Presidents A & B Neighborhood Roadway Reconstruction
Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!
This 2025 construction project includes:
- Complete reconstruction of the roadway asphalt pavement,
- Full installation or replacement of concrete curb and gutter,
- Complete reconstruction of two alleys west of Madison Avenue,
- Complete replacement of the watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems, and
- Proposed construction of multi-modal facilities along:
- Monroe Avenue (5' sidewalk)
- Belmore Lane (8' shared use path)
- Washington Avenue (8' shared use path)
- The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
- A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
- An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
- If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!
This 2025 construction project includes:
- Complete reconstruction of the roadway asphalt pavement,
- Full installation or replacement of concrete curb and gutter,
- Complete reconstruction of two alleys west of Madison Avenue,
- Complete replacement of the watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems, and
- Proposed construction of multi-modal facilities along:
- Monroe Avenue (5' sidewalk)
- Belmore Lane (8' shared use path)
- Washington Avenue (8' shared use path)
- The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
- A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
- An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
- If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
-
Sidewalk Snow Removal
Share Sidewalk Snow Removal on Facebook Share Sidewalk Snow Removal on Twitter Share Sidewalk Snow Removal on Linkedin Email Sidewalk Snow Removal link
Property owners are responsible for snow removal on the sidewalks adjoining their property as shown here.
To keep pedestrians safe, sidewalks must be cleared of all ice and snow during the winter. According to Edina City Code 1200.03, "All snow and ice shall be removed from a sidewalk by the owner of the property adjoining the sidewalk within 48 hours of the cessation of the precipitation." This means property owners must clear sidewalks of all snow or ice within two days of the end of a snowfall. Any snow removed from walkways, driveways or sidewalks must remain on the property. Snow cannot be plowed into City streets or onto a neighboring property.
If snow and ice are not removed within seven days after receiving a written notice from the City, residents may be charged for the cost of removal by the City.
-
Construction Update - 11/28/2025
Share Construction Update - 11/28/2025 on Facebook Share Construction Update - 11/28/2025 on Twitter Share Construction Update - 11/28/2025 on Linkedin Email Construction Update - 11/28/2025 linkConstruction Update – 11/28/2025
Project Area
- All work dates below are weather permitting.
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Sanitary Sewer Lining – Phases 1 and 2
Visu-Sewer will be lining the City’s sanitary sewer main via access through manholes in the street. The lining is scheduled to begin in the project area on Monday, 12/1 and is anticipated to be complete by late December.
- Limiting major water use is required to avoid a sewer backup.
- Avoid running your washing machine or dishwasher during this 8-12 hour period of work or you risk your sewer backing up.
- Pungent odors from the lining process are common.
- To prevent odors in your home, pour a gallon of water into floor drains and any infrequently used sinks.
- Check your front door daily for details and notice of this work occurring on your street.
- The notice will include information on the process, and approximate length of time your water usage should be minimized.
- See example door notice here.
Phases 1, 2, 3
- Retaining wall installation is ongoing as long as weather permits.
- Landscape restoration is complete for the season. Any remaining work will be completed when the project resumes in the spring of 2026.
Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue
The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.
We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.
-
Construction Update – 11/20/2025
Share Construction Update – 11/20/2025 on Facebook Share Construction Update – 11/20/2025 on Twitter Share Construction Update – 11/20/2025 on Linkedin Email Construction Update – 11/20/2025 linkConstruction Update – 11/21/2025
Project Area
- All work dates below are weather permitting.
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Sanitary Sewer Lining – Phases 1 and 2
Visu-Sewer will be lining the City’s sanitary sewer main via access through manholes in the street. The lining is scheduled to begin in the project area on Monday, 12/1 and is anticipated to be complete by late December.
- Limiting major water use is required to avoid a sewer backup.
- Avoid running your washing machine or dishwasher during this 8-12 hour period of work or you risk your sewer backing up.
- Pungent odors from the lining process are common.
- To prevent odors in your home, pour a gallon of water into floor drains and any infrequently used sinks.
- Check your front door daily for details and notice of this work occurring on your street.
- The notice will include information on the process, and approximate length of time your water usage should be minimized.
- See example door notice here.
Phases 1, 2, 3
- Temporary pavement striping will be placed on Washington Ave.
- Retaining wall installation is scheduled to be completed by late November.
- The landscape contractor will be replacing impacted landscaping as long as weather permits. Any remaining work will be completed when the project resumes in the spring of 2026.
- The final layer of asphalt is complete.
- Street sign installation is complete.
Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue
The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.
We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.
-
Construction Update - 11/14/2025
Share Construction Update - 11/14/2025 on Facebook Share Construction Update - 11/14/2025 on Twitter Share Construction Update - 11/14/2025 on Linkedin Email Construction Update - 11/14/2025 linkProject Area
- All work dates below are weather permitting.
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- Grass and leaves cannot be blown or raked into the street.
- Supplemental Street sweeping increases the project costs and slows the contractors progress
- See the following link for Yard Waste guidelines(External link)
Phases 1, 2, 3
- The final layer of asphalt for Washington Ave and 3rd St is scheduled for Monday, 11/17.
- Tree replacements are scheduled for the week of 11/17.
- Retaining wall installation is scheduled to be completed by late November.
- Sod installation is complete for the season.
- Street sign installation is complete.
- The landscape contractor will be replacing impacted landscaping as long as weather permits. Any remaining work will be completed when the project resumes in the spring of 2026.
Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue
The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.
We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.
-
Construction Update - 11/7/2025
Share Construction Update - 11/7/2025 on Facebook Share Construction Update - 11/7/2025 on Twitter Share Construction Update - 11/7/2025 on Linkedin Email Construction Update - 11/7/2025 linkProject Area
- All work dates below are weather permitting.
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- Grass and leaves cannot be blown or raked into the street.
- Supplemental Street sweeping increases the project costs and slows the contractors progress
- See the following link for Yard Waste guidelines
Phases 1, 2, 3
- The final layer of asphalt paving is tentatively scheduled for the week of 11/10.
- Sod installation is scheduled to continue the week of 11/10 in Phase 3.
- Tree replacements are scheduled for the week of 11/10.
- Retaining wall installation is scheduled to be completed by late November.
- Street sign installation is scheduled for the week of 11/10.
Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue
The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.
We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.
-
Construction Update - 10/31/2025
Share Construction Update - 10/31/2025 on Facebook Share Construction Update - 10/31/2025 on Twitter Share Construction Update - 10/31/2025 on Linkedin Email Construction Update - 10/31/2025 linkRoad Closures
Maloney Avenue between Washington Avenue and Tyler Court will be CLOSED for asphalt improvements through November 6. The detour route will be Blake Road, Excelsior Boulevard and Washington Avenue.
Project Area
- All work dates below are weather permitting.
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, and Alleys west of Madison Avenue
- The final layer of asphalt paving is scheduled for Saturday, 11/1.
Phase 3
- Asphalt driveways are complete.
- Sod installation is scheduled to continue the week of 11/3.
- The final layer of asphalt paving is tentatively scheduled to be completed the week of 11/3.
- Retaining wall installation is scheduled to be completed by late November.
- The concrete shared use path along Belmore Ln and Washington Ave is complete.
- Tree replacements are scheduled for the week of 11/3.
- The remaining fences that were removed during the project are scheduled to be reinstalled
Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue
The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.
We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.
-
Maloney Avenue Closure - 10/29 through 11/6
Share Maloney Avenue Closure - 10/29 through 11/6 on Facebook Share Maloney Avenue Closure - 10/29 through 11/6 on Twitter Share Maloney Avenue Closure - 10/29 through 11/6 on Linkedin Email Maloney Avenue Closure - 10/29 through 11/6 linkWashington Avenue will OPEN to traffic on Wednesday October 29. Maloney Avenue between Washington Avenue and Tyler Court will be CLOSED for asphalt improvements beginning on Wednesday October 29 through November 6. The detour route will be Blake Road, Excelsior Boulevard and Washington Avenue. Please contact Brandon Freeman at 952-826-0443 or BFreeman@edinamn.gov with any questions.
-
Construction Update – 10/24/2025
Share Construction Update – 10/24/2025 on Facebook Share Construction Update – 10/24/2025 on Twitter Share Construction Update – 10/24/2025 on Linkedin Email Construction Update – 10/24/2025 linkProject Area
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Alleys west of Madison Avenue
- The first layer of asphalt is scheduled to be paved on Saturday, 10/25 (weather permitting)
Phases 1 & 2
- The final layer of asphalt paving is tentatively scheduled for the week of 11/3 (weather permitting).
- Sod care
Phase 3
- If you did NOT receive a door hanger for notifying you about driveway asphalt replacement, please DO NOT PARK ON THE STREET. Park in your driveway or garage instead.
- Street parking at this stage disrupts the ongoing work needed to complete the work in a timely manner this fall.
- Asphalt driveways are scheduled for paving Saturday, 10/25.
- If you received a door hanger notifying you about driveway asphalt replacement, please follow the parking instructions provided.
- Crews will be onsite Saturday, 10/25 preparing the topsoil for sod installation.
- Sod installation is scheduled for the week of 10/27.
- The first layer of asphalt paving is complete.
- Retaining wall installation is tentatively scheduled to begin the week of 10/27.
- The concrete shared use path along Belmore Ln and Washington Ave is scheduled to be completed the week of 10/27 (weather permitting)
- The final layer of asphalt is scheduled to be installed the week of 11/3 (weather permitting).
Tyler Court
- Temporary replacement of curb and asphalt impacted by the watermain lining will occur by the end of October.
- The permanent and remaining roadway improvements have been postponed until 2026.
Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue
The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.
We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.
-
Construction Update - 10/17/2025
Share Construction Update - 10/17/2025 on Facebook Share Construction Update - 10/17/2025 on Twitter Share Construction Update - 10/17/2025 on Linkedin Email Construction Update - 10/17/2025 linkRoad Closures
- Washington Avenue will be CLOSED until October 23.
- The detour route is Maloney Avenue, Blake Road and Excelsior Boulevard
- The Maloney and 3rd Street intersections will be OPEN during the closure.
- Belmore Lane between Jefferson and Adams Avenues will be closed through Monday 10/6. Please use other routes until Tuesday, 10/7.
Project Area
-
See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Alleys west of Madison Avenue
- The first layer of paving is tentatively scheduled to be installed on Saturday, 10/18 (Weather Permitting)
Phases 1 & 2
- The final layer of asphalt paving is is tentatively scheduled for the week of 10/20.
- Phase 2 sod installation is complete.
- Sod care
Phase 3
- Please park vehicles in your driveways unless notified otherwise.
- Curb and gutter installation is complete.
- The first layer of asphalt pavement is tentatively scheduled to be installed on Saturday, 10/18, weather permitting.
- Retaining wall installation is scheduled to begin the week of 10/20.
- The concrete shared use path along Belmore Ln and Washington Ave is scheduled to be completed the week of 10/20(Weather Permitting)
Tyler Court
- Temporary replacement of concrete curb and asphalt impacted by the watermain lining will occur by the end of October.
- The permanent and remaining roadway improvements have been postponed until 2026.
Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue
The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.
We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.
- Washington Avenue will be CLOSED until October 23.
-
Construction Update - 10/10/2025
Share Construction Update - 10/10/2025 on Facebook Share Construction Update - 10/10/2025 on Twitter Share Construction Update - 10/10/2025 on Linkedin Email Construction Update - 10/10/2025 linkRoad Closures
- Washington Avenue will be CLOSED until mid-October.
- The detour route is Maloney Avenue, Blake Road and Excelsior Boulevard
- The Maloney and 3rd Street intersections will be OPEN during the closure.
- Belmore Lane between Jefferson and Adams Avenues will be closed through Monday 10/6. Please use other routes until Tuesday, 10/7.
Project Area
-
See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Alleys west of Madison Avenue
- Alley paving is tentatively scheduled to be installed on Saturday, 10/18 (Weather Permitting)
Phases 1 & 2
- The final layer of asphalt paving is scheduled for late October.
- Phase 2 sod installation is complete.
- Sod care
Phase 3
- Curb and gutter installation will continue Monday, 10/13.
- Please have all vehicles off the street by 7:00 am to allow work to continue on the roadway.
- The base layer of asphalt is tentatively scheduled to be installed on Saturday, 10/18, weather permitting.
- Driveway access will be restored the week of 10/13.
Tyler Court
- Temporary replacement of concrete curb and asphalt impacted by the watermain lining will occur by the end of October.
- The permanent and remaining roadway improvements have been postponed until 2026.
Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue
The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.
We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.
- Washington Avenue will be CLOSED until mid-October.
Email Signup
Sign Up for Emailed Project Updates
PRIVACY NOTICE: Under M.S. 13.356, your email address is private data. If you do not provide an email address you will not receive requested updates. Your email address will be available to anyone with a work assignment that reasonably require access.
Who's Listening
-
Phone 952-826-0448 Email BFreeman@Edinamn.gov -
Phone 952-826-0443 Email aditzler@EdinaMN.gov
Text Notifications
During the project there may be unexpected time sensitive resident impacts. In addition to providing those notices on the project page you may opt into receiving text notifications.
To sign up scan the QR code below or text PRESIDENTS-AB to 844-929-4328.
Key Dates
-
April 28 2025
-
April 01 2025
-
December 17 2024
Videos
Documents
-
Presidents A & B Project Area (145 KB) (pdf)
-
Living Streets Typical Section.pdf (885 KB) (pdf)
-
Construction Kickoff Update - Sample (84 KB) (docx)
-
Pedestrian Facilities Master Plan (1.98 MB) (pdf)
-
Bicycle Facilities Master Plan (1.96 MB) (pdf)
-
September 24 Informational Meeting Presentation Slides (10.2 MB) (pdf)
-
September 24 Informational Meeting Presentation Slides - Sidewalks_Paths (1.11 MB) (pdf)
-
Proposed Sidewalk and Path Facilities (299 KB) (pdf)
-
Proposed Street Widths, Sidewalk and Path Facilities (442 KB) (pdf)
-
Presidents A B Assessments - Roadway (145 KB) (pdf)
-
Presidents A B Assessments - Alley (150 KB) (pdf)
-
Assessment Benefit Report (6.88 MB) (pdf)
-
2025 Presidents A/B Engineering Study (12.4 MB) (pdf)
-
Presidents Public Hearing Presentation - 12/9/24 (9.45 MB) (pdf)
-
Utility Upgrade Letter Optional (824 KB) (pdf)
-
Construction Kickoff Update and What to Expect (108 KB) (pdf)
-
Construction Phasing Map - Updated (1.38 MB) (pdf)
-
Maloney Avenue Detour for CenterPoint Energy (8.54 MB) (pdf)
-
Sod Care Installation Phase 1 (68.3 KB) (docx)
-
Maloney Ave Detour (354 KB) (pdf)
-
Washington Avenue Detour (297 KB) (jpg)
-
Sanitary Sewer Lining Door Notice (120 KB) (pdf)