Presidents A & B Neighborhood Roadway Reconstruction

Share Presidents A & B Neighborhood Roadway Reconstruction on Facebook Share Presidents A & B Neighborhood Roadway Reconstruction on X (formerly Twitter) Share Presidents A & B Neighborhood Roadway Reconstruction on Linkedin Email Presidents A & B Neighborhood Roadway Reconstruction link
Map showing the Presidents neighborhood and the project limit boundaries.

Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2025 construction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete reconstruction of two alleys west of Madison Avenue,
  • Complete replacement of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Proposed construction of multi-modal facilities along:
    • Monroe Avenue (5' sidewalk)
    • Belmore Lane (8' shared use path)
    • Washington Avenue (8' shared use path)
  • The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
  • A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
  • An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
  • If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.

Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This 2025 construction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete reconstruction of two alleys west of Madison Avenue,
  • Complete replacement of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Proposed construction of multi-modal facilities along:
    • Monroe Avenue (5' sidewalk)
    • Belmore Lane (8' shared use path)
    • Washington Avenue (8' shared use path)
  • The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
  • A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
  • An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
  • If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
  • Construction Update - 10/17/2025

    Share Construction Update - 10/17/2025 on Facebook Share Construction Update - 10/17/2025 on X (formerly Twitter) Share Construction Update - 10/17/2025 on Linkedin Email Construction Update - 10/17/2025 link

    Road Closures


    Project Area

    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Alleys west of Madison Avenue

    • The first layer of paving is tentatively scheduled to be installed on Saturday, 10/18 (Weather Permitting)


    Phases 1 & 2

    • The final layer of asphalt paving is is tentatively scheduled for the week of 10/20.
    • Phase 2 sod installation is complete.
    • Sod care
      • See written and video sod care tips here and here.
      • To prevent sod damage, please avoid walking on or mowing it initially.
      • The contractor will be watering for the first 60 days.
      • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.


    Phase 3

    • Please park vehicles in your driveways unless notified otherwise.
    • Curb and gutter installation is complete.
    • The first layer of asphalt pavement is tentatively scheduled to be installed on Saturday, 10/18, weather permitting.
    • Retaining wall installation is scheduled to begin the week of 10/20.
    • The concrete shared use path along Belmore Ln and Washington Ave is scheduled to be completed the week of 10/20(Weather Permitting)


    Tyler Court

    • Temporary replacement of concrete curb and asphalt impacted by the watermain lining will occur by the end of October.
    • The permanent and remaining roadway improvements have been postponed until 2026.


    Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue

    The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.

    Road Closures


    Project Area

    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Alleys west of Madison Avenue

    • The first layer of paving is tentatively scheduled to be installed on Saturday, 10/18 (Weather Permitting)


    Phases 1 & 2

    • The final layer of asphalt paving is is tentatively scheduled for the week of 10/20.
    • Phase 2 sod installation is complete.
    • Sod care
      • See written and video sod care tips here and here.
      • To prevent sod damage, please avoid walking on or mowing it initially.
      • The contractor will be watering for the first 60 days.
      • If there is little rainfall and hot temperatures, supplemental daily watering from property owners is appreciated.


    Phase 3

    • Please park vehicles in your driveways unless notified otherwise.
    • Curb and gutter installation is complete.
    • The first layer of asphalt pavement is tentatively scheduled to be installed on Saturday, 10/18, weather permitting.
    • Retaining wall installation is scheduled to begin the week of 10/20.
    • The concrete shared use path along Belmore Ln and Washington Ave is scheduled to be completed the week of 10/20(Weather Permitting)


    Tyler Court

    • Temporary replacement of concrete curb and asphalt impacted by the watermain lining will occur by the end of October.
    • The permanent and remaining roadway improvements have been postponed until 2026.


    Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue

    The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.

  • Fall Progress Update

    Share Fall Progress Update on Facebook Share Fall Progress Update on X (formerly Twitter) Share Fall Progress Update on Linkedin Email Fall Progress Update link

    While progress has been made this construction season, and all the streets west of Harrison Avenue will be complete by the original November 15, 2025, completion date, it’s highly likely the streets east of Van Buren Avenue will not begin until spring 2026.

    Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area. We will continue to share updates as milestones are reached and a new 2026 completion schedule is confirmed.


    While progress has been made this construction season, and all the streets west of Harrison Avenue will be complete by the original November 15, 2025, completion date, it’s highly likely the streets east of Van Buren Avenue will not begin until spring 2026.

    Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.

    We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area. We will continue to share updates as milestones are reached and a new 2026 completion schedule is confirmed.


  • Maloney Avenue Closure 9/3-9/19

    Share Maloney Avenue Closure 9/3-9/19 on Facebook Share Maloney Avenue Closure 9/3-9/19 on X (formerly Twitter) Share Maloney Avenue Closure 9/3-9/19 on Linkedin Email Maloney Avenue Closure 9/3-9/19 link

    Maloney Avenue between Washington Avenue and Tyler Court will be closed for watermain lining improvements beginning on Tuesday September 3 through September 19. The detour route will be Blake Road, Excelsior Boulevard and Washington Avenue. Please contact Brandon Freeman at 952-826-0443 or BFreeman@edinamn.gov with any questions.

    Maloney Avenue between Washington Avenue and Tyler Court will be closed for watermain lining improvements beginning on Tuesday September 3 through September 19. The detour route will be Blake Road, Excelsior Boulevard and Washington Avenue. Please contact Brandon Freeman at 952-826-0443 or BFreeman@edinamn.gov with any questions.

  • Construction Update – 8/15/2025

    Share Construction Update – 8/15/2025 on Facebook Share Construction Update – 8/15/2025 on X (formerly Twitter) Share Construction Update – 8/15/2025 on Linkedin Email Construction Update – 8/15/2025 link

    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Excavation in preparation for topsoil installation is complete.
    • Sod installation is scheduled to begin on Monday, 8/18 (Weather dependent)
    • Landscaping replacement will continue the week of 8/18.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Crews will be onsite on Saturday, 8/16 to continue excavation of poor soils in preparation for the new roadway. This work will continue the week of 8/18.
    • Sump line installation is complete.
    • Curb and gutter Installation is tentatively scheduled to begin on 8/20 (Weather dependent).


    Phase 3

    • Curb and driveway apron removals are complete.
    • Temporary water line installation is scheduled to continue into the week of 8/18.
      • The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
      • Anticipate short term water loss during this process.
    • Installation of the new water main is scheduled to begin the week of 8/18.



    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Excavation in preparation for topsoil installation is complete.
    • Sod installation is scheduled to begin on Monday, 8/18 (Weather dependent)
    • Landscaping replacement will continue the week of 8/18.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Crews will be onsite on Saturday, 8/16 to continue excavation of poor soils in preparation for the new roadway. This work will continue the week of 8/18.
    • Sump line installation is complete.
    • Curb and gutter Installation is tentatively scheduled to begin on 8/20 (Weather dependent).


    Phase 3

    • Curb and driveway apron removals are complete.
    • Temporary water line installation is scheduled to continue into the week of 8/18.
      • The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
      • Anticipate short term water loss during this process.
    • Installation of the new water main is scheduled to begin the week of 8/18.



  • Construction Update – 8/8/2025

    Share Construction Update – 8/8/2025 on Facebook Share Construction Update – 8/8/2025 on X (formerly Twitter) Share Construction Update – 8/8/2025 on Linkedin Email Construction Update – 8/8/2025 link

    Project Area

    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Excavation in preparation for topsoil installation will continue the week of 8/11.
    • Retaining wall installation is complete.
    • Replacement of landscape items that were removed during construction will begin the week of 8/11.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Storm sewer installation is complete.
    • Sump line installation will continue the week of 8/11.
    • Removal and replacement of poor soils in preparation for the new roadway is scheduled to begin the week of 8/11.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave, and Belmore Ave will continue into the week of 8/11.
    • Temporary water line installation is scheduled to continue into the week of 8/11.
      • The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
      • Anticipate short term water loss during this process.
    • Installation of the new water main is scheduled to begin the week of 8/11.


    Project Area

    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Excavation in preparation for topsoil installation will continue the week of 8/11.
    • Retaining wall installation is complete.
    • Replacement of landscape items that were removed during construction will begin the week of 8/11.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Storm sewer installation is complete.
    • Sump line installation will continue the week of 8/11.
    • Removal and replacement of poor soils in preparation for the new roadway is scheduled to begin the week of 8/11.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave, and Belmore Ave will continue into the week of 8/11.
    • Temporary water line installation is scheduled to continue into the week of 8/11.
      • The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
      • Anticipate short term water loss during this process.
    • Installation of the new water main is scheduled to begin the week of 8/11.


  • Construction Update – 8/1/2025

    Share Construction Update – 8/1/2025 on Facebook Share Construction Update – 8/1/2025 on X (formerly Twitter) Share Construction Update – 8/1/2025 on Linkedin Email Construction Update – 8/1/2025 link

    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Concrete path installation along Belmore Lane is complete.
    • Excavation in preparation for topsoil installation will continue the week of 8/4.
    • Retaining wall installation is scheduled to begin the week of 8/4.


    Alleys west of Madison Avenue

    • The concrete valley gutter and curb installation is complete.
    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Water service installations are complete on Monroe and Madison Ave.
    • Storm sewer and sump line installation will continue the week of 8/4.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 8/4.
    • Temporary water line installation is scheduled to continue into the week of 8/4.



    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Concrete path installation along Belmore Lane is complete.
    • Excavation in preparation for topsoil installation will continue the week of 8/4.
    • Retaining wall installation is scheduled to begin the week of 8/4.


    Alleys west of Madison Avenue

    • The concrete valley gutter and curb installation is complete.
    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Water service installations are complete on Monroe and Madison Ave.
    • Storm sewer and sump line installation will continue the week of 8/4.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 8/4.
    • Temporary water line installation is scheduled to continue into the week of 8/4.



  • Construction Update – 7/25/2025

    Share Construction Update – 7/25/2025 on Facebook Share Construction Update – 7/25/2025 on X (formerly Twitter) Share Construction Update – 7/25/2025 on Linkedin Email Construction Update – 7/25/2025 link

    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Asphalt driveways are complete.
    • Excavation in preparation for topsoil installation will begin the week of 7/28.
    • Installation of the concrete path along Belmore Lane is scheduled for the week of 7/28.


    Alleys west of Madison Avenue

    • A short portion of the alley will receive concrete curb and valley gutter for drainage purposes. Concrete installation is scheduled for Monday, 7/28.
    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Water service installation on Monroe Ave is scheduled to continue the week of 7/28.
    • Water service installation on Madison Ave is complete.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 7/28.
    • Temporary water lines are scheduled to be setup the week of 7/28.



    Project Area


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Asphalt driveways are complete.
    • Excavation in preparation for topsoil installation will begin the week of 7/28.
    • Installation of the concrete path along Belmore Lane is scheduled for the week of 7/28.


    Alleys west of Madison Avenue

    • A short portion of the alley will receive concrete curb and valley gutter for drainage purposes. Concrete installation is scheduled for Monday, 7/28.
    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Water service installation on Monroe Ave is scheduled to continue the week of 7/28.
    • Water service installation on Madison Ave is complete.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 7/28.
    • Temporary water lines are scheduled to be setup the week of 7/28.



  • Construction Update - 7/18/2025

    Share Construction Update - 7/18/2025 on Facebook Share Construction Update - 7/18/2025 on X (formerly Twitter) Share Construction Update - 7/18/2025 on Linkedin Email Construction Update - 7/18/2025 link

    Project Area

    • See the UPDATED construction phasing map.


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • The first layer of asphalt paving is complete.
    • Asphalt driveways are scheduled for paving the week of 7/21.
    • Excavation in preparation for topsoil installation will begin the week of 7/21.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Watermain replacement is complete on Monroe and Madison Aves.
    • Water service installation will continue the week of 7/21.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 7/21.


    Project Area

    • See the UPDATED construction phasing map.


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • The first layer of asphalt paving is complete.
    • Asphalt driveways are scheduled for paving the week of 7/21.
    • Excavation in preparation for topsoil installation will begin the week of 7/21.


    Alleys west of Madison Avenue

    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Watermain replacement is complete on Monroe and Madison Aves.
    • Water service installation will continue the week of 7/21.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave, Jefferson Ave and Washington Ave will continue into the week of 7/21.


  • Construction Update - 7/11/2025

    Share Construction Update - 7/11/2025 on Facebook Share Construction Update - 7/11/2025 on X (formerly Twitter) Share Construction Update - 7/11/2025 on Linkedin Email Construction Update - 7/11/2025 link

    Project Area

    • The neighborhood phasing map has changed for the second consecutive week. See the UPDATED construction phasing map.


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Concrete curb and gutter installation is complete. Driveways will be accessible by the end of the day on Wednesday, 7/16.
    • The first layer of asphalt paving is scheduled for Thursday, 7/17, weather permitting.
    • Asphalt driveways will be replaced at a later date.


    Alleys west of Madison Avenue

    • Storm sewer replacement in the alley between Madison Ave and Jefferson Ave is complete.
    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Watermain replacement is complete on Monroe and Madison Aves.
    • Water service installation will begin the week of 7/14.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave and Washington Ave are scheduled to begin on Monday, 7/14.


    Project Area

    • The neighborhood phasing map has changed for the second consecutive week. See the UPDATED construction phasing map.


    All Phases

    • PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
    • Vehicles cannot be parked on the street during construction.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    Phase 1

    • Concrete curb and gutter installation is complete. Driveways will be accessible by the end of the day on Wednesday, 7/16.
    • The first layer of asphalt paving is scheduled for Thursday, 7/17, weather permitting.
    • Asphalt driveways will be replaced at a later date.


    Alleys west of Madison Avenue

    • Storm sewer replacement in the alley between Madison Ave and Jefferson Ave is complete.
    • Alley paving will occur at a future date when the Phase 2 roadways are paved.


    Phase 2

    • Watermain replacement is complete on Monroe and Madison Aves.
    • Water service installation will begin the week of 7/14.


    Phase 3

    • Removals of the existing curb and driveway ends on Adams Ave and Washington Ave are scheduled to begin on Monday, 7/14.


  • Construction Update – 7/3/2025

    Share Construction Update – 7/3/2025 on Facebook Share Construction Update – 7/3/2025 on X (formerly Twitter) Share Construction Update – 7/3/2025 on Linkedin Email Construction Update – 7/3/2025 link
    supporting image

    No work will occur on Friday, 7/4. Have a safe and happy Happy 4th of July!


    Project Area

    • The neighborhood phasing map has CHANGED. See the UPDATED construction phasing map.


    Phase 1

    • Vehicles cannot be parked on the street during construction.
    • Roadway excavation on Van Buren Ave is complete.
    • Concrete curb and gutter installation is scheduled to begin on Tuesday, 7/8 weather permitting.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Alleys west of Madison Avenue

    • Storm sewer replacement in the alley between Madison Ave and Jefferson Ave has been rescheduled for the week of 7/7.
    • Alley paving will occur at a future date when the roadways are paved.


    Phase 2

    • Temporary water line installation is complete.
    • Watermain replacement on Monroe Ave will continue into the week of 7/7.
    • Watermain replacement on Madison Ave is scheduled to begin the week of 7/7.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 3

    • Reclaiming the road pavement is scheduled for 7/9. Reclaiming is the process of grinding the existing asphalt into a gravel base.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


    No work will occur on Friday, 7/4. Have a safe and happy Happy 4th of July!


    Project Area

    • The neighborhood phasing map has CHANGED. See the UPDATED construction phasing map.


    Phase 1

    • Vehicles cannot be parked on the street during construction.
    • Roadway excavation on Van Buren Ave is complete.
    • Concrete curb and gutter installation is scheduled to begin on Tuesday, 7/8 weather permitting.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Alleys west of Madison Avenue

    • Storm sewer replacement in the alley between Madison Ave and Jefferson Ave has been rescheduled for the week of 7/7.
    • Alley paving will occur at a future date when the roadways are paved.


    Phase 2

    • Temporary water line installation is complete.
    • Watermain replacement on Monroe Ave will continue into the week of 7/7.
    • Watermain replacement on Madison Ave is scheduled to begin the week of 7/7.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 3

    • Reclaiming the road pavement is scheduled for 7/9. Reclaiming is the process of grinding the existing asphalt into a gravel base.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


Page last updated: 26 Jun 2026, 01:51 PM