Melody Lake A & B, Birchcrest C and Grandview A Neighborhood Roadway Reconstruction
Consultation has concluded
Melody Lake A & B, Birchcrest C and Grandview A Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!
This project, scheduled for construction in 2021, includes:
- Complete reconstruction of the asphalt pavement,
- Complete reconstruction of the concrete pavement with asphalt pavement,
- Full installation or replacement of concrete curb and gutter,
- Complete replacement of watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems, and
- Construction of a 5-foot concrete sidewalk along
- Hansen Road between West 60th Street and West 56th Street, and
- West 56th Street between Hanson Road and Normandale Road
- A preliminary assessment amount of $17,200 per REU (Apr 2021)
- A revised preliminary assessment amount of $13,600 per REU (Assess Policy Revision Jul 2021)
Melody Lake A & B, Birchcrest C and Grandview A Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!
This project, scheduled for construction in 2021, includes:
- Complete reconstruction of the asphalt pavement,
- Complete reconstruction of the concrete pavement with asphalt pavement,
- Full installation or replacement of concrete curb and gutter,
- Complete replacement of watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems, and
- Construction of a 5-foot concrete sidewalk along
- Hansen Road between West 60th Street and West 56th Street, and
- West 56th Street between Hanson Road and Normandale Road
- A preliminary assessment amount of $17,200 per REU (Apr 2021)
- A revised preliminary assessment amount of $13,600 per REU (Assess Policy Revision Jul 2021)
-
Tips for Growing Green Grass
Share Tips for Growing Green Grass on Facebook Share Tips for Growing Green Grass on Twitter Share Tips for Growing Green Grass on Linkedin Email Tips for Growing Green Grass linkThe turf contractor has applied topsoil, seed and fertilizer to disturbed areas. Tips to help grass grow can be found in this video and briefly summarized below.
- Water - While the contractor is responsible to establish the turf for 90 days, your assistance during this period will help establish the turf more quickly. It is just as important to not over-water the new seed as it is to water the seed. The mulch bed should be moist but not over watered. Continue to water even after grass looks established.
- Fertilize - A commercial fertilizer is applied with the hydroseed. Additional fertilizer and herbicides are not recommended during the initial year of seeding as they can have damaging effects on grass sprouts.
- Mowing - Do not mow new grass until it is 6" high. When grass reaches this height, mow at the highest setting. Cut with this setting for the first few months, even after grass looks established. Do not collect clippings as they help feed the soil while grass develops. Please pass along the mowing recommendations to your lawn care service if you have one.
- Weeding - The contractor is responsible for establishing turf free of weeds. During the initial establishment period, weeding is the responsibility of the contractor, not the residents.
- Preventing Future Weeds - Weeds will likely appear with new grass. Properly watered, mowed and fertilized grass will prevent weeds from gaining a stronghold.
Turf establishment takes time. The City will continue to review the turf in the project area this summer to ensure proper growth.
-
Turf Restoration Update 6/7/2022
Share Turf Restoration Update 6/7/2022 on Facebook Share Turf Restoration Update 6/7/2022 on Twitter Share Turf Restoration Update 6/7/2022 on Linkedin Email Turf Restoration Update 6/7/2022 linkThe Contractor began performing weed removal, seeding, and hydromulching in the areas that only received hydromulch in fall 2022. This work is anticipated to last through the week of 6/13.
-
Turf Restoration Delay
Share Turf Restoration Delay on Facebook Share Turf Restoration Delay on Twitter Share Turf Restoration Delay on Linkedin Email Turf Restoration Delay linkTurf establishment is delayed due to mechanical problems with the contractor’s hydro seeder equipment. Shipping delays on replacement parts are not helping the delay either.
It’s the contractor’s responsibility to establish turf free of weeds, so they will need to take care of the weeds as well. The contractor anticipates resuming work in early June.
We're sorry for the delay. We understand the frustration. The City is frustrated at the lack of progress as well. Thanks for your continued patience.
-
Construction Update - Windsor Ave - 4/22/22
Share Construction Update - Windsor Ave - 4/22/22 on Facebook Share Construction Update - Windsor Ave - 4/22/22 on Twitter Share Construction Update - Windsor Ave - 4/22/22 on Linkedin Email Construction Update - Windsor Ave - 4/22/22 linkWindsor Ave
- Valley Paving is scheduled to begin removing curb and gutter as well as reclaim the asphalt pavement into a gravel driving surface on 4/25.
- Kusske Construction will begin connecting homes to the temporary water service on 4/25. If you aren’t typically home during working hours, check your front door daily for a notice from Kusske Construction regarding scheduling your temporary water hookup.
- Once homes are connected to the temporary watermain, the new watermain installation will begin. The new watermain installation is anticipated to conclude during the week of 5/2.
-
Construction Update 4/18/22
Share Construction Update 4/18/22 on Facebook Share Construction Update 4/18/22 on Twitter Share Construction Update 4/18/22 on Linkedin Email Construction Update 4/18/22 linkPhase 6 - Windsor Ave
Construction Work Resumes
On 4/15 the contractor saw cut driveways to prepare for the temporary watermain setup. The contractor will begin removing driveway and roadway pavement necessary for the watermain work during the week of 4/18.
Watermain and Temporary Water Service Update
The contractor plans to begin temporary water setup and sanitizing the week of 4/18. Kusske Construction anticipates connecting houses to the temporary water system as soon as 4/22. Please check your front door for time sensitive notices, which will include information about scheduling your temporary water hookup. The new watermain and water service installation is scheduled to finish in early May, weather permitting.
Phases 1-5
Irrigation Repairs Resume
The contractor has returned to site to continue repairing the systems damaged during construction. These repairs are expected to continue through mid May.
It's anticipated that seeding, topsoil, and hydromulch work will resume in May. Stay tuned for an updated schedule.
-
Construction Update - Windsor Ave 3/30/2022
Share Construction Update - Windsor Ave 3/30/2022 on Facebook Share Construction Update - Windsor Ave 3/30/2022 on Twitter Share Construction Update - Windsor Ave 3/30/2022 on Linkedin Email Construction Update - Windsor Ave 3/30/2022 linkOn Monday April 4, CenterPoint Energy will begin removing the old 12" steel gas main from under the Windsor Ave roadway surface. Recall that in 2021, a new gas main was installed on the North side of Windsor Ave.
CenterPoint's contact information for this work is:
- csv.constructionservices@centerpointenergy.com
- 612-321-5369 or 612-321-5546
The City's contractor, Valley Paving, is scheduled to begin work on Windsor Ave the week of 4/25, pending CenterPoint Energy completing the gas main removal . Valley Paving will begin with removal of driveways, curb and gutter, and pavement necessary to install the new watermain, water services, and storm sewer. Completion of the Windsor Ave work is anticipated by the end of June 2022.
-
Sanitary Sewer Lining Update
Share Sanitary Sewer Lining Update on Facebook Share Sanitary Sewer Lining Update on Twitter Share Sanitary Sewer Lining Update on Linkedin Email Sanitary Sewer Lining Update linkThe sanitary sewer lining is nearly complete in the project area. The work is expected to be complete by early January 2022.
- Please check your door for this important notice from Hydro Klean to get the details of the work.
- Consider pouring water into floor drains and infrequently used sinks to help reduce the odor from the lining process.
-
2021 Construction Wrap Up - 11/24/2021
Share 2021 Construction Wrap Up - 11/24/2021 on Facebook Share 2021 Construction Wrap Up - 11/24/2021 on Twitter Share 2021 Construction Wrap Up - 11/24/2021 on Linkedin Email 2021 Construction Wrap Up - 11/24/2021 link -
Hansen Rd & W 56th St - Sidewalk Snow Removal
Share Hansen Rd & W 56th St - Sidewalk Snow Removal on Facebook Share Hansen Rd & W 56th St - Sidewalk Snow Removal on Twitter Share Hansen Rd & W 56th St - Sidewalk Snow Removal on Linkedin Email Hansen Rd & W 56th St - Sidewalk Snow Removal linkProperty owners are responsible for clearing snow and ice from the newly installed Hansen Road and West 56th Street sidewalks. According to Edina City Code, Chapter 24, Section 91:
"All snow and ice shall be removed from a sidewalk by the owner of the property adjoining the sidewalk within 48 hours of the cessation of the precipitation."
Note that any snow removed from walkways, driveways or sidewalks must remain on the property and cannot be plowed into City streets or onto a neighboring property. Violation of the City Code could result in a fine and a charge for removing the snow.
Thank you.
-
Construction Update 11/17/2021
Share Construction Update 11/17/2021 on Facebook Share Construction Update 11/17/2021 on Twitter Share Construction Update 11/17/2021 on Linkedin Email Construction Update 11/17/2021 linkPhase 3:
- The contractor will apply hydromulch to the topsoil throughout the phase the week of 11/15.
Phase 4:
- The final layer of asphalt pavement is scheduled to be installed on 11/19.
- The contractor will apply hydromulch to the topsoil throughout the phase the week of 11/15.
Phase 5:
- Mailbox reinstallations are in progress on Hansen Road.
- The final layer of asphalt pavement is scheduled to be installed on 11/19.
- Topsoil placement is complete in the phase, the contractor will apply hydromulch to the topsoil the remainder of the week.
Who's Listening
-
Phone 952-912-2633 Email kmanzke@sehinc.com -
Phone 952-826-0443 Email aditzler@EdinaMN.gov
Key Dates
-
December 07 2020
-
April 20 2021
-
April 21 2021
-
November 2021
Text Notifications
During the project there may be unexpected resident impacts. In addition to providing those notices on the project page you may opt into receiving text notifications.
To sign up text MELODY to 5-7-8-3-8.
Photos
Videos
-
Click here to play video Growing Green Grass Tips to help grow and maintain your grass.
-
Click here to play video Introduction and Agenda Introductions, Agenda, City Engineering Dept
-
Click here to play video Project Areas and Reconstruction Reasons 2021 Project Areas, Why My Street?, Why Street Reconstruction?, Existing Roadway Conditions
Documents
-
Assessment Table - Melody Lake (58.1 KB) (pdf)
-
Construction Kickoff Update & What to Expect (307 KB) (pdf)
-
Melody Lake_Phasing Map.pdf (321 KB) (pdf)
-
Utility Upgrade Letter (925 KB) (pdf)
-
August 2020 Informational Video Presentation Slides (8.57 MB) (pdf)
-
Preliminary Opinion of Market Benefit Letter Report (11 MB) (pdf)
-
BA-457 ENGINEERING STUDY.pdf (18 MB) (pdf)
-
Assessment History.pdf (101 KB) (pdf)
-
2021 Melody Lake A&B Grandview B Birchcrest C Project Area.pdf (279 KB) (pdf)
-
Living Streets Typical Section.pdf (885 KB) (pdf)
-
Pedestrian Facilities Master Plan.pdf (497 KB) (pdf)
-
September 26, 2019 Open House Presentation (5.81 MB) (pdf)
-
August 12, 2019 Neighborhood Reconstruction Presentation (7.71 MB) (pdf)
-
Benton Ave Detour Route.pdf (700 KB) (pdf)
-
Hansen Road Closure & Alternate Route (2.21 MB) (pdf)
-
Hansen Road Closure & Alternate Route - Modified (2.21 MB) (pdf)
-
Sanitary Sewer Lining (984 KB) (pdf)
-
Hansen Road Closure CP Rail - Detour 2023 (2.21 MB) (pdf)