Concord B & C Neighborhood Roadway Reconstruction
Concord B & C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!
This project, scheduled for construction in 2024, includes:
- Complete reconstruction of the asphalt pavement,
- Complete reconstruction of the concrete pavement with asphalt pavement,
- Full installation or replacement of concrete curb and gutter,
- Complete replacement of the majority of the watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems, and
- Construction of concrete sidewalks or pedestrian facilities along
- Concord Avenue between West 64th Street and Valley View Road
- Wooddale Avenue between Nancy Lane and Valley View Road, and
- West 64th Street between Concord Avenue and Rose Court.
- A preliminary assessment amount of $13,400 per Residential Equivalent Unit was approved by the Council at the December 2023 public hearing. This $13,400 per REU amount has been recorded with Hennepin County as pending assessments for all impacted properties. If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
Concord B & C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!
This project, scheduled for construction in 2024, includes:
- Complete reconstruction of the asphalt pavement,
- Complete reconstruction of the concrete pavement with asphalt pavement,
- Full installation or replacement of concrete curb and gutter,
- Complete replacement of the majority of the watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems, and
- Construction of concrete sidewalks or pedestrian facilities along
- Concord Avenue between West 64th Street and Valley View Road
- Wooddale Avenue between Nancy Lane and Valley View Road, and
- West 64th Street between Concord Avenue and Rose Court.
- A preliminary assessment amount of $13,400 per Residential Equivalent Unit was approved by the Council at the December 2023 public hearing. This $13,400 per REU amount has been recorded with Hennepin County as pending assessments for all impacted properties. If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
-
Construction Update - 9/13/2024
Share Construction Update - 9/13/2024 on Facebook Share Construction Update - 9/13/2024 on Twitter Share Construction Update - 9/13/2024 on Linkedin Email Construction Update - 9/13/2024 linkPLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 9/16 and are WEATHER PERMITTING.
Concord Ave, Ashcroft Ln, W. 63rd St, St. Johns Ave (South of Garrison Ln), Virginia Ln, W 64th St, Millers Ln, Rose Ct, Garrison Ln, Nancy Ln, Wooddale Ave
- Boulevard excavation and topsoil installation are occurring sporadically.
- Sign installation.
- Dave’s Irrigation will continue doing irrigation repairs.
- Please continue to park vehicles in driveways to prevent construction interruptions.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 62nd St, Ashcroft Ave, St. Johns Ave (North of Garrison Ln)
- Removal and replacement of poor soils in preparation for curb and gutter continues.
- Curb and gutter installation is tentatively scheduled to begin on Thursday, 9/19.
- Check your front door daily for notification of temporary driveway access or water loss.
US Internet
US Internet is scheduled to install fiber optic lines in the City right of way beginning the week of 9/16. Completion is expected this fall. Residential internet service likely will not be available until 2025. US Internet contact information can be found on the construction flyer.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
-
Construction Update - 9/6/2024
Share Construction Update - 9/6/2024 on Facebook Share Construction Update - 9/6/2024 on Twitter Share Construction Update - 9/6/2024 on Linkedin Email Construction Update - 9/6/2024 linkPLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 9/9 and are WEATHER PERMITTING.
Concord Ave, Ashcroft Ln, W. 63rd St, St. Johns Ave (South of Garrison Ln), Virginia Ln, W 64th St, Millers Ln, Rose Ct, Garrison Ln, Nancy Ln
- Boulevard excavation and topsoil installation are occurring sporadically.
- Retaining wall installation began.
- Sign installation.
- Dave’s Irrigation will continue doing irrigation repairs throughout the project.
- Please continue to park vehicles in driveways to prevent construction interruptions.
- Check your front door daily for notification of temporary driveway access or water loss.
Wooddale Ave
- Excavation in preparation for sidewalk installation on Wooddale Ave.
- Boulevard excavation and topsoil installation are occurring sporadically.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 62nd St, Ashcroft Ave, St. Johns Ave (North of Garrison Ln)
- Reclaiming of the remaining asphalt on W 62nd St and Ashcroft Ave will take place on Saturday, 9/7. Please have all vehicles off the road before 7:00 am or you may get towed.
- Temporary water is being removed from homes. If you have not contacted Bituminous Roadways, please reach out to Jake Evertz at 651-600-9120 by Monday, 9/9 to avoid interruption.
- Storm sewer installation on St. Johns Ave and Ashcroft Ave.
- Removal and replacement of poor soils in preparation for curb and gutter.
- Check your front door daily for notification of temporary driveway access or water loss.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
-
Construction Update - 8/30/2024
Share Construction Update - 8/30/2024 on Facebook Share Construction Update - 8/30/2024 on Twitter Share Construction Update - 8/30/2024 on Linkedin Email Construction Update - 8/30/2024 linkCrews will not be working during the Monday, 9/2 Labor Day holiday. PLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 9/2 and are WEATHER PERMITTING.
Concord Ave, Ashcroft Ln, W. 63rd St, St. Johns Ave (South of Garrison Ln), Virginia Ln, W 64th St, Millers Ln, Rose Ct, Garrison Ln, Nancy Ln,
- Excavation in preparation for topsoil and retaining walls is occurring sporadically.
- Dave’s Irrigation will continue doing irrigation repairs throughout the project.
- Please continue to park vehicles in driveways to prevent construction interruptions.
- Check your front door daily for notification of temporary driveway access or water loss.
Wooddale Ave
- Excavation in preparation for sidewalk installation on Wooddale Ave.
- Excavation in preparation for topsoil is occurring sporadically.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 62nd St, Ashcroft Ave, St. Johns Ave (North of Garrison Ln)
- Installation of new water services will continue into the week of 9/2.
- Storm sewer installation at the intersection of St. Johns Ave and W 62nd St
- Check your front door daily for notification of temporary driveway access or water loss.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
-
Construction Update- 8/23/2024
Share Construction Update- 8/23/2024 on Facebook Share Construction Update- 8/23/2024 on Twitter Share Construction Update- 8/23/2024 on Linkedin Email Construction Update- 8/23/2024 linkPLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 8/26 and are WEATHER PERMITTING.
W 64th St, Millers Ln, Rose Ct
- Excavation in preparation for topsoil is occurring sporadically.
- Check your front door daily for notification of temporary driveway access or water loss.
- Watermain lining at the intersection of W 64th St/ Ashcroft Ln will continue into the week of 8/26. Please use alternate routes.
Concord Ave, Ashcroft Ln, W. 63rd St, St. Johns Ave (South of Garrison Ln), Virginia Ln
- Excavation in preparation for topsoil and retaining walls is occurring sporadically.
- Irrigation repairs continue on Concord Ave. Dave’s Irrigation will begin doing irrigation repairs on the remainder of the streets.
- Please continue to park vehicles in driveways to prevent construction interruptions.
- Check your front door daily for notification of temporary driveway access or water loss.
Garrison Ln, Nancy Ln, Wooddale Ave
- Driveway installations will continue Saturday, 8/24 and Monday, 8/26.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 62nd St, Ashcroft Ave, St. Johns Ave (North of Garrison Ln)
- Installation of new water services will begin the week of 8/26.
- Check your front door daily for notification of temporary driveway access or water loss.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
-
Construction Update- 8/16/2024
Share Construction Update- 8/16/2024 on Facebook Share Construction Update- 8/16/2024 on Twitter Share Construction Update- 8/16/2024 on Linkedin Email Construction Update- 8/16/2024 linkPLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 8/19 and are WEATHER PERMITTING.
Traffic Update
- A map visualizing this traffic update can be found here.
W 64th St, Millers Ln, Rose Ct
- Excavation in preparation for topsoil is occurring sporadically.
- Check your front door daily for notification of temporary driveway access or water loss.
- Watermain lining at the intersection of W 64th St / Ashcroft Ln is scheduled for the week of 8/19. Please use alternate routes.
Concord Ave, Ashcroft Ln, W. 63rd St, St. Johns Ave (South of Garrison Ln), Virginia Ln
- Excavation in preparation for topsoil and retaining walls is occurring sporadically.
- Irrigation repairs continue on Concord Ave. Dave’s Irrigation will begin doing irrigation repairs on the remainder of the streets.
- Please continue to park vehicles in driveways to prevent construction interruptions.
- Check your front door daily for notification of temporary driveway access or water loss.
Garrison Ln, Nancy Ln, Wooddale Ave
- Removal and replacement of poor soils in preparation for curb and gutter will continue.
- Curb and gutter installation is tentatively scheduled for 8/23.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 62nd St, Ashcroft Ave, St. Johns Ave (North of Garrison Ln)
- Installation of the new watermain continues.
- Check your front door daily for notification of temporary driveway access or water loss.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
-
Construction Update - 8/9/2024
Share Construction Update - 8/9/2024 on Facebook Share Construction Update - 8/9/2024 on Twitter Share Construction Update - 8/9/2024 on Linkedin Email Construction Update - 8/9/2024 linkPLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 8/9 and are WEATHER PERMITTING.
W 64th St, Millers Ln, Rose Ct
- Excavation in preparation for topsoil is occurring sporadically.
- Check your front door daily for notification of temporary driveway access or water loss.
- Watermain lining at the W 64th St / Ashcroft Ln intersection is scheduled for the week of 8/19.
Concord Ave, Ashcroft Ln, W. 63rd St, St. Johns Ave (South of Garrison Ln), Virginia Ln
- Excavation in preparation for topsoil and retaining walls is occurring sporadically.
- Irrigation repairs continue on Concord Ave. Dave’s Irrigation will begin doing irrigation repairs on the remainder of the streets.
- Please continue to park vehicles in driveways to prevent construction interruptions.
- Check your front door daily for notification of temporary driveway access or water loss.
Garrison Ln, Nancy Ln, Wooddale Ave
- Installation of the new water services will continue.
- Storm sewer installation.
- Reclaiming is scheduled for Tuesday, 8/13. Reclaiming is the process of grinding the existing asphalt into a gravel base.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 62nd St, Ashcroft Ave, St. Johns Ave (North of Garrison Ln)
- Temporary water setup in preparation for water main replacement will continue.
- The Contractor will be sending out notifications to coordinate a time to connect homes to temporary water on Friday, 8/9.
- Reclaiming is scheduled for Tuesday, 8/13. Reclaiming is the process of grinding the existing asphalt into a gravel base.
- Installation of the new watermain.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
-
Construction Update- 8/2/2024
Share Construction Update- 8/2/2024 on Facebook Share Construction Update- 8/2/2024 on Twitter Share Construction Update- 8/2/2024 on Linkedin Email Construction Update- 8/2/2024 linkPLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 8/5 and are WEATHER PERMITTING.
Traffic Update
- A map visualizing this traffic update can be found here.
Millers Ln, and Rose Ct
- Excavation in preparation for topsoil is occurring sporadically.
W 64th St
- Sidewalk installation west of Ashcroft Ln.
Concord Ave
- Excavation in preparation for topsoil and retaining walls is occurring sporadically.
- Irrigation repairs continue.
- Please continue to park vehicles in driveways to prevent construction interruptions.
- Check your front door daily for notification of temporary driveway access or water loss.
Ashcroft Ln, W. 63rd St, St. Johns Ave (South of Garrison Ln), Virginia Ln
- Driveway access restoration will occur.
- Concrete curb will continue Monday, 8/5 on Ashcroft Ln and St Johns Ave
- Roadway preparation for asphalt paving.
- The first layer of asphalt paving is tentatively scheduled for Friday, 8/9.
- Check your front door daily for notification of temporary driveway access or water loss.
Garrison Ln, Nancy Ln, and Wooddale Ave
- Installation of the new water services will continue.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 62nd St, Ashcroft Ave, St. Johns Ave (North of Garrison Ln)
- Temporary water setup in preparation for water main replacement will continue.
- The Contractor will send out notifications to coordinate a time to connect homes to temporary water.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
-
Construction Update - 7/26/2024
Share Construction Update - 7/26/2024 on Facebook Share Construction Update - 7/26/2024 on Twitter Share Construction Update - 7/26/2024 on Linkedin Email Construction Update - 7/26/2024 linkAs construction begins on your street, PLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 7/29 and are WEATHER PERMITTING.
Traffic Update
- The intersection of Wooddale Ave / Valley View Road will be closed on 7/29 through 7/30. Please use alternative routes.
- A map visualizing this traffic update can be found here.
W 64th St, Millers Ln, and Rose Ct
- Excavation in preparation for topsoil is occurring sporadically.
- Curb and sidewalk installation west of St. Johns Ave.
Concord Ave
- Excavation in preparation for topsoil and retaining walls is occurring sporadically.
- Irrigation repairs will begin.
- Please continue to park vehicles in driveways or on adjacent streets to prevent construction interruptions.
- Check your front door daily for notification of temporary driveway access or water loss.
Ashcroft Ln
- Removal and replacement of poor soils in preparation for curb and gutter will continue between West 63rd St and St. Johns Ave.
- Storm sewer installation at the intersection of Ashcroft Ln and St Johns Ave.
- Installation of curb and gutter followed by concrete driveway restoration is tentatively scheduled to begin on Wednesday, 7/31.
- Check your front door daily for notification of temporary driveway access or water loss.
St. Johns Ave south of Garrison Ln
- Removal of the remaining concrete on the west side of the street, followed by the removal and replacement of poor soils in preparation for curb and gutter.
- Installation of curb and gutter followed by concrete driveway replacements is tentatively scheduled to begin on Wednesday, 7/31.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 63rd St
- Installation of curb and gutter followed by driveway replacements is tentatively scheduled to begin on Wednesday, 7/31.
Garrison Ln, Nancy Ln, and Wooddale Ave
- Installation of the new water main and water services will continue.
- Check your front door daily for notification of temporary driveway access or water loss.
Virginia Ln
- Installation of curb and gutter followed by driveway replacements is tentatively scheduled to begin on Wednesday, 7/31.
W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln
- Temporary water will begin to be setup in preparation for water main replacement.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
-
Construction Update - 7/19/2024
Share Construction Update - 7/19/2024 on Facebook Share Construction Update - 7/19/2024 on Twitter Share Construction Update - 7/19/2024 on Linkedin Email Construction Update - 7/19/2024 linkAs construction begins on your street, PLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 7/22 and are WEATHER PERMITTING.
Traffic Update
- The intersection of Wooddale Ave and Valley View Road will be closed for the week of 7/22. Please use alternative routes.
- A map visualizing this traffic update can be found here.
W 64th St, Millers Ln, and Rose Ct
- Excavation in preparation for topsoil is occurring sporadically.
- Concrete sidewalk and pedestrian ramp installation on W 64th St. has been tentatively scheduled for 7/25.
Concord Ave
- Concrete sidewalk installation is tentatively scheduled for Thursday 7/25 and Friday 7/26.
- Please continue to park vehicles in driveways or on adjacent streets to prevent construction interruptions.
- Check your front door daily for notification of temporary driveway access or water loss.
Ashcroft Ln
- Removal and replacement of poor soils in preparation for curb and gutter will continue between West 63rd and 64th Sts.
- Completing storm sewer installation at the intersection of Ashcroft Ln and St Johns Ave.
- Check your front door daily for notification of temporary driveway access or water loss.
St. Johns Ave south of Garrison Ln
- Removal of the remaining concrete on the west side of the street, followed by the removal and replacement of poor soils in preparation for curb and gutter.
- Removal of temporary water service from homes is scheduled to be complete by 7/26.
- Check your front door daily for notification of temporary driveway access or water loss.
W. 63rd St, Garrison Ln, Nancy Ln, and Wooddale Ave
- Installation of the new water main.
- Check your front door daily for notification of temporary driveway access or water loss.
Virginia Ln
- Removal and replacement of poor soils in preparation for curb and gutter.
W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln – Work tentatively scheduled to begin early August.
Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
-
Wooddale Avenue Closure 7/18 - 7/25
Share Wooddale Avenue Closure 7/18 - 7/25 on Facebook Share Wooddale Avenue Closure 7/18 - 7/25 on Twitter Share Wooddale Avenue Closure 7/18 - 7/25 on Linkedin Email Wooddale Avenue Closure 7/18 - 7/25 linkWooddale Avenue between Valley View Road and Garrison Lane is scheduled to be closed beginning on Thursday, 7/18 until 7/25 for watermain improvements. Sorry for the inconvenience and we thank you for your patience.
Email Signup
Sign Up for Emailed Project Updates
PRIVACY NOTICE: Under M.S. 13.356, your email address is private data. If you do not provide an email address you will not receive requested updates. Your email address will be available to anyone with a work assignment that reasonably require access.
Who's Listening
-
Phone 952-826-0448 Email BFreeman@Edinamn.gov -
Phone 952-826-0443 Email aditzler@EdinaMN.gov
Text Notifications
During the project there may be unexpected time sensitive resident impacts. In addition to providing those notices on the project page you may opt into receiving text notifications.
To sign up text CONCORD to 844-929-4328.
Key Dates
-
April 15 2024
-
April 02 2024
-
December 19 2023
-
December 11 2023
Videos
Documents
-
Concord B C Project Area (150 KB) (pdf)
-
Construction Phasing Map (1.55 MB) (pdf)
-
Construction Kickoff Update & What to Expect (75.8 KB) (docx)
-
Utility Upgrade Letter (805 KB) (pdf)
-
Proposed Road Widths, Parking, Sidewalk, Shared Use Path Details (3.07 MB) (pdf)
-
Pedestrian Facilities Master Plan (1.98 MB) (pdf)
-
Bicycle Facilities Master Plan (1.96 MB) (pdf)
-
Living Streets Typical Section.pdf (885 KB) (pdf)
-
Video Presentation Slides - 2024 Projects (10 MB) (pdf)
-
Assessment History (101 KB) (pdf)
-
Estimated Market Benefit - Concord B/C (5.82 MB) (pdf)
-
Concord B/C Engineering Study (11.1 MB) (pdf)
-
Concord B/C - Estimated Market Benefit (5.82 MB) (pdf)
-
Concord Plans (14.2 MB) (pdf)
-
Traffic Map Week of 8/19/24 (898 KB) (pdf)
-
US Internet Flyer (195 KB) (pdf)
-
Sod Care Flyer October 2024 (68.2 KB) (docx)