Morningside D & E Neighborhood Roadway Reconstruction

Share Morningside D & E Neighborhood Roadway Reconstruction on Facebook Share Morningside D & E Neighborhood Roadway Reconstruction on Twitter Share Morningside D & E Neighborhood Roadway Reconstruction on Linkedin Email Morningside D & E Neighborhood Roadway Reconstruction link

Morningside D & E Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project began construction in 2022 and will continue in 2023. The work includes:

  • Complete reconstruction of the asphalt pavement,
  • Full replacement of concrete curb and gutter and sidewalk,
  • Replacement of fire hydrants and watermain gate valves. The project will also include new water services between the main in the street and the property’s shut-off valve (curb stop),
  • Improvements to the sanitary sewer and storm sewer systems, including flood risk reduction improvements, and
  • Assessments to property owners for the roadway project costs, at $8,338.95 per residential equivalent unit

Morningside D & E Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project began construction in 2022 and will continue in 2023. The work includes:

  • Complete reconstruction of the asphalt pavement,
  • Full replacement of concrete curb and gutter and sidewalk,
  • Replacement of fire hydrants and watermain gate valves. The project will also include new water services between the main in the street and the property’s shut-off valve (curb stop),
  • Improvements to the sanitary sewer and storm sewer systems, including flood risk reduction improvements, and
  • Assessments to property owners for the roadway project costs, at $8,338.95 per residential equivalent unit
  • Construction Update - 7/21/2023

    Share Construction Update - 7/21/2023 on Facebook Share Construction Update - 7/21/2023 on Twitter Share Construction Update - 7/21/2023 on Linkedin Email Construction Update - 7/21/2023 link

    Project Wide

    • Retaining wall installations continue.
    • Sanitary sewer main cleaning and televising in preparation for lining will begin the week of 7/24. The sewer main will be lined in the weeks following.
    • Replacement of landscaping items impacted by construction is scheduled to begin the week of 7/24.
    • Please contact Nina if your irrigation system has not been restored.
    • Boulevard clean-up will continue into the week of 7/24.
    • To avoid the hot summer temperatures, seeding will begin in August. Likewise, new topsoil will be placed in August prior to seeding to minimize weed growth.
    • The City is aware that the boulevards have weeds. The contractor is responsible for resolving the weed issue and for the subsequent re-seeding. Property owners are not responsible to remove the weeds at this point, but we encourage residents to mow the weeds down. Stay tuned for further details on the Better Together Edina website for next steps.


    Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St

    • Final layer of asphalt tentatively scheduled for end of August.


  • Construction Update - 7/14/2023

    Share Construction Update - 7/14/2023 on Facebook Share Construction Update - 7/14/2023 on Twitter Share Construction Update - 7/14/2023 on Linkedin Email Construction Update - 7/14/2023 link

    W. 42nd Street

    • To avoid the hot summer temperatures, seeding will begin in August. Likewise, new topsoil will be placed in August prior to seeding to minimize weed growth.

    Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St

    • The first layer of asphalt paving is complete. Final layer of asphalt tentatively scheduled for end of August.
    • To avoid the hot summer temperatures, seeding will begin in August. Likewise, new topsoil will be placed in August prior to seeding to minimize weed growth.


    Remainder of the project area

    • Please contact Nina if your irrigation system has not been restored.
    • Retaining wall installations will continue the week of 7/17.
    • The City is aware that the boulevards have weeds. The contractor is responsible for resolving the weed issue and for the subsequent re-seeding. Property owners are not responsible to remove the weeds at this point, but we encourage residents to mow the weeds down. Stay tuned for further details on the Better Together Edina website for next steps.
  • Construction Update - 7/7/2023

    Share Construction Update - 7/7/2023 on Facebook Share Construction Update - 7/7/2023 on Twitter Share Construction Update - 7/7/2023 on Linkedin Email Construction Update - 7/7/2023 link

    W. 42nd Street

    • Concrete work is complete.
    • To avoid the hot summer temperatures, seeding will begin in August. Likewise, new topsoil will be placed in August prior to seeding to minimize weed growth.


    Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St

    • Concrete curb and gutter and sidewalk work is complete.
    • Final roadway gravel grading will continue through 7/7.
    • The first layer of asphalt paving is tentatively scheduled for 7/10.
    • Check your front door for notifications on parking locations during paving.
    • To avoid the hot summer temperatures, seeding will begin in August. Likewise, new topsoil will be placed in August prior to seeding to minimize weed growth.


    Remainder of the project area

    • The irrigation contractor will be back on site to continue restoring systems the week of 7/10. Please contact Nina if your system has not been restored.
    • Retaining wall installations scheduled to begin the week of 7/10.
    • The City is aware that the boulevards have weeds. The contractor is responsible for resolving the weed issue and for the subsequent re-seeding. Property owners are not responsible to remove the weeds at this point, but we encourage residents to mow the weeds down. Stay tuned for further details on the Better Together Edina website for next steps.


  • Construction Update - 6/30/2023

    Share Construction Update - 6/30/2023 on Facebook Share Construction Update - 6/30/2023 on Twitter Share Construction Update - 6/30/2023 on Linkedin Email Construction Update - 6/30/2023 link
    supporting image

    The Contractor will NOT be working Monday 7/3 or Tuesday 7/4.

    W. 42nd Street

    • The remaining concrete items to resume after concrete driveway access to Morningside Rd and Grimes Ave is restored. Likely resuming the week of 7/3.
    • To avoid the hot summer temperatures, seeding will begin in August. Likewise, new topsoil will be placed in August prior to seeding to minimize weed growth.


    Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St

    • Concrete driveway and aprons are complete.
    • Concrete curb and gutter and sidewalk work will continue the week of 7/3.
    • Final roadway grading work will take place the week of 7/3.
    • The first layer of asphalt paving is tentatively scheduled for the week of 7/10.


    Remainder of the project area

    • The irrigation contractor will be back on site to continue restoring systems early July. Please contact Nina if your system has not been restored.
    • Retaining walls scheduled to be installed starting the week of 7/10.
    • Miscellaneous concrete work to continue the week of 7/3.
    • The City is aware that the boulevards have weeds. The contractor is responsible for resolving the weed issue and for the subsequent re-seeding. Property owners are not responsible to remove the weeds at this point, but we encourage residents to mow the weeds down. Stay tuned for further details on the Better Together Edina website for next steps.


    Have a happy and safe 4th of July!

  • Construction Update - 6/23/2023

    Share Construction Update - 6/23/2023 on Facebook Share Construction Update - 6/23/2023 on Twitter Share Construction Update - 6/23/2023 on Linkedin Email Construction Update - 6/23/2023 link

    W. 42nd Street

    • The remaining concrete items to resume after concrete driveway access to Morningside Rd and Grimes Ave is restored. Estimated schedule is early July.
    • To avoid the hot summer temperatures, seeding will begin in August. Likewise, new topsoil will be placed in August prior to seeding to minimize weed growth.


    Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St

    • Concrete curb and gutter, sidewalk, and driveway work will continue the week of 6/26.
      • Please continue to check your front door daily for time sensitive notifications about parking restrictions and appropriate parking locations.
    • The first layer of asphalt paving is tentatively scheduled for early to mid-July.


    Remainder of the project area

    • The irrigation contractor will be back on site to continue restoring systems late June or early July. Please contact Nina if your system has not been restored.
    • Retaining walls scheduled to be rebuilt starting beginning of July.
    • Miscellaneous concrete work to be completed following work on Morningside Rd, Grimes Ave, and W. 42nd St.
    • The City is aware that the boulevards have weeds. The contractor is responsible for resolving the weed issue and for the subsequent re-seeding. Property owners are not responsible to remove the weeds at this point. Stay tuned for further details on the Better Together Edina website for next steps.
  • Construction Update - 6/16/2023

    Share Construction Update - 6/16/2023 on Facebook Share Construction Update - 6/16/2023 on Twitter Share Construction Update - 6/16/2023 on Linkedin Email Construction Update - 6/16/2023 link

    W. 42nd Street

    • The remaining concrete items to be completed in concurrence with Morningside Rd and Grimes Ave, scheduled to begin the week of 6/19.
    • To avoid the hot summer temperatures, seeding will begin in August. Likewise, new topsoil will be placed in August prior to seeding to minimize weed growth.

    Morningside Road, Grimes Avenue between Morningside Rd and W. 44th Street

    • Sump drain and storm sewer work is complete.
    • Remaining Morningside Road sidewalk removals are complete.
    • Roadway excavation and gravel installation is complete.
    • Concrete curb and gutter, sidewalk, and driveway work scheduled to begin the week of 6/19.
      • Please continue to check your front door daily for time sensitive notifications about parking restrictions and appropriate parking locations.
    • The first layer of asphalt paving tentatively scheduled for early July.

    Remainder of the project area

    • The irrigation contractor will be back on site to continue restoring systems the week of 6/19. Please contact Nina if your system has not been restored.
    • Retaining walls scheduled to rebuilt starting the week of 6/19.
    • Miscellaneous concrete work to be completed following work on Morningside Rd, Grimes Ave, and W 42nd St.
    • The City is aware that the boulevards have weeds. The contractor is responsible for resolving the weed issue and for the subsequent re-seeding. Property owners are not responsible to remove the weeds at this point. Stay tuned for further details on the Better Together Edina website for next steps.
  • Construction Update 6/9/2023

    Share Construction Update 6/9/2023 on Facebook Share Construction Update 6/9/2023 on Twitter Share Construction Update 6/9/2023 on Linkedin Email Construction Update 6/9/2023 link

    Please continue to check your front door daily for time sensitive notifications.


    W. 42nd Street

    • Asphalt driveway restoration is complete.
    • The remaining concrete items to be completed in concurrence with Morningside Rd and Grimes Ave, tentatively scheduled to begin the week of 6/19.


    Morningside Road, Grimes Avenue between Morningside Rd and W. 44th St

    • Watermain, storm sewer, and sump drain work is complete on Grimes Avenue.
    • Sump drain and storm sewer work is scheduled to conclude by 6/16 on Morningside Road.
    • Remaining Morningside Road sidewalk removals to be completed by 6/12.
    • Roadway excavation and gravel installation is scheduled to begin the week of 6/12, following completion of utility work.
    • Concrete curb and gutter, sidewalk, and driveway work to begin following roadway excavation and gravel installation activities, tentatively scheduled to begin the week of 6/19.
    • The first layer of asphalt paving tentatively scheduled for early July.


    Remainder of the project area

    • The irrigation contractor will be back on site to continue restoring systems the week of 6/12. Please contact Nina if your system has not been restored.
    • The City is aware that the boulevards have weeds. The contractor is responsible for resolving the weed issue and for the subsequent re-seeding. Property owners are not responsible to remove the weeds at this point. Stay tuned for further details on the Better Together Edina website for next steps.
    • Retaining walls scheduled to rebuilt starting the week of 6/12.
  • Construction Update 6/2/2023

    Share Construction Update 6/2/2023 on Facebook Share Construction Update 6/2/2023 on Twitter Share Construction Update 6/2/2023 on Linkedin Email Construction Update 6/2/2023 link

    Please continue to check your front door daily for time sensitive notifications.

    W. 42nd Street

    • The first layer of asphalt paving is complete.
    • Asphalt driveway restoration is scheduled to be completed by 6/5.
    • The remaining concrete items to be completed in concurrence with Morningside Rd and Grimes Ave, tentatively scheduled for mid-June.

    Morningside Road

    • Water service work is scheduled to begin the week of 6/5 between Lynn and Grimes Aves.
    • Sump drain installation to continue into the week of 6/5 following completion of water services.
    • Remaining sidewalk removals to begin the week of 6/5.
    • Roadway excavation and gravel installation is scheduled to begin the week of 6/12, contingent upon completion of the utility work.
    • Concrete curb and gutter, sidewalk, and driveway work to begin following roadway excavation and gravel installation activities.


    Grimes Avenue between West 44th Street and Morningside Road

    • Water service work is scheduled to continue the week of 6/5.
    • Check your front door daily for more information regarding driveway access loss, and parking requirements.
    • Sump drain installation will occur following completion of the water system improvements.
    • Roadway excavation and gravel installation is scheduled to begin the week of 6/12, contingent upon completion of the utility work.
    • Concrete curb and gutter, sidewalk, and driveway work to begin following roadway excavation and gravel installation activities.

    Remainder of the project area

    • The irrigation contractor will be back on site to continue restoring systems the week of 6/5. Please contact Nina if your system has not been restored.
  • Construction Update 5/26/2023

    Share Construction Update 5/26/2023 on Facebook Share Construction Update 5/26/2023 on Twitter Share Construction Update 5/26/2023 on Linkedin Email Construction Update 5/26/2023 link
    supporting image

    No work will occur on Memorial Day, Monday, May 29.


    Please continue to check your front door daily for time sensitive notifications.


    W. 42nd Street

    • Roadway final grading and the first layer of asphalt paving are tentatively scheduled to begin May 30 and June 1, respectively.
    • The remaining concrete items to be completed in concurrence with Morningside Rd and Grimes Ave


    Morningside Road

    • Watermain improvements are complete, water service work to follow beginning week of 5/29 between Lynn and Grimes Aves.
    • Sump drain installation to continue into week of 5/29.
    • Remaining sidewalk removals to begin in early June.
    • Roadway excavation and gravel installation is scheduled to occur in early June after the utility work is complete.
    • Concrete curb and gutter, sidewalk, and driveway work to begin following roadway excavation and gravel installation activities.



    Grimes Avenue between West 44th Street and Morningside Road

    • Deep storm sewer improvements are complete.
    • Watermain and service related work is scheduled to continue the week of 5/29.
    • Check your front door daily for more information regarding driveway access loss, and parking requirements.
    • Sump drain installation will occur following completion of the watermain improvements.
    • Roadway excavation and gravel installation is scheduled to occur in early June after the utility work is complete.
    • Concrete curb and gutter, sidewalk, and driveway work to begin following roadway excavation and gravel installation activities.



    Remainder of the project area

    • The irrigation contractor resumed restoring systems within all phases of the project completed last year. Please contact Nina if your system has not been restored.
    • Topsoil and seed re-work occurred in most of the areas where paving has been completed.
  • Construction Update - 5/19/2023

    Share Construction Update - 5/19/2023 on Facebook Share Construction Update - 5/19/2023 on Twitter Share Construction Update - 5/19/2023 on Linkedin Email Construction Update - 5/19/2023 link

    Continue checking your front door daily for time sensitive notifications.

    W. 42nd Street

    • Concrete curb and gutter, driveway aprons and concrete driveways are complete with exception of the few small locations.
    • Concrete sidewalk is complete except for the block between Kipling Ave and Grimes Ave, as well as several intersection tie-ins. This work will be completed within a few weeks.
    • Asphalt paving is tentatively scheduled to begin June 1.


    Morningside Road between Crocker Ave and Grimes Ave

    • Deep storm sewer work is complete.
    • Watermain improvements are scheduled to begin the week of 5/22, with water service work to follow.
    • Roadway excavation and gravel installation is scheduled to occur in June after the utility work is complete.


    Grimes Avenue between Branson Street and Morningside Road

    • The contractor will begin the deep storm sewer on Grimes Ave early during the week of 5/22 and likely will conclude by 5/26.
    • Check your front door daily for more information regarding driveway access loss, and parking requirements.
    • Watermain related work is scheduled to begin at the end of May.
    • Roadway excavation and gravel installation is scheduled to occur in June after the utility work is complete.


    Grimes Avenue between West 44th and Branson Streets

    • Water service replacements are scheduled to begin late May.


    Remainder of the project area

    • The irrigation contractor resumed restoring systems on Oakdale Ave and Branson St and will continue restoring systems in the remainder of the project area.
    • Topsoil and seed re-work will begin the week of 5/22 starting with the areas with completed irrigation.