Presidents A & B Neighborhood Roadway Reconstruction
Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!
This 2025 construction project includes:
- Complete reconstruction of the roadway asphalt pavement,
- Full installation or replacement of concrete curb and gutter,
- Complete reconstruction of two alleys west of Madison Avenue,
- Complete replacement of the watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems, and
- Proposed construction of multi-modal facilities along:
- Monroe Avenue (5' sidewalk)
- Belmore Lane (8' shared use path)
- Washington Avenue (8' shared use path)
- The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
- A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
- An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
- If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!
This 2025 construction project includes:
- Complete reconstruction of the roadway asphalt pavement,
- Full installation or replacement of concrete curb and gutter,
- Complete reconstruction of two alleys west of Madison Avenue,
- Complete replacement of the watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems, and
- Proposed construction of multi-modal facilities along:
- Monroe Avenue (5' sidewalk)
- Belmore Lane (8' shared use path)
- Washington Avenue (8' shared use path)
- The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
- A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
- An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
- If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
-
Construction Update - 6/26/2026
Share Construction Update - 6/26/2026 on Facebook Share Construction Update - 6/26/2026 on X (formerly Twitter) Share Construction Update - 6/26/2026 on Linkedin Email Construction Update - 6/26/2026 linkProject Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until early July. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction working hours.
- Sod installation, irrigation repairs and replacement of impacted landscaping is scheduled to begin during the week of 6/29.
- Paving the final layer of asphalt is tentatively scheduled for Monday, 7/6.
- Check your front door daily for notifications.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Any outstanding landscaping and sod issues are scheduled to occur the week of 6/29.
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
Project Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until early July. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction working hours.
- Sod installation, irrigation repairs and replacement of impacted landscaping is scheduled to begin during the week of 6/29.
- Paving the final layer of asphalt is tentatively scheduled for Monday, 7/6.
- Check your front door daily for notifications.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Any outstanding landscaping and sod issues are scheduled to occur the week of 6/29.
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
-
Construction Update - 6/19/2026
Share Construction Update - 6/19/2026 on Facebook Share Construction Update - 6/19/2026 on X (formerly Twitter) Share Construction Update - 6/19/2026 on Linkedin Email Construction Update - 6/19/2026 linkProject Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until late June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction working hours.
- Asphalt driveway paving is scheduled to occur the week of 6/22.
- Concrete sidewalk installation on Belmore Ln is scheduled to occur the week of 6/22.
- Topsoil installation is scheduled to begin the week of 6/22.
- Check your front door daily for notification of temporary driveway access loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
Project Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until late June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction working hours.
- Asphalt driveway paving is scheduled to occur the week of 6/22.
- Concrete sidewalk installation on Belmore Ln is scheduled to occur the week of 6/22.
- Topsoil installation is scheduled to begin the week of 6/22.
- Check your front door daily for notification of temporary driveway access loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
-
Construction Update - 6/12/2026
Share Construction Update - 6/12/2026 on Facebook Share Construction Update - 6/12/2026 on X (formerly Twitter) Share Construction Update - 6/12/2026 on Linkedin Email Construction Update - 6/12/2026 linkProject Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until late June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction working hours.
- Roadway grading in preparation for the first layer of paving will occur during the week of 6/15.
- Paving of the first layer of asphalt on the streets is scheduled to occur late during the week of 6/15.
- Asphalt driveway paving is scheduled to occur soon after the first layer of asphalt street paving occurs, likely during the week of 6/15.
- Check your front door daily for notification of temporary driveway access loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
Project Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until late June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction working hours.
- Roadway grading in preparation for the first layer of paving will occur during the week of 6/15.
- Paving of the first layer of asphalt on the streets is scheduled to occur late during the week of 6/15.
- Asphalt driveway paving is scheduled to occur soon after the first layer of asphalt street paving occurs, likely during the week of 6/15.
- Check your front door daily for notification of temporary driveway access loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
-
Construction Update - 6/5/2026
Share Construction Update - 6/5/2026 on Facebook Share Construction Update - 6/5/2026 on X (formerly Twitter) Share Construction Update - 6/5/2026 on Linkedin Email Construction Update - 6/5/2026 linkProject Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until late June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Concrete curb and driveway apron installation will continue into the week of 6/8.
- Concrete driveway installation is scheduled to begin during the week of 6/8.
- Following concrete curing, roadway grading in preparation for the first layer of paving will occur.
- Check your front door daily for notification of temporary driveway access loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
Project Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until late June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Concrete curb and driveway apron installation will continue into the week of 6/8.
- Concrete driveway installation is scheduled to begin during the week of 6/8.
- Following concrete curing, roadway grading in preparation for the first layer of paving will occur.
- Check your front door daily for notification of temporary driveway access loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
-
Construction Update - 5/29/2026
Share Construction Update - 5/29/2026 on Facebook Share Construction Update - 5/29/2026 on X (formerly Twitter) Share Construction Update - 5/29/2026 on Linkedin Email Construction Update - 5/29/2026 linkProject Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Work will occur on Saturday, 5/30.
- Roadway excavation and soil corrections will continue into the week of 6/1.
- Concrete curb and driveway apron installation is scheduled to begin late during the week of 6/1.
- Check your front door daily for notification of temporary driveway access loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Please check your front door daily the week of 6/1 for notifications of driveway access loss due to concrete warranty work.
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
Project Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Work will occur on Saturday, 5/30.
- Roadway excavation and soil corrections will continue into the week of 6/1.
- Concrete curb and driveway apron installation is scheduled to begin late during the week of 6/1.
- Check your front door daily for notification of temporary driveway access loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Please check your front door daily the week of 6/1 for notifications of driveway access loss due to concrete warranty work.
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
-
Construction Update - 5/22/2026
Share Construction Update - 5/22/2026 on Facebook Share Construction Update - 5/22/2026 on X (formerly Twitter) Share Construction Update - 5/22/2026 on Linkedin Email Construction Update - 5/22/2026 linkProject Area
- No work will occur on Memorial Day, Monday, 5/25.
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Roadway excavation and soil corrections will continue through the week of 5/26.
- Concrete curb and driveway apron installation is scheduled to begin the week of 6/2.
- Sump drain installation is complete.
- Check your front door daily for notification of temporary driveway access.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Please check your front door daily the week of 5/26 for notifications of driveway access loss due to concrete warranty work.
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
Project Area
- No work will occur on Memorial Day, Monday, 5/25.
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Roadway excavation and soil corrections will continue through the week of 5/26.
- Concrete curb and driveway apron installation is scheduled to begin the week of 6/2.
- Sump drain installation is complete.
- Check your front door daily for notification of temporary driveway access.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Please check your front door daily the week of 5/26 for notifications of driveway access loss due to concrete warranty work.
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
-
Construction Update - 5/15/2026
Share Construction Update - 5/15/2026 on Facebook Share Construction Update - 5/15/2026 on X (formerly Twitter) Share Construction Update - 5/15/2026 on Linkedin Email Construction Update - 5/15/2026 linkProject Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Sump drain installation will continue into the week of 5/18.
- Roadway excavation and soil corrections are scheduled to begin the week of 5/18.
- The watermain and storm sewer related improvements are complete.
- Check your front door daily for notification of temporary driveway access.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Remaining sod and sod replacement is complete.
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
Project Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Sump drain installation will continue into the week of 5/18.
- Roadway excavation and soil corrections are scheduled to begin the week of 5/18.
- The watermain and storm sewer related improvements are complete.
- Check your front door daily for notification of temporary driveway access.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Remaining sod and sod replacement is complete.
- Sod watering continues. Residents will receive a letter in the mail when the sod watering period has concluded.
-
Construction Update - 5/8/2026
Share Construction Update - 5/8/2026 on Facebook Share Construction Update - 5/8/2026 on X (formerly Twitter) Share Construction Update - 5/8/2026 on Linkedin Email Construction Update - 5/8/2026 linkProject Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Water service replacement and storm sewer installation is scheduled to be completed the week of 5/11.
- Sump drain installation is scheduled to begin the week of 5/11.
- Check your front door daily for notification of temporary driveway access or water loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Remaining sod and sod replacement is expected to be installed the week of 5/11.
- Sod watering has resumed. Residents will receive a letter in the mail when the sod watering period has concluded.
Project Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Water service replacement and storm sewer installation is scheduled to be completed the week of 5/11.
- Sump drain installation is scheduled to begin the week of 5/11.
- Check your front door daily for notification of temporary driveway access or water loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Remaining sod and sod replacement is expected to be installed the week of 5/11.
- Sod watering has resumed. Residents will receive a letter in the mail when the sod watering period has concluded.
-
Construction Update - 5/1/2026
Share Construction Update - 5/1/2026 on Facebook Share Construction Update - 5/1/2026 on X (formerly Twitter) Share Construction Update - 5/1/2026 on Linkedin Email Construction Update - 5/1/2026 linkProject Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Watermain installation is scheduled to be complete the week of 5/4.
- Water service replacement is expected to begin on Harrison Ave the week of 5/4.
- Storm sewer installation is scheduled to begin the week of 5/4.
- Check your front door daily for notification of temporary driveway access or water loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Sod watering has resumed. Residents will receive a letter in the mail when the sod watering period has concluded and replacement sod has been installed.
- Replacement of landscaping, retaining walls, and trees is complete. If you have any outstanding issues, please reach out to project manager Chris Moore.
Project Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Watermain installation is scheduled to be complete the week of 5/4.
- Water service replacement is expected to begin on Harrison Ave the week of 5/4.
- Storm sewer installation is scheduled to begin the week of 5/4.
- Check your front door daily for notification of temporary driveway access or water loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Sod watering has resumed. Residents will receive a letter in the mail when the sod watering period has concluded and replacement sod has been installed.
- Replacement of landscaping, retaining walls, and trees is complete. If you have any outstanding issues, please reach out to project manager Chris Moore.
-
Construction Update - 4/24/2026
Share Construction Update - 4/24/2026 on Facebook Share Construction Update - 4/24/2026 on X (formerly Twitter) Share Construction Update - 4/24/2026 on Linkedin Email Construction Update - 4/24/2026 linkProject Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Watermain installation is scheduled for the week of 4/27.
- Check your front door daily for notification of temporary driveway access or water loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Please park on the street if you have an alley. Alley access will be limited due to restoration work.
- Retaining wall installation is ongoing and is scheduled to be completed by mid July.
- Replacement of landscaping and trees is ongoing and is scheduled to be completed by mid July.
Project Area
- Maloney Ave will be CLOSED to through traffic between Washington Ave and Tyler Ave. This closure is expected to last until mid-June. Please see the attached detour map.
- See the construction phasing map.
- All work dates below are weather permitting.
Phase 4:
- Vehicles cannot be parked on the street during construction.
- Watermain installation is scheduled for the week of 4/27.
- Check your front door daily for notification of temporary driveway access or water loss.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1, 2, 3
- Please park on the street if you have an alley. Alley access will be limited due to restoration work.
- Retaining wall installation is ongoing and is scheduled to be completed by mid July.
- Replacement of landscaping and trees is ongoing and is scheduled to be completed by mid July.
Email Signup
Sign Up for Emailed Project Updates
PRIVACY NOTICE: Under M.S. 13.356, your email address is private data. If you do not provide an email address you will not receive requested updates. Your email address will be available to anyone with a work assignment that reasonably require access.
Who's Listening
-
Phone 952-826-0444 Email CMoore@EdinaMN.gov -
Phone 952-826-0443 Email aditzler@EdinaMN.gov
Text Notifications
During the project there may be unexpected time sensitive resident impacts. In addition to providing those notices on the project page you may opt into receiving text notifications.
To sign up scan the QR code below or text PRESIDENTS-AB to 844-929-4328.
Key Dates
-
July 2026
-
March 30 2026
-
April 28 2025
Videos
Documents
-
Presidents A & B Project Area (145 KB) (pdf)
-
Living Streets Typical Section.pdf (885 KB) (pdf)
-
Construction Kickoff Update - Sample (84 KB) (docx)
-
Pedestrian Facilities Master Plan (1.98 MB) (pdf)
-
Bicycle Facilities Master Plan (1.96 MB) (pdf)
-
September 24 Informational Meeting Presentation Slides (10.2 MB) (pdf)
-
September 24 Informational Meeting Presentation Slides - Sidewalks_Paths (1.11 MB) (pdf)
-
Proposed Sidewalk and Path Facilities (299 KB) (pdf)
-
Proposed Street Widths, Sidewalk and Path Facilities (442 KB) (pdf)
-
Presidents A B Assessments - Roadway (145 KB) (pdf)
-
Presidents A B Assessments - Alley (150 KB) (pdf)
-
Assessment Benefit Report (6.88 MB) (pdf)
-
2025 Presidents A/B Engineering Study (12.4 MB) (pdf)
-
Presidents Public Hearing Presentation - 12/9/24 (9.45 MB) (pdf)
-
Utility Upgrade Letter Optional (824 KB) (pdf)
-
Construction Kickoff Update and What to Expect (108 KB) (pdf)
-
Presidents A B Phasing Map v4.pdf (1.38 MB) (pdf)
-
Maloney Avenue Detour for CenterPoint Energy (8.54 MB) (pdf)
-
Sod Care Installation Phase 1 (68.3 KB) (docx)
-
Maloney Ave Detour (354 KB) (pdf)
-
Washington Avenue Detour (297 KB) (jpg)
-
Sanitary Sewer Lining Door Notice (120 KB) (pdf)