underway, and a base course will be installed on the roadway. Depending on the weather, this will take place either Tuesday afternoon or on Wednesday. While the base course is being installed, there may be up to 15-minute delays when trying to cross the road. If you anticipate needing to be able to use your vehicle quickly, please consider parking on Brook Drive between McGuire Road and Hillside Lane. We will send out another update when we have confirmation of the time and date of base course installation. Thank you for your patience.