York Avenue Trunk Sanitary

Share York Avenue Trunk Sanitary on Facebook Share York Avenue Trunk Sanitary on Twitter Share York Avenue Trunk Sanitary on Linkedin Email York Avenue Trunk Sanitary link

The project includes design and construction of a new trunk sanitary sewer pipe and manholes in the southbound lanes of York Avenue (CSAH 31) between the Promenade and 69th Street West intersection. The improvements are listed in the 2023-2028 Capital Improvement Plan (CIP) under CIP #19-335 and are funded by the sanitary sewer utility.

Planned construction is for Summer/Fall 2025

The scope of construction includes;

  • 2 phases of construction over 4 months to construct new and upgraded Sanitary sewer pipe
  • Phased closures of southbound York between the Promenade and 69th Street West
  • New sections of road, curb, crosswalks and catch basins

The project includes design and construction of a new trunk sanitary sewer pipe and manholes in the southbound lanes of York Avenue (CSAH 31) between the Promenade and 69th Street West intersection. The improvements are listed in the 2023-2028 Capital Improvement Plan (CIP) under CIP #19-335 and are funded by the sanitary sewer utility.

Planned construction is for Summer/Fall 2025

The scope of construction includes;

  • 2 phases of construction over 4 months to construct new and upgraded Sanitary sewer pipe
  • Phased closures of southbound York between the Promenade and 69th Street West
  • New sections of road, curb, crosswalks and catch basins
  • Introduction and outreach

    Share Introduction and outreach on Facebook Share Introduction and outreach on Twitter Share Introduction and outreach on Linkedin Email Introduction and outreach link

    The introduction letter is in the mail and calls are already coming in. Here are the key Q&As of interest so far:

    • This work is only in the southbound lane
    • We're working from the south to the north
    • Phase 1a and 1b (Hazelton intersection and south) is split to maintain traffic access for York Plaza and York Condos east and west
    • We're reaching out specifically with three properties with key access constraints
    • Sanitary service is generally not interrupted, we've reached out to one property individually where a <1 day outage is planned
    • We're in design phase now with bidding and contractor selection to follow. We'll share an approximate start date in the Spring once a contractor is selected

    Thanks to everyone who has reached out so far to help inform our work.

  • Project Letter and Introduction

    Share Project Letter and Introduction on Facebook Share Project Letter and Introduction on Twitter Share Project Letter and Introduction on Linkedin Email Project Letter and Introduction link
    supporting image

    A letter will be sent out the week of January 22 introducing the project and welcoming input and questions.

    We understand this road is the only way in and out of several properties and is important for commerce, so we will be including provisions for temporary access and detours.

    Follow this website for more information on design and construction as it develops. If you have questions or comments, please reach out to Ross Bintner at rbintner@edinamn.gov or 952-903-5713.

Page last updated: 12 Jun 2025, 09:17 AM