Morningside D & E Neighborhood Roadway Reconstruction

Share Morningside D & E Neighborhood Roadway Reconstruction on Facebook Share Morningside D & E Neighborhood Roadway Reconstruction on Twitter Share Morningside D & E Neighborhood Roadway Reconstruction on Linkedin Email Morningside D & E Neighborhood Roadway Reconstruction link

Morningside D & E Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project began construction in 2022 and will continue in 2023. The work includes:

  • Complete reconstruction of the asphalt pavement,
  • Full replacement of concrete curb and gutter and sidewalk,
  • Replacement of fire hydrants and watermain gate valves. The project will also include new water services between the main in the street and the property’s shut-off valve (curb stop),
  • Improvements to the sanitary sewer and storm sewer systems, including flood risk reduction improvements, and
  • Assessments to property owners for the roadway project costs, at $8,338.95 per residential equivalent unit

Morningside D & E Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!

This project began construction in 2022 and will continue in 2023. The work includes:

  • Complete reconstruction of the asphalt pavement,
  • Full replacement of concrete curb and gutter and sidewalk,
  • Replacement of fire hydrants and watermain gate valves. The project will also include new water services between the main in the street and the property’s shut-off valve (curb stop),
  • Improvements to the sanitary sewer and storm sewer systems, including flood risk reduction improvements, and
  • Assessments to property owners for the roadway project costs, at $8,338.95 per residential equivalent unit
  • Construction Update 8/11/2022

    Share Construction Update 8/11/2022 on Facebook Share Construction Update 8/11/2022 on Twitter Share Construction Update 8/11/2022 on Linkedin Email Construction Update 8/11/2022 link

    Phase 1 Sidewalk

    • The sidewalk installation is scheduled to be complete on 8/12.
    • After the sidewalk has gained adequate strength, crews will prepare the boulevards for topsoil placement.


    Phase 2 – Driveway Aprons and Concrete Driveway Work

    • Driveway aprons and concrete driveway replacements are scheduled to start on 8/11. Check your front door for a notification on this work. You will be asked to park on an adjacent street while work is occurring on your driveway.
    • The first layer of asphalt is now anticipated to be paved during the week of 8/22.


    Phase 3 – W 42nd Street, Grimes Ave between W 42nd & Morningside Rd

    • Due to a rise in the groundwater level after the recent rain event, the storm sewer on Grimes Ave is delayed while the pumps at Weber Pond temporarily lower the water table.
    • Following the sewer work, crews will begin the roadway excavation in advance of concrete curb and gutter.


    Phase 4 – Crocker Ave

    • Crews are scheduled to begin the utility work by replacing the sanitary sewer manholes beginning on 8/11.
    • Following the sanitary manhole work, the crews will begin replacing water services on the East side of the street in advance of the storm sewer work. Anticipate short term water shutoffs.
    • The dewatering well stations that will aid in temporarily lower the groundwater prior to the installation of the storm sewer will be installed the week of 8/15.
  • Crocker Avenue Utility Work

    Share Crocker Avenue Utility Work on Facebook Share Crocker Avenue Utility Work on Twitter Share Crocker Avenue Utility Work on Linkedin Email Crocker Avenue Utility Work link

    As discussed at the resident construction kickoff meeting on May 3, residents on Crocker Ave should anticipate changes to your daily routines due to the contractor installing deep and large diameter storm sewer pipe. Residents should expect the following challenges:

    • Loss of driveway access for up to 48 hours
    • Temporary daytime water shutdowns
    • No parking on Crocker Ave
    • Crocker Ave road closure
    • Potential temporary mailbox bank for mail pickup
    • Temporary relocation of garbage and recycling containers by the contractor due to lack of access for garbage and recycling haulers
    • Pumps and generators running 24 hours per day to temporarily lower the groundwater so the storm sewer work can be completed in a dry environment.

    We do not yet have a firm start date for the deep and large utility work. Further details will be provided by door notification related to the challenges listed above. It’s critical that you check your front door daily for time sensitive information as the work begins.

  • Construction Update 8/5/2022

    Share Construction Update 8/5/2022 on Facebook Share Construction Update 8/5/2022 on Twitter Share Construction Update 8/5/2022 on Linkedin Email Construction Update 8/5/2022 link

    Phase 1 Irrigation and Sidewalk

    • Irrigation system repairs are scheduled to be complete on 8/5.
    • The concrete sidewalk is scheduled to be installed the week of 8/8.
    • Topsoil and seeding work will occur after mid-August when the seed has a higher probability of germinating due to cooler temperatures.


    Phase 2 – Utility Work Complete / Curb and Gutter installation

    • Concrete curb and gutter is being installed and is anticipated to be completed on 8/5.
    • Driveway aprons and concrete driveway replacements are scheduled for the week of 8/8. Check your front door for a notification on this work, including temporary loss of driveway access details.
    • Paving the first layer of asphalt is anticipated to occur during the week of 8/15.


    Phase 3 – W 42nd St, Grimes Ave between W 42nd St & Morningside Rd

    • Water service replacements are complete on Grimes Ave.
    • The crews will now be installing the storm sewer and sump drain on Grimes Ave during the week of 8/8.
    • The West 42nd St schedule is dependent on Xcel Energy relocating utility poles. Xcel Energy continues to delay their relocation work.
    • Following the utility work, crews will begin the roadway excavation in advance of curb and gutter.


    Phase 4 – Crocker Avenue

    • Asphalt pavement reclamation will occur on Crocker Avenue on 8/9, weather permitting. Reclamation is the process of grinding the existing asphalt into a gravel base.
    • Following the pavement reclamation, the crews will remove driveway aprons, sidewalk, and curb and gutter in preparation for the utility work.
    • See the update regarding impactful utility work and resident impacts here.
  • Construction Update 7/28/2022

    Share Construction Update 7/28/2022 on Facebook Share Construction Update 7/28/2022 on Twitter Share Construction Update 7/28/2022 on Linkedin Email Construction Update 7/28/2022 link

    Phase 1 Irrigation and Sidewalk

    • During the week of 7/25, the contractor will prepare the boulevards for the new sidewalk.
    • Irrigation system repairs are in progress throughout the phase, and are anticipated to be complete the week of 8/1.
    • Sidewalk installation is scheduled for the week of 8/8.
    • Topsoil and seeding work will follow the sidewalk work.


    Phase 2 – Utility Work Complete / Street Excavation to begin 7/29

    • The utility work is complete.
    • The contractor will begin installing the new roadway gravel section on 7/29. This work is anticipated to last into the week of 8/1.
    • Curb and Gutter is scheduled to be installed on 8/5.
    • Driveway aprons and concrete driveway replacements are scheduled for the week of 8/8. Check your front door for important updates regarding loss of driveway access.


    Phase 3 – W 42nd Street, Grimes Ave between W 42nd & Morningside Rd - Utility Work Begins

    • The contractor began water service replacement work on Grimes Ave near Morningside Rd.
    • The crews will install the storm sewer on Grimes Ave near W 42nd St early in the week of 8/1.
    • Check your front door for time sensitive information on this work. The water service replacements on Grimes Ave are anticipated to be completed on 8/5.
  • Construction Update 7/22/2022

    Share Construction Update 7/22/2022 on Facebook Share Construction Update 7/22/2022 on Twitter Share Construction Update 7/22/2022 on Linkedin Email Construction Update 7/22/2022 link

    Phase 1 Paving

    • The first layer of asphalt pavement will be placed throughout the phase on 7/22.
    • The concrete driveway aprons and concrete driveway replacements are complete in the phase.
    • During the week of 7/25, the contractor will be preparing the boulevards for the concrete sidewalk.
    • Irrigation system repairs are now anticipated to begin the week of 7/25.


    Phase 2 – Storm Sewer Installation

    • Water service work is complete in the phase. Crews are taking down the temporary above ground watermain and completing the transition to regular water service. Kusske Construction may need to access the basement to finalize this switchover.
    • Storm sewer installation began on 7/18 and is scheduled to be complete on 7/22.
    • Upon completion of the storm sewer, sump drain installation is scheduled to take place early in the week of 7/25. Anyone choosing to make the optional private connection to the sump drain is encouraged to reach out to Evan Acosta to ensure your private connection to the sump drain is feasible.
    • Following the sump drain installation, crews will begin to install the gravel roadway section in advance of concrete curb and gutter. This roadway work is scheduled to begin late in the week of 7/25.


    Phase 3 – W 42nd Street, Grimes Ave between 42nd & Morningside Rd

    • The contractor will begin removing the concrete curb and gutter, driveway aprons, and sidewalks on 7/21.
    • The contractor is scheduled to begin water service replacement work on 7/29 on Grimes Ave. Check your front door for time sensitive information on this work, including brief daytime water shutoffs. The water service replacements on Grimes Ave are anticipated to be completed on 8/5.
    • Following the water service replacements on Grimes Ave, crews will begin installing storm sewer at the north end of Grimes Ave.
  • Construction Update 7/13/2022

    Share Construction Update 7/13/2022 on Facebook Share Construction Update 7/13/2022 on Twitter Share Construction Update 7/13/2022 on Linkedin Email Construction Update 7/13/2022 link

    Phase 1

    • Concrete curb and gutter installation is complete.
    • The concrete driveway aprons and concrete driveway replacements began on 7/12. Check your front door daily for time sensitive notifications.
    • Irrigation system repairs will begin the week of 7/18.


    Phase 2 – Water Service Installations Continue

    • Water service work continues on Branson Street and is scheduled to be complete on 7/15.
    • Once the water services are installed, Kusske Construction will switch you off the temporary above ground water service. They will need to access the basement to finalize this switchover.
    • Storm sewer installation is anticipated to begin on 7/15 and conclude during the week of 7/18.


    Phase 3 – W 42nd Street, Grimes Avenue between W 42nd Street & Morningside Road

    • Due to private utility company delays in relocating West 42nd Street utility poles, the contractor has ­­­­moved Grimes Avenue between West 42nd Street and Morningside Road from phase 4 to phase 3.
    • The new gas main in the roadway of W 42nd Street has been installed by Michels.
    • The contractor will be reclaiming the phase 3 streets on 7/15. Expect short term loss of driveway access during this work.
    • After the removals are complete, crews will begin installing a temporary above ground watermain on West 42nd Street in advance of the watermain work.
  • Construction Update 7/6/2022

    Share Construction Update 7/6/2022 on Facebook Share Construction Update 7/6/2022 on Twitter Share Construction Update 7/6/2022 on Linkedin Email Construction Update 7/6/2022 link

    Phase 1

    • The contractor finished the roadway gravel base installation throughout the phase.
    • US Internet is anticipated to complete installing fiber lines on 7/7.
    • Concrete curb and gutter installation is scheduled to begin on 7/8. The concrete driveway aprons and concrete driveway replacements will follow the curb and gutter installation.


    Phase 2 – Water Service Installations

    • Crews began replacing the Oakdale Ave water services on 7/5. The water service work is scheduled to be complete during the week of 7/11 throughout the phase.
    • Once the water services are installed, Kusske Construction will transition your water service from the the temporary above ground main to the permanent main. They will need to access the basement to finalize this switchover.
    • Following the water service replacements, crews will begin storm sewer and sump drain installation.


    Phase 3 – W 42nd Street

    • Michels, on behalf of CenterPoint Energy, began installing a new gas main in the roadway. This work is anticipated to be completed during the week of 7/11.
    • Work on W 42nd Street will now begin the week of 7/18 with pavement reclamation, curb & gutter removals, and driveway apron removals.
    • After the removals are complete, crews will begin installing a temporary above ground watermain in advance of the watermain work.
  • Construction Update 6/30/2022

    Share Construction Update 6/30/2022 on Facebook Share Construction Update 6/30/2022 on Twitter Share Construction Update 6/30/2022 on Linkedin Email Construction Update 6/30/2022 link
    supporting image

    Phase 1

    • Michels is scheduled to be complete with the new gas main installation in the Lynn Ave roadway on 6/30.
    • The contractor is scheduled to be complete with installing the gravel roadway base on Oakdale Ave and Littel St on 6/30. Crews will install the gravel roadway base on Lynn Ave beginning on 7/1 and concluding on 7/5.
    • Concrete curb and gutter is now anticipated to be installed late in the week of 7/5.


    Phase 2 - Watermain Work to Begin

    • The new watermain has been installed and is now being tested.
    • Water service replacement work will begin during the week of 7/5 and likely conclude the week of 7/11.
    • Following the water service replacements, crews will begin storm sewer and sump drain installation.


    Phase 3 - W 42nd Street

    • Work on W 42nd Street will begin the week of 7/11 with pavement reclamation, curb & gutter removals, and driveway apron removals.
    • After the removals are complete, crews will begin installing a temporary above ground watermain in advance of the watermain work.


    Have a happy and safe Fourth of July!

    • There will be no work on Monday, 7/4.
  • Construction Update 6/23/2022

    Share Construction Update 6/23/2022 on Facebook Share Construction Update 6/23/2022 on Twitter Share Construction Update 6/23/2022 on Linkedin Email Construction Update 6/23/2022 link

    Phase 1

    • Following completion of the existing gas main removal in the roadway, Michels will install the replacement gas main, which is anticipated to conclude on 7/1.
    • Upon completion of the gas main replacement on Lynn Ave, the contractor will begin excavating the streets and installing the new roadway base. This work is still anticipated to begin the week of 6/27 – beginning on Oakdale Ave and Littel St.
    • Following the roadway excavation, concrete curb and gutter will be installed. This work is scheduled for late in the week of 6/27.


    Phase 2

    • The new watermain installation began on 6/21 and is anticipated to be complete on 6/27.
    • Upon completion of the new watermain, crews will begin water service replacement work, which is scheduled to be complete during the week of 7/11. After the water services are installed, the crews will be taking homes off of the temporary water service. The contractor will need access to the home to transition water service from the temporary to the new permanent watermain.


    Phase 3 – W 42nd Street

    • Work on W 42nd Street is scheduled to begin the week of 7/11 with pavement reclamation, curb & gutter removals, and driveway apron removals.
    • After the removals are complete, crews will begin installing a temporary above ground watermain in advance of the watermain work.
  • West 44th Street Road Closure

    Share West 44th Street Road Closure on Facebook Share West 44th Street Road Closure on Twitter Share West 44th Street Road Closure on Linkedin Email West 44th Street Road Closure link

    West 44th St will be closed between Wooddale Avenue and Grimes Avenue beginning on 6/21 for watermain improvements in the Morningside D/E Street Reconstruction Project area. This closure is scheduled through the end of the day on 6/24. The detour route will be France Avenue, West 50th Street, and Brookside Avenue. If you have any questions, contact Evan Acosta.

Page last updated: 17 Apr 2024, 01:08 PM