Presidents A & B Neighborhood Roadway Reconstruction

Share Presidents A & B Neighborhood Roadway Reconstruction on Facebook Share Presidents A & B Neighborhood Roadway Reconstruction on Twitter Share Presidents A & B Neighborhood Roadway Reconstruction on Linkedin Email Presidents A & B Neighborhood Roadway Reconstruction link

Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2025 construction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete reconstruction of two alleys west of Madison Avenue,
  • Complete replacement of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Proposed construction of multi-modal facilities along:
    • Monroe Avenue (5' sidewalk)
    • Belmore Lane (8' shared use path)
    • Washington Avenue (8' shared use path)
  • The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
  • A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
  • An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
  • If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.

Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2025 construction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete reconstruction of two alleys west of Madison Avenue,
  • Complete replacement of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Proposed construction of multi-modal facilities along:
    • Monroe Avenue (5' sidewalk)
    • Belmore Lane (8' shared use path)
    • Washington Avenue (8' shared use path)
  • The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
  • A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
  • An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
  • If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
  • Construction Update – 8/1/2025

    Share Construction Update – 8/1/2025 on Facebook Share Construction Update – 8/1/2025 on Twitter Share Construction Update – 8/1/2025 on Linkedin Email Construction Update – 8/1/2025 link

    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Concrete path installation along Belmore Lane is complete.
    • Excavation in preparation for topsoil installation will continue the week of 8/4.
    • Retaining wall installation is scheduled to begin the week of 8/4.


    Alleys west of Madison Avenue

    • The concrete valley gutter and curb installation is complete.
    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Water service installations are complete on Monroe and Madison Ave.
    • Storm sewer and sump line installation will continue the week of 8/4.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 8/4.
    • Temporary water line installation is scheduled to continue into the week of 8/4.



  • Construction Update – 7/25/2025

    Share Construction Update – 7/25/2025 on Facebook Share Construction Update – 7/25/2025 on Twitter Share Construction Update – 7/25/2025 on Linkedin Email Construction Update – 7/25/2025 link

    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Asphalt driveways are complete.
    • Excavation in preparation for topsoil installation will begin the week of 7/28.
    • Installation of the concrete path along Belmore Lane is scheduled for the week of 7/28.


    Alleys west of Madison Avenue

    • A short portion of the alley will receive concrete curb and valley gutter for drainage purposes. Concrete installation is scheduled for Monday, 7/28.
    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Water service installation on Monroe Ave is scheduled to continue the week of 7/28.
    • Water service installation on Madison Ave is complete.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 7/28.
    • Temporary water lines are scheduled to be setup the week of 7/28.



  • Construction Update - 7/18/2025

    Share Construction Update - 7/18/2025 on Facebook Share Construction Update - 7/18/2025 on Twitter Share Construction Update - 7/18/2025 on Linkedin Email Construction Update - 7/18/2025 link

    Project Area

    • See the UPDATED construction phasing map.


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • The first layer of asphalt paving is complete.
    • Asphalt driveways are scheduled for paving the week of 7/21.
    • Excavation in preparation for topsoil installation will begin the week of 7/21.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Watermain replacement is complete on Monroe and Madison Aves.
    • Water service installation will continue the week of 7/21.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 7/21.


  • Construction Update - 7/11/2025

    Share Construction Update - 7/11/2025 on Facebook Share Construction Update - 7/11/2025 on Twitter Share Construction Update - 7/11/2025 on Linkedin Email Construction Update - 7/11/2025 link

    Project Area

    • The neighborhood phasing map has changed for the second consecutive week. See the UPDATED construction phasing map.


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Concrete curb and gutter installation is complete. Driveways will be accessible by the end of the day on Wednesday, 7/16.
    • The first layer of asphalt paving is scheduled for Thursday, 7/17, weather permitting.
    • Asphalt driveways will be replaced at a later date.


    Alleys west of Madison Avenue

    • Storm sewer replacement in the alley between Madison Ave and Jefferson Ave is complete.
    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Watermain replacement is complete on Monroe and Madison Aves.
    • Water service installation will begin the week of 7/14.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave and Washington Ave are scheduled to begin on Monday, 7/14.


  • Construction Update – 7/3/2025

    Share Construction Update – 7/3/2025 on Facebook Share Construction Update – 7/3/2025 on Twitter Share Construction Update – 7/3/2025 on Linkedin Email Construction Update – 7/3/2025 link
    supporting image

    No work will occur on Friday, 7/4. Have a safe and happy Happy 4th of July!


    Project Area

    • The neighborhood phasing map has CHANGED. See the UPDATED construction phasing map.


    Phase 1

    • Vehicles cannot be parked on the street during construction.
    • Roadway excavation on Van Buren Ave is complete.
    • Concrete curb and gutter installation is scheduled to begin on Tuesday, 7/8 weather permitting.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Alleys west of Madison Avenue

    • Storm sewer replacement in the alley between Madison Ave and Jefferson Ave has been rescheduled for the week of 7/7.
    • Alley paving will occur at a future date when the roadways are paved.


    Phase 2

    • Temporary water line installation is complete.
    • Watermain replacement on Monroe Ave will continue into the week of 7/7.
    • Watermain replacement on Madison Ave is scheduled to begin the week of 7/7.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 3

    • Reclaiming the road pavement is scheduled for 7/9. Reclaiming is the process of grinding the existing asphalt into a gravel base.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


  • Construction Update - 6/27/2025

    Share Construction Update - 6/27/2025 on Facebook Share Construction Update - 6/27/2025 on Twitter Share Construction Update - 6/27/2025 on Linkedin Email Construction Update - 6/27/2025 link

    PLEASE consistently check your front door daily for time sensitive notifications.


    Project Area

    • See the construction phasing map here.


    Phase 1

    • Vehicles cannot be parked on the street during construction.
    • Roadway excavation on Van Buren Ave is scheduled to begin Monday, 6/30.
    • Sump line installation on Van Buren Ave is complete.
    • Roadway excavation on Jackson Ave in preparation for curb and gutter is complete.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Alleys west of Madison Avenue

    • Storm sewer replacement in the alley between Madison Ave and Jefferson Ave is scheduled for the week of 6/30.
    • Alley paving will occur at a future date when the roadways are paved.


    Phase 2

    • Temporary water line installation is complete.
    • Watermain replacement on Monroe Ave has been rescheduled to begin on 7/2 due to weather delays.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


  • Construction Update - 6/20/2025

    Share Construction Update - 6/20/2025 on Facebook Share Construction Update - 6/20/2025 on Twitter Share Construction Update - 6/20/2025 on Linkedin Email Construction Update - 6/20/2025 link

    PLEASE consistently check your front door daily for time sensitive notifications.


    Project Area

    • See the construction phasing map here.


    Phase 1

    • Vehicles cannot be parked on the street during construction.
    • Water service installation on Van Buren Ave is complete.
    • Sump line installation on Van Buren Ave will continue the week of 6/23.
    • Roadway excavation on Jackson Ave is scheduled to begin Monday, 6/23 at 6:30am.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Alleys west of Madison Avenue

    • Storm sewer replacement in the alley between Madison Ave and Jefferson Ave is scheduled for the week of 6/23.
    • Alley paving will occur at a future date when the roadways are paved.


    Phase 2

    • Temporary water line installation continues the week of 6/23.
    • Watermain replacement on Monroe Ave is scheduled to begin on Wednesday, 6/25.
    • Check your front door daily for notification of temporary driveway access or water loss.


    CenterPoint Energy

    • CenterPoint Energy's work is not part of the City's Presidents Neighborhood Roadway Reconstruction contract.
    • Maloney Avenue is scheduled to open to traffic later during the week of 6/23
    • All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at csv.constructionservices@centerpointenergy.com, 612-321-5369 or 612-542-6198.


    Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


  • Construction Update – 6/13/2025

    Share Construction Update – 6/13/2025 on Facebook Share Construction Update – 6/13/2025 on Twitter Share Construction Update – 6/13/2025 on Linkedin Email Construction Update – 6/13/2025 link

    PLEASE consistently check your front door daily for time sensitive notifications.


    Project Area

    • See the construction phasing map here.


    Phase 1

    • Vehicles cannot be parked on the street during construction.
    • Storm sewer installation will continue the week of 6/16.
    • Water service installation on Van Buren Ave will continue into the week of 6/16.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the roadways are paved.


    Phase 2

    • Temporary water line installation continues the week of 6/16.
    • Check your front door daily for notification of temporary driveway access or water loss.


    CenterPoint Energy

    • CenterPoint Energy's work is not part of the City's Presidents Neighborhood Roadway Reconstruction contract.
    • For additional information regarding the Maloney Avenue road closure can be found here.
    • All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at csv.constructionservices@centerpointenergy.com, 612-321-5369 or 612-542-6198.


    Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


  • Construction Update - 6/6/2025

    Share Construction Update - 6/6/2025 on Facebook Share Construction Update - 6/6/2025 on Twitter Share Construction Update - 6/6/2025 on Linkedin Email Construction Update - 6/6/2025 link

    PLEASE consistently check your front door daily for time sensitive notifications.


    Project Area

    • See the construction phasing map here.


    Phase 1

    • Vehicles cannot be parked on the street during construction.
    • Storm sewer installation will begin the week of 6/9.
    • Water service installation on Jackson Ave is complete.
    • Watermain service installation begins on Van Buren Ave the week of 6/9.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the roadways are paved.


    Phase 2

    • Curb and gutter removal is complete.
    • Temporary water line installation begins the week of 6/9.


    CenterPoint Energy

    • CenterPoint Energy's work is not part of the City's Presidents Neighborhood Roadway Reconstruction contract.
    • For additional information regarding the Maloney Avenue road closure can be found here.
    • All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at csv.constructionservices@centerpointenergy.com, 612-321-5369 or 612-542-6198.


    Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.



  • Construction Update – 5/30/2025

    Share Construction Update – 5/30/2025 on Facebook Share Construction Update – 5/30/2025 on Twitter Share Construction Update – 5/30/2025 on Linkedin Email Construction Update – 5/30/2025 link

    Project Area

    • See the construction map here.


    Phase 1

    • Vehicles cannot be parked on the street during construction.
    • Water service installation on Jackson Ave will continue the week of 6/2.
    • Watermain installation on Van Buren Ave will continue the week of 6/2.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Alleys west of Madison Avenue

    • Washington Avenue alley excavation work is complete.
    • Alley paving will occur at a future date when the roadways are paved.


    Phase 2

    • Curb and gutter removal is scheduled to continue into the week of 6/2.


    CenterPoint Energy

    • CenterPoint Energy's work is not part of the City's Presidents Neighborhood Roadway Reconstruction contract.
    • For additional information regarding the Maloney Avenue road closure can be found here.
    • All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at csv.constructionservices@centerpointenergy.com, 612-321-5369 or 612-542-6198.


    Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.