Presidents A & B Neighborhood Roadway Reconstruction

Share Presidents A & B Neighborhood Roadway Reconstruction on Facebook Share Presidents A & B Neighborhood Roadway Reconstruction on Twitter Share Presidents A & B Neighborhood Roadway Reconstruction on Linkedin Email Presidents A & B Neighborhood Roadway Reconstruction link

Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2025 construction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete reconstruction of two alleys west of Madison Avenue,
  • Complete replacement of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Proposed construction of multi-modal facilities along:
    • Monroe Avenue (5' sidewalk)
    • Belmore Lane (8' shared use path)
    • Washington Avenue (8' shared use path)
  • The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
  • A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
  • An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
  • If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.

Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2025 construction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete reconstruction of two alleys west of Madison Avenue,
  • Complete replacement of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Proposed construction of multi-modal facilities along:
    • Monroe Avenue (5' sidewalk)
    • Belmore Lane (8' shared use path)
    • Washington Avenue (8' shared use path)
  • The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
  • A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
  • An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
  • If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
  • Construction Update - 10/31/2025

    Share Construction Update - 10/31/2025 on Facebook Share Construction Update - 10/31/2025 on Twitter Share Construction Update - 10/31/2025 on Linkedin Email Construction Update - 10/31/2025 link

    Road Closures

    Maloney Avenue between Washington Avenue and Tyler Court will be CLOSED for asphalt improvements through November 6. The detour route will be Blake Road, Excelsior Boulevard and Washington Avenue.


    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1, 2, and Alleys west of Madison Avenue

    • The final layer of asphalt paving is scheduled for Saturday, 11/1.


    Phase 3

    • Asphalt driveways are complete.
    • Sod installation is scheduled to continue the week of 11/3.
    • The final layer of asphalt paving is tentatively scheduled to be completed the week of 11/3.
    • Retaining wall installation is scheduled to be completed by late November.
    • The concrete shared use path along Belmore Ln and Washington Ave is complete.
    • Tree replacements are scheduled for the week of 11/3.
    • The remaining fences that were removed during the project are scheduled to be reinstalled


    Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue

    The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.


  • Maloney Avenue Closure - 10/29 through 11/6

    Share Maloney Avenue Closure - 10/29 through 11/6 on Facebook Share Maloney Avenue Closure - 10/29 through 11/6 on Twitter Share Maloney Avenue Closure - 10/29 through 11/6 on Linkedin Email Maloney Avenue Closure - 10/29 through 11/6 link

    Washington Avenue will OPEN to traffic on Wednesday October 29. Maloney Avenue between Washington Avenue and Tyler Court will be CLOSED for asphalt improvements beginning on Wednesday October 29 through November 6. The detour route will be Blake Road, Excelsior Boulevard and Washington Avenue. Please contact Brandon Freeman at 952-826-0443 or BFreeman@edinamn.gov with any questions.

  • Construction Update – 10/24/2025

    Share Construction Update – 10/24/2025 on Facebook Share Construction Update – 10/24/2025 on Twitter Share Construction Update – 10/24/2025 on Linkedin Email Construction Update – 10/24/2025 link

    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Alleys west of Madison Avenue

    • The first layer of asphalt is scheduled to be paved on Saturday, 10/25 (weather permitting)


    Phases 1 & 2

    • The final layer of asphalt paving is tentatively scheduled for the week of 11/3 (weather permitting).
    • Sod care
      • See written and video sod care tips here and here.
      • To prevent sod damage, please avoid walking on or mowing it initially.
      • The contractor will be watering for the first 60 days.
      • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.


    Phase 3

    • If you did NOT receive a door hanger for notifying you about driveway asphalt replacement, please DO NOT PARK ON THE STREET. Park in your driveway or garage instead.
      • Street parking at this stage disrupts the ongoing work needed to complete the work in a timely manner this fall.
    • Asphalt driveways are scheduled for paving Saturday, 10/25.
      • If you received a door hanger notifying you about driveway asphalt replacement, please follow the parking instructions provided.
    • Crews will be onsite Saturday, 10/25 preparing the topsoil for sod installation.
    • Sod installation is scheduled for the week of 10/27.
    • The first layer of asphalt paving is complete.
    • Retaining wall installation is tentatively scheduled to begin the week of 10/27.
    • The concrete shared use path along Belmore Ln and Washington Ave is scheduled to be completed the week of 10/27 (weather permitting)
    • The final layer of asphalt is scheduled to be installed the week of 11/3 (weather permitting).


    Tyler Court

    • Temporary replacement of curb and asphalt impacted by the watermain lining will occur by the end of October.
    • The permanent and remaining roadway improvements have been postponed until 2026.


    Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue

    The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.

  • Construction Update - 10/17/2025

    Share Construction Update - 10/17/2025 on Facebook Share Construction Update - 10/17/2025 on Twitter Share Construction Update - 10/17/2025 on Linkedin Email Construction Update - 10/17/2025 link

    Road Closures


    Project Area

    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Alleys west of Madison Avenue

    • The first layer of paving is tentatively scheduled to be installed on Saturday, 10/18 (Weather Permitting)


    Phases 1 & 2

    • The final layer of asphalt paving is is tentatively scheduled for the week of 10/20.
    • Phase 2 sod installation is complete.
    • Sod care
      • See written and video sod care tips here and here.
      • To prevent sod damage, please avoid walking on or mowing it initially.
      • The contractor will be watering for the first 60 days.
      • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.


    Phase 3

    • Please park vehicles in your driveways unless notified otherwise.
    • Curb and gutter installation is complete.
    • The first layer of asphalt pavement is tentatively scheduled to be installed on Saturday, 10/18, weather permitting.
    • Retaining wall installation is scheduled to begin the week of 10/20.
    • The concrete shared use path along Belmore Ln and Washington Ave is scheduled to be completed the week of 10/20(Weather Permitting)


    Tyler Court

    • Temporary replacement of concrete curb and asphalt impacted by the watermain lining will occur by the end of October.
    • The permanent and remaining roadway improvements have been postponed until 2026.


    Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue

    The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.

  • Construction Update - 10/10/2025

    Share Construction Update - 10/10/2025 on Facebook Share Construction Update - 10/10/2025 on Twitter Share Construction Update - 10/10/2025 on Linkedin Email Construction Update - 10/10/2025 link

    Road Closures


    Project Area

    • See the construction phasing map.

    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Alleys west of Madison Avenue

    • Alley paving is tentatively scheduled to be installed on Saturday, 10/18 (Weather Permitting)


    Phases 1 & 2

    • The final layer of asphalt paving is scheduled for late October.
    • Phase 2 sod installation is complete.
    • Sod care
      • See written and video sod care tips here and here.
      • To prevent sod damage, please avoid walking on or mowing it initially.
      • The contractor will be watering for the first 60 days.
      • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.


    Phase 3

    • Curb and gutter installation will continue Monday, 10/13.
      • Please have all vehicles off the street by 7:00 am to allow work to continue on the roadway.
    • The base layer of asphalt is tentatively scheduled to be installed on Saturday, 10/18, weather permitting.
    • Driveway access will be restored the week of 10/13.


    Tyler Court

    • Temporary replacement of concrete curb and asphalt impacted by the watermain lining will occur by the end of October.
    • The permanent and remaining roadway improvements have been postponed until 2026.


    Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue

    The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.


  • Construction Update - 10/3/2025

    Share Construction Update - 10/3/2025 on Facebook Share Construction Update - 10/3/2025 on Twitter Share Construction Update - 10/3/2025 on Linkedin Email Construction Update - 10/3/2025 link

    Road Closures


    Project Area

    • See the construction phasing map.

    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phases 1 & 2

    • Phase 2 sod installation will continue the week of 10/6.
    • Sod care
      • See written and video sod care tips here and here.
      • To prevent sod damage, please avoid walking on or mowing it initially.
      • The contractor will be watering for the first 60 days.
      • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.
    • New retaining wall installation on Monroe Ave will continue into the week of 10/6.
    • The final layer of asphalt paving is scheduled for late October.


    Phase 3

    • Crews will be onsite Saturday, 10/4 removing and replacing poor soils in preparation for curb and gutter.
    • Storm sewer infiltration system Installation on Belmore Ln is complete.
    • Curb and Gutter installation is scheduled to begin Tuesday, 10/7.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 3 roadways are paved.


    Tyler Court

    • Watermain lining on Tyler Court is complete.
    • Temporary water is scheduled to be removed the week of 10/6.
    • The roadway improvements have been postponed until 2026.


    Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue

    The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.

  • Construction Update - 9/26/2025

    Share Construction Update - 9/26/2025 on Facebook Share Construction Update - 9/26/2025 on Twitter Share Construction Update - 9/26/2025 on Linkedin Email Construction Update - 9/26/2025 link

    Road Closures


    Project Area

    • See the construction phasing map.

    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Sod care
      • See written and video sod care tips here and here.
      • To prevent sod damage, please avoid walking on or mowing it initially.
      • The contractor will be watering for the first 60 days.
      • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.
    • The final layer of asphalt paving is scheduled for late October.


    Phase 2

    • Concrete sidewalk installation on Monroe Ave and Belmore Ln is complete.
    • Excavation in preparation for topsoil installation is scheduled to continue the week of 9/29.
    • New retaining wall installation on Monroe Ave will continue into the week of 9/29.


    Phase 3

    • Crews will be onsite Saturday, 9/27 removing and replacing poor soils in preparation for curb and gutter. This work will continue the week of 9/29.
    • Sump line installation on Adams Ave is complete.
    • Watermain lining on Maloney Ave is complete.
    • Installation of a storm sewer infiltration system on Belmore Ln between Jefferson Ave and Adams Ave is scheduled to begin the week of 9/29.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 3 roadways are paved.


    Tyler Court

    • Watermain lining on Tyler Court is complete.
    • Brandon will be setting up times to reinstall water meters the week of 9/29 for homes affected by the watermain lining.
    • The roadway improvements have been postponed until 2026.


    Harrison and Tyler Avenues and Tyler Ct

  • Construction Update - 9/19/2025

    Share Construction Update - 9/19/2025 on Facebook Share Construction Update - 9/19/2025 on Twitter Share Construction Update - 9/19/2025 on Linkedin Email Construction Update - 9/19/2025 link

    Road Closures

    • Maloney Avenue will remain closed until Wed. 9/24.
    • Washington Avenue will be CLOSED beginning Wed. 9/24 for approximately 3 weeks.
    • Belmore Lane between Jefferson and Adams Avenues will be closed beginning the week of 9/22. Please use other routes.


    Project Area

    • See the construction phasing map.


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Sod care
      • See written and video sod care tips here and here.
      • To prevent sod damage, please avoid walking on or mowing it initially.
      • The contractor will be watering for the first 60 days.
      • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.
    • The final layer of asphalt paving is scheduled for late October.


    Phase 2

    • The first layer of asphalt paving is complete.
    • Concrete sidewalk installation on Monroe Ave and Belmore Ln is scheduled for the week of 9/22.
    • Excavation in preparation for topsoil installation is scheduled to begin the week of 9/22.
    • New retaining wall installation on Monroe Ave will continue into the week of 9/22.


    Phase 3

    • Water service installation on Adams Ave is complete.
    • Sump line installation on Adams Ave will continue into the week of 9/22.
    • Watermain lining on Maloney Ave will continue into the week of 9/22.
    • Removal and replacement of poor soils in preparation for curb and gutter is scheduled to begin the week of 9/22.
    • Installation of a storm sewer infiltration system on Belmore Ln between Jefferson Ave and Adams Ave is scheduled to begin the week of 9/22.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 3 roadways are paved.


    Tyler Court

    • Watermain lining on Tyler Court will continue into the week of 9/22.
    • The roadway improvements have been postponed until 2026.


    Harrison Avenue, Tyler Avenue, Tyler Ct, and Belmore Ln

  • Construction Update – 9/12/2025

    Share Construction Update – 9/12/2025 on Facebook Share Construction Update – 9/12/2025 on Twitter Share Construction Update – 9/12/2025 on Linkedin Email Construction Update – 9/12/2025 link

    Maloney Avenue Road Closure

    • Please see the road closure update here for details.


    Project Area

    • See the construction phasing map.


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Landscaping replacement will continue the week of 9/15.
    • Sod care
      • See written and video sod care tips here and here.
      • To prevent sod damage, please avoid walking on or mowing it initially.
      • The contractor will be watering for the first 60 days.
      • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.
    • The final layer of asphalt paving is scheduled for late October.


    Phase 2

    • The first layer of asphalt paving is scheduled for Monday, 9/15. Please have all vehicles off the street by 7am.
    • Concrete sidewalk installation on Monroe Ave and Belmore Ln is scheduled for the week of 9/15.


    Phase 3

    • Water service installation on Jefferson Ave is complete.
    • Sump line installation will continue into the week of 9/15.
    • Watermain lining on Maloney Ave will continue into the week of 9/15.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 3 roadways are paved.


    Tyler Court

    • Watermain lining on Tyler Court will continue into the week of 9/15.


    Harrison and Tyler Avenues



  • Fall Progress Update

    Share Fall Progress Update on Facebook Share Fall Progress Update on Twitter Share Fall Progress Update on Linkedin Email Fall Progress Update link

    While progress has been made this construction season, and all the streets west of Harrison Avenue will be complete by the original November 15, 2025, completion date, it’s highly likely the streets east of Van Buren Avenue will not begin until spring 2026.

    Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area. We will continue to share updates as milestones are reached and a new 2026 completion schedule is confirmed.


Page last updated: 31 Oct 2025, 12:44 PM