Prospect Knolls A/C/D Neighborhood Roadway Reconstruction

Share Prospect Knolls A/C/D Neighborhood Roadway Reconstruction on Facebook Share Prospect Knolls A/C/D Neighborhood Roadway Reconstruction on X (formerly Twitter) Share Prospect Knolls A/C/D Neighborhood Roadway Reconstruction on Linkedin Email Prospect Knolls A/C/D Neighborhood Roadway Reconstruction link
Map showing the Prospect Knolls neighborhood and the project limits.

Prospect Knolls A/C/D Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

The proposed 2026 reconstruction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Installation or replacement of concrete curb and gutter,
  • Replacement of a portion of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • The project is funded by a combination of special assessments, property taxes, and respective utility funds.
  • Based on the assessment policy, 52.6% of the roadway project costs will be assessed to Prospect Knolls A/C/D property owners, and 47.4% of the roadway project costs will be paid for by property taxes. Estimated preliminary assessment amounts, by district, are:
    • District 1 - $19,000 per Residential Equivalent Unit (REU)
    • District 2 - $9,700 per REU
    • District 3 - $1,700 per multi-family residential unit (condominium)

Prospect Knolls A/C/D Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

The proposed 2026 reconstruction project includes:

  • Complete reconstruction of the roadway asphalt pavement,
  • Installation or replacement of concrete curb and gutter,
  • Replacement of a portion of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • The project is funded by a combination of special assessments, property taxes, and respective utility funds.
  • Based on the assessment policy, 52.6% of the roadway project costs will be assessed to Prospect Knolls A/C/D property owners, and 47.4% of the roadway project costs will be paid for by property taxes. Estimated preliminary assessment amounts, by district, are:
    • District 1 - $19,000 per Residential Equivalent Unit (REU)
    • District 2 - $9,700 per REU
    • District 3 - $1,700 per multi-family residential unit (condominium)
  • Private Electric Service Lines to Homes: What Residents Should Know

    Share Private Electric Service Lines to Homes: What Residents Should Know on Facebook Share Private Electric Service Lines to Homes: What Residents Should Know on X (formerly Twitter) Share Private Electric Service Lines to Homes: What Residents Should Know on Linkedin Email Private Electric Service Lines to Homes: What Residents Should Know link

    Xcel Energy provide the City the following statement:

    Xcel Energy’s current standard is to install, own, and maintain any basic electric service to a residential customer. In other words, Xcel Energy will own the cable that runs from our equipment to the meter on the customer’s house. Xcel Energy refers to this as a “company-owned service”.

    In the past, Xcel Energy allowed residential customers to install and own their underground service themselves. Xcel Energy refers to these services as “customer-owned” or “private” services. While they don’t meet Xcel Energy's current standards, many of them are still in place. Xcel Energy has confirmed that some homes in this area have private (customer-owned) underground electric service lines.

    Private and company-owned services are treated differently when they fault, i.e. something goes wrong with the underground wires, causing an outage. For a company-owned service, Xcel Energy is responsible and will repair or replace faulty service wires at no cost to the customer.

    For a private service, the customer is responsible. If there is a fault in a private service the customer can fix the service wires themselves by hiring an electrician or apply for Xcel Energy to replace their faulty service wires with a company-owned service. Once your service is company-owned, Xcel Energy will be responsible for repairing or replacing faulty service wires going forward at no cost. There will be costs associated with converting to a company owned service.

    Xcel Energy is mailing letters to customers in this area who are currently known to have private services. The letter will include more detailed information on these options. To find out more information on this topic, please contact Xcel Energy at 1-800-895-4999.

    Xcel Energy provide the City the following statement:

    Xcel Energy’s current standard is to install, own, and maintain any basic electric service to a residential customer. In other words, Xcel Energy will own the cable that runs from our equipment to the meter on the customer’s house. Xcel Energy refers to this as a “company-owned service”.

    In the past, Xcel Energy allowed residential customers to install and own their underground service themselves. Xcel Energy refers to these services as “customer-owned” or “private” services. While they don’t meet Xcel Energy's current standards, many of them are still in place. Xcel Energy has confirmed that some homes in this area have private (customer-owned) underground electric service lines.

    Private and company-owned services are treated differently when they fault, i.e. something goes wrong with the underground wires, causing an outage. For a company-owned service, Xcel Energy is responsible and will repair or replace faulty service wires at no cost to the customer.

    For a private service, the customer is responsible. If there is a fault in a private service the customer can fix the service wires themselves by hiring an electrician or apply for Xcel Energy to replace their faulty service wires with a company-owned service. Once your service is company-owned, Xcel Energy will be responsible for repairing or replacing faulty service wires going forward at no cost. There will be costs associated with converting to a company owned service.

    Xcel Energy is mailing letters to customers in this area who are currently known to have private services. The letter will include more detailed information on these options. To find out more information on this topic, please contact Xcel Energy at 1-800-895-4999.

  • Construction Update - 7/10/2026

    Share Construction Update - 7/10/2026 on Facebook Share Construction Update - 7/10/2026 on X (formerly Twitter) Share Construction Update - 7/10/2026 on Linkedin Email Construction Update - 7/10/2026 link

    Gleason Road Closure Notice

    Gleason Road between Schey Drive and Tupa Drive will be closed for utility improvements until approximately Wednesday, 7/22. The detour route will be Hilary Lane and Valley View Road.


    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Work will occur on Saturday, July 11.
    • Please see the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Mail Delivery

    We apologize if delivery of your mail has been disrupted. The City and McNamara continue to coordinate construction activities to provide safe access to temporary mailbox banks and permanent mailboxes whenever possible. However, the City cannot direct USPS delivery operations or require postal carriers to complete deliveries. The City has communicated these concerns to USPS management and continues to request that mail service be provided whenever safe access to the designated delivery location exists.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 1

    • Upcoming Work
      • Tara Road, Kemrich Drive, Antrim Court, and Antrim Terrace curb and gutter installation is scheduled to begin the week of 7/13.
      • Lanham Lane roadway and soil corrections is scheduled to begin the week of 7/13.
      • Lee Valley Circle and Weston Circle sod installation will begin when weather permits.
    • Ongoing Work
      • Tara Road and Kemrich Drive roadway excavation and soil corrections will continue into the week of 7/13.
    • Completed Work
      • Lanham Lane, Kemrich Drive, and Tara Road sump drain installation is complete.
      • Lee Valley Circle, Weston Circle, and Village Drive temporary turf stabilization has been placed until temperatures are suitable for sod placement.


    Phase 2:

    • Upcoming Work
      • Fleetwood Drive roadway excavation and soil corrections is scheduled to begin the week of 7/13.
    • Ongoing Work
      • Fleetwood Drive storm sewer and sump drain installation is scheduled to continue into the week of 7/13.
      • Dublin Road, Kerry Road, and Wexford Road watermain installation will continue the week of 7/6.
    • Completed Work
      • Fleetwood Drive hydrant and gate valve installation is complete.

    Gleason Road Closure Notice

    Gleason Road between Schey Drive and Tupa Drive will be closed for utility improvements until approximately Wednesday, 7/22. The detour route will be Hilary Lane and Valley View Road.


    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • Work will occur on Saturday, July 11.
    • Please see the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Mail Delivery

    We apologize if delivery of your mail has been disrupted. The City and McNamara continue to coordinate construction activities to provide safe access to temporary mailbox banks and permanent mailboxes whenever possible. However, the City cannot direct USPS delivery operations or require postal carriers to complete deliveries. The City has communicated these concerns to USPS management and continues to request that mail service be provided whenever safe access to the designated delivery location exists.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 1

    • Upcoming Work
      • Tara Road, Kemrich Drive, Antrim Court, and Antrim Terrace curb and gutter installation is scheduled to begin the week of 7/13.
      • Lanham Lane roadway and soil corrections is scheduled to begin the week of 7/13.
      • Lee Valley Circle and Weston Circle sod installation will begin when weather permits.
    • Ongoing Work
      • Tara Road and Kemrich Drive roadway excavation and soil corrections will continue into the week of 7/13.
    • Completed Work
      • Lanham Lane, Kemrich Drive, and Tara Road sump drain installation is complete.
      • Lee Valley Circle, Weston Circle, and Village Drive temporary turf stabilization has been placed until temperatures are suitable for sod placement.


    Phase 2:

    • Upcoming Work
      • Fleetwood Drive roadway excavation and soil corrections is scheduled to begin the week of 7/13.
    • Ongoing Work
      • Fleetwood Drive storm sewer and sump drain installation is scheduled to continue into the week of 7/13.
      • Dublin Road, Kerry Road, and Wexford Road watermain installation will continue the week of 7/6.
    • Completed Work
      • Fleetwood Drive hydrant and gate valve installation is complete.
  • Construction Update - 7/2/2026

    Share Construction Update - 7/2/2026 on Facebook Share Construction Update - 7/2/2026 on X (formerly Twitter) Share Construction Update - 7/2/2026 on Linkedin Email Construction Update - 7/2/2026 link

    Gleason Road Closure Notice

    Gleason Road between Schey Drive and Tupa Drive will be closed for utility improvements beginning on Wednesday, 7/8 until approximately Wednesday, 7/22. The detour route will be Hilary Lane and Valley View Road.


    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • No work will occur on Friday, July 3rd in observance of Independence Day holiday.
    • Please see the REVISED construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 1

    • Upcoming Work
      • Sod installation will begin when weather permits
    • Ongoing Work
      • Lanham Lane, Kemrich Drive, and Tara Road sump drain installation will continue into the week of 7/6.
    • Completed Work
      • Mailbox reinstallation on Lee Valley Circle and Weston Circle.


    Phase 2:

    • Upcoming Work
      • Fleetwood Drive hydrant and gate valve installation is scheduled to begin the week of 7/6.
      • Fleetwood Drive storm sewer installation is scheduled to begin the week of 7/6.
    • Ongoing Work
      • Salvaging of remaining mailboxes will continue the week of 7/6. Mailboxes will be placed in front yards
      • Dublin Road and Wexford Road watermain installation will continue the week of 7/6.
    • Completed Work
      • Fleetwood Drive water service installation is complete.

    Gleason Road Closure Notice

    Gleason Road between Schey Drive and Tupa Drive will be closed for utility improvements beginning on Wednesday, 7/8 until approximately Wednesday, 7/22. The detour route will be Hilary Lane and Valley View Road.


    Project Area

    • If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
    • No work will occur on Friday, July 3rd in observance of Independence Day holiday.
    • Please see the REVISED construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 1

    • Upcoming Work
      • Sod installation will begin when weather permits
    • Ongoing Work
      • Lanham Lane, Kemrich Drive, and Tara Road sump drain installation will continue into the week of 7/6.
    • Completed Work
      • Mailbox reinstallation on Lee Valley Circle and Weston Circle.


    Phase 2:

    • Upcoming Work
      • Fleetwood Drive hydrant and gate valve installation is scheduled to begin the week of 7/6.
      • Fleetwood Drive storm sewer installation is scheduled to begin the week of 7/6.
    • Ongoing Work
      • Salvaging of remaining mailboxes will continue the week of 7/6. Mailboxes will be placed in front yards
      • Dublin Road and Wexford Road watermain installation will continue the week of 7/6.
    • Completed Work
      • Fleetwood Drive water service installation is complete.
  • Construction Update - 6/26/2026

    Share Construction Update - 6/26/2026 on Facebook Share Construction Update - 6/26/2026 on X (formerly Twitter) Share Construction Update - 6/26/2026 on Linkedin Email Construction Update - 6/26/2026 link

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Crews may be on site Saturday 6/27 installing topsoil on Weston Circle, Lee Valley Circle, and Village Drive
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.

    Phase 1

    • Upcoming Work
      • Lanham Lane, Kemrich Drive, and Tara Road sump drain installation is scheduled to begin the week of 6/29.
      • Lee Valley Circle, Weston Circle, and Village Drive mailbox installation is scheduled to begin late during the week of 6/29.
        • Mail delivery to your permanent mailbox should resume soon after it's installed.
    • Ongoing Work
      • Lee Valley Circle, Weston Circle, and Village Drive topsoil installation will continue into the week of 6/29.
    • Completed Work
      • Lanham Lane, Tara Road, Kemrich Drive, Antrim Court, and Antrim Terrace storm sewer installation is complete.

    Phase 2:

    • Upcoming Work
      • Dublin Road and Wexford Road watermain installation is scheduled to begin the week of 6/29.
      • Fleetwood Drive water service replacement is scheduled to begin the week of 6/29.

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Crews may be on site Saturday 6/27 installing topsoil on Weston Circle, Lee Valley Circle, and Village Drive
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.

    Phase 1

    • Upcoming Work
      • Lanham Lane, Kemrich Drive, and Tara Road sump drain installation is scheduled to begin the week of 6/29.
      • Lee Valley Circle, Weston Circle, and Village Drive mailbox installation is scheduled to begin late during the week of 6/29.
        • Mail delivery to your permanent mailbox should resume soon after it's installed.
    • Ongoing Work
      • Lee Valley Circle, Weston Circle, and Village Drive topsoil installation will continue into the week of 6/29.
    • Completed Work
      • Lanham Lane, Tara Road, Kemrich Drive, Antrim Court, and Antrim Terrace storm sewer installation is complete.

    Phase 2:

    • Upcoming Work
      • Dublin Road and Wexford Road watermain installation is scheduled to begin the week of 6/29.
      • Fleetwood Drive water service replacement is scheduled to begin the week of 6/29.
  • Construction Update - 6/19/2026

    Share Construction Update - 6/19/2026 on Facebook Share Construction Update - 6/19/2026 on X (formerly Twitter) Share Construction Update - 6/19/2026 on Linkedin Email Construction Update - 6/19/2026 link

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Crews may be onsite on Saturday 6/20 preparing for pavement reclamation in Phase 1.
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.

    Phase 1

    • Upcoming Work
      • Lanham Lane and Tara Road storm sewer and sump drain installation is scheduled to begin the week of 6/22.
      • Tara Road, Antrim Court, Antrim Terrace, and Lanham Lane reclaiming of existing asphalt is scheduled for Monday, 6/22.
      • Weston Circle, Lee Valley Circle, and Village Drive topsoil installation is scheduled to begin the week of 6/22.
    • Ongoing Work
      • Kemrich Drive, Antrim Court, Antrim Terrace, and Tara Road storm sewer installation will continue into the week of 6/22.
    • Completed Work
      • Lanham Lane, Tara Road, Antrim Court, and Antrim Terrace water service installation is complete.

    Phase 2:

    • Completed Work
      • Mail boxes have been salvaged and placed in front yards.
        • Temporary mail bank information can be found here.

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Crews may be onsite on Saturday 6/20 preparing for pavement reclamation in Phase 1.
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.

    Phase 1

    • Upcoming Work
      • Lanham Lane and Tara Road storm sewer and sump drain installation is scheduled to begin the week of 6/22.
      • Tara Road, Antrim Court, Antrim Terrace, and Lanham Lane reclaiming of existing asphalt is scheduled for Monday, 6/22.
      • Weston Circle, Lee Valley Circle, and Village Drive topsoil installation is scheduled to begin the week of 6/22.
    • Ongoing Work
      • Kemrich Drive, Antrim Court, Antrim Terrace, and Tara Road storm sewer installation will continue into the week of 6/22.
    • Completed Work
      • Lanham Lane, Tara Road, Antrim Court, and Antrim Terrace water service installation is complete.

    Phase 2:

    • Completed Work
      • Mail boxes have been salvaged and placed in front yards.
        • Temporary mail bank information can be found here.
  • Construction Update - 6/12/2026

    Share Construction Update - 6/12/2026 on Facebook Share Construction Update - 6/12/2026 on X (formerly Twitter) Share Construction Update - 6/12/2026 on Linkedin Email Construction Update - 6/12/2026 link

    Project Area

    • The contractor is scheduled to work on Juneteenth, Friday, June 16
    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.

    Phase 1

    • Upcoming Work
      • The first layer of asphalt paving on Weston Circle, Lee Valley Circle, and Village Drive is expected to occur on Tuesday, 6/16.
      • Tara Road, Kemrich Drive, Antrim Court, and Antrim Terrace storm sewer installation is scheduled to begin the week of 6/15.
      • Antrim Court and Antrim Terrace water service installation will begin the week of 6/15.
      • Lanham Lane hydrant and gate valve installation is scheduled to begin the week of 6/15.
    • Ongoing Work
      • Lanham Lane, Kemrich Drive, and Tara Road water service installation will continue into the week of 6/15.

    Phase 2:

    • Upcoming Work
      • Mail boxes will be salvaged and placed in front yards on 6/19.
        • Temporary mail bank information can be found here.
      • Dublin Circle temporary water main setup in preparation for water main improvements is scheduled to begin the week of 6/15.
      • Dublin Circle and W 70th Street hydrant and gate valve installation is scheduled to begin the week of 6/15.
      • Dublin Circle and W 70th Street gas main removal is scheduled to occur during the week of 6/15.

    Project Area

    • The contractor is scheduled to work on Juneteenth, Friday, June 16
    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1 & 2:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.

    Phase 1

    • Upcoming Work
      • The first layer of asphalt paving on Weston Circle, Lee Valley Circle, and Village Drive is expected to occur on Tuesday, 6/16.
      • Tara Road, Kemrich Drive, Antrim Court, and Antrim Terrace storm sewer installation is scheduled to begin the week of 6/15.
      • Antrim Court and Antrim Terrace water service installation will begin the week of 6/15.
      • Lanham Lane hydrant and gate valve installation is scheduled to begin the week of 6/15.
    • Ongoing Work
      • Lanham Lane, Kemrich Drive, and Tara Road water service installation will continue into the week of 6/15.

    Phase 2:

    • Upcoming Work
      • Mail boxes will be salvaged and placed in front yards on 6/19.
        • Temporary mail bank information can be found here.
      • Dublin Circle temporary water main setup in preparation for water main improvements is scheduled to begin the week of 6/15.
      • Dublin Circle and W 70th Street hydrant and gate valve installation is scheduled to begin the week of 6/15.
      • Dublin Circle and W 70th Street gas main removal is scheduled to occur during the week of 6/15.
  • Construction Update - 6/5/2026

    Share Construction Update - 6/5/2026 on Facebook Share Construction Update - 6/5/2026 on X (formerly Twitter) Share Construction Update - 6/5/2026 on Linkedin Email Construction Update - 6/5/2026 link

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.
    • Upcoming Work
      • Remaining concrete installation on Village Drive and Weston Circle is scheduled to occur the week of 6/8.
      • Driveways are scheduled to be temporarily restored with gravel on 6/8.
      • Following concrete curing, roadway grading in preparation for the first layer of paving will occur on Lee Valley Circle, Village Drive, and Weston Circle.
      • Tara Road, Antrim Court and Antrim Terrace water service installation will begin the week of 6/8.
    • Ongoing Work
      • Lanham Lane water service installation will continue into the week of 6/8.
    • Completed Work
      • Watermain installation on Tara Road, Antrim Court, and Antrim Terrace is complete.

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1:

    • General Notes
      • Vehicles cannot be parked on the street during construction working hours.
      • Check your front door daily for notification of temporary driveway access or water loss.
    • Upcoming Work
      • Remaining concrete installation on Village Drive and Weston Circle is scheduled to occur the week of 6/8.
      • Driveways are scheduled to be temporarily restored with gravel on 6/8.
      • Following concrete curing, roadway grading in preparation for the first layer of paving will occur on Lee Valley Circle, Village Drive, and Weston Circle.
      • Tara Road, Antrim Court and Antrim Terrace water service installation will begin the week of 6/8.
    • Ongoing Work
      • Lanham Lane water service installation will continue into the week of 6/8.
    • Completed Work
      • Watermain installation on Tara Road, Antrim Court, and Antrim Terrace is complete.
  • Construction Update - 5/29/2026

    Share Construction Update - 5/29/2026 on Facebook Share Construction Update - 5/29/2026 on X (formerly Twitter) Share Construction Update - 5/29/2026 on Linkedin Email Construction Update - 5/29/2026 link

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.
    • CenterPoint Energy completed gas main and service replacements.


    Phase 1:

    • General Notes
      • Vehicles cannot be parked on the street during construction.
      • Check your front door daily for notification of temporary driveway access or water loss.
      • Work will occur on Saturday, 5/30.
    • Upcoming Work
      • Concrete curb & gutter and concrete driveway installation on Village Drive, Lee Valley Circle, and Weston Circle is scheduled to begin on Monday. 6/1.
        • Driveways will be inaccessible for 5 days once the curb is poured to allow the concrete to cure.
        • Door hanger notifications have been delivered with parking information during concrete curb installation and curing.
    • Ongoing Work
      • Lanham Ln water service installation will continue into the week of 6/1.
      • Tara Road, Antrim Terrace, and Antrim Court watermain installation will continue into the week of 6/1.
    • Completed Work
      • Sump drain installation on Lee Valley Circle and Weston Circle is complete.
      • Watermain installation on Lanham Lane near Kemrich Drive is complete.

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.
    • CenterPoint Energy completed gas main and service replacements.


    Phase 1:

    • General Notes
      • Vehicles cannot be parked on the street during construction.
      • Check your front door daily for notification of temporary driveway access or water loss.
      • Work will occur on Saturday, 5/30.
    • Upcoming Work
      • Concrete curb & gutter and concrete driveway installation on Village Drive, Lee Valley Circle, and Weston Circle is scheduled to begin on Monday. 6/1.
        • Driveways will be inaccessible for 5 days once the curb is poured to allow the concrete to cure.
        • Door hanger notifications have been delivered with parking information during concrete curb installation and curing.
    • Ongoing Work
      • Lanham Ln water service installation will continue into the week of 6/1.
      • Tara Road, Antrim Terrace, and Antrim Court watermain installation will continue into the week of 6/1.
    • Completed Work
      • Sump drain installation on Lee Valley Circle and Weston Circle is complete.
      • Watermain installation on Lanham Lane near Kemrich Drive is complete.
  • Construction Update - 5/22/2026

    Share Construction Update - 5/22/2026 on Facebook Share Construction Update - 5/22/2026 on X (formerly Twitter) Share Construction Update - 5/22/2026 on Linkedin Email Construction Update - 5/22/2026 link

    Project Area

    • No work will occur on Memorial Day, Monday, 5/25.
    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Traffic Update:

    • Expect delays on Lanham Ln southbound at Kemrich Dr on 5/27 and 5/28. Please utilize northbound Lanham Ln toward W. 70th St.


    Phase 1:

    • Vehicles cannot be parked on the street during construction.
    • Lanham Ln watermain installation near Kemrich Drive is scheduled to begin the week of 5/26.
      • Please refer to the map here showing where watermain will be replaced.
    • The City's contractor, McNamara Contracting, will be reaching out to residents on Lanham Lane and Tara Road to set up temporary water service to homes getting watermain replacement.
      • Please see the sample door hanger notice here that will be given out to affected properties.
    • Weston Circle and Lee Valley Circle sump drain installation will continue into the week of 5/26.
    • Watermain installation on Lanham Lane from W 70th Street to Fleetwood Drive is complete.
    • Check your front door daily for notification of temporary driveway access or water loss.


    CenterPoint Energy:

    • CenterPoint Energy will continue installing new gas service lines the week of 5/26 and is expected to be complete by mid-June.
    • CenterPoint Energy will be doing some restoration work including driveway patching. All questions and concerns related to their restoration should be directed to CenterPoint Energy. They can be reached at
      • csv.restoration@centerpointenergy.com or 612-321-5477.
    • CenterPoint Energy's work is not part of the City's Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at
      • csv.constructionservices@centerpointenergy.com or 612-542-6198.
    • For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.

    Project Area

    • No work will occur on Memorial Day, Monday, 5/25.
    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Traffic Update:

    • Expect delays on Lanham Ln southbound at Kemrich Dr on 5/27 and 5/28. Please utilize northbound Lanham Ln toward W. 70th St.


    Phase 1:

    • Vehicles cannot be parked on the street during construction.
    • Lanham Ln watermain installation near Kemrich Drive is scheduled to begin the week of 5/26.
      • Please refer to the map here showing where watermain will be replaced.
    • The City's contractor, McNamara Contracting, will be reaching out to residents on Lanham Lane and Tara Road to set up temporary water service to homes getting watermain replacement.
      • Please see the sample door hanger notice here that will be given out to affected properties.
    • Weston Circle and Lee Valley Circle sump drain installation will continue into the week of 5/26.
    • Watermain installation on Lanham Lane from W 70th Street to Fleetwood Drive is complete.
    • Check your front door daily for notification of temporary driveway access or water loss.


    CenterPoint Energy:

    • CenterPoint Energy will continue installing new gas service lines the week of 5/26 and is expected to be complete by mid-June.
    • CenterPoint Energy will be doing some restoration work including driveway patching. All questions and concerns related to their restoration should be directed to CenterPoint Energy. They can be reached at
      • csv.restoration@centerpointenergy.com or 612-321-5477.
    • CenterPoint Energy's work is not part of the City's Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at
      • csv.constructionservices@centerpointenergy.com or 612-542-6198.
    • For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.
  • Construction Update - 5/15/2026

    Share Construction Update - 5/15/2026 on Facebook Share Construction Update - 5/15/2026 on X (formerly Twitter) Share Construction Update - 5/15/2026 on Linkedin Email Construction Update - 5/15/2026 link

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1:

    • Vehicles cannot be parked on the street during construction.
    • All roads are scheduled to be reclaimed on 5/18. Reclaiming is the process of grinding the existing asphalt into a gravel base.
      • Lanham Ln will be partially reclaimed. The remainder will be reclaimed as the work progresses to reduce erosion.
    • Lanham Ln new watermain installation will begin the week of 5/18.
      • Please refer to the map here showing where watermain will be replaced.
    • The City's contractor, McNamara Contracting, will be reaching out to residents on Lanham Lane to set up temporary water service to homes getting watermain replacement.
      • Please see the sample door hanger notice here that will be given out to affected properties.
    • Antrim Ct, Antrim Terr, and Tara Rd temporary watermain set up will continue into the week of 5/18.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Hydrant, watermain gate valve, and water service replacement on Lee Valley Circle and Weston Circle are complete.


    Xcel Energy:

    • Xcel Energy began removing streetlights on Lanham Lane, Tara Road, Kemrich Drive, Weston Circle, and Village Drive to prepare for their upcoming streetlight replacement project.


    CenterPoint Energy:

    • CenterPoint Energy will start installing new gas service lines the week of 5/18 and is expected to be complete by mid-June.
    • CenterPoint Energy has completed gas main installation.
    • CenterPoint Energy's work is not part of the City's Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at
      • csv.constructionservices@centerpointenergy.com or 612-542-6198.
    • For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.

    Project Area

    • See the construction phasing map.
    • Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
    • All work dates below are weather permitting.


    Phase 1:

    • Vehicles cannot be parked on the street during construction.
    • All roads are scheduled to be reclaimed on 5/18. Reclaiming is the process of grinding the existing asphalt into a gravel base.
      • Lanham Ln will be partially reclaimed. The remainder will be reclaimed as the work progresses to reduce erosion.
    • Lanham Ln new watermain installation will begin the week of 5/18.
      • Please refer to the map here showing where watermain will be replaced.
    • The City's contractor, McNamara Contracting, will be reaching out to residents on Lanham Lane to set up temporary water service to homes getting watermain replacement.
      • Please see the sample door hanger notice here that will be given out to affected properties.
    • Antrim Ct, Antrim Terr, and Tara Rd temporary watermain set up will continue into the week of 5/18.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Hydrant, watermain gate valve, and water service replacement on Lee Valley Circle and Weston Circle are complete.


    Xcel Energy:

    • Xcel Energy began removing streetlights on Lanham Lane, Tara Road, Kemrich Drive, Weston Circle, and Village Drive to prepare for their upcoming streetlight replacement project.


    CenterPoint Energy:

    • CenterPoint Energy will start installing new gas service lines the week of 5/18 and is expected to be complete by mid-June.
    • CenterPoint Energy has completed gas main installation.
    • CenterPoint Energy's work is not part of the City's Neighborhood Roadway Reconstruction contract. All questions and concerns related to their work should be directed to CenterPoint Energy. They can be reached at
      • csv.constructionservices@centerpointenergy.com or 612-542-6198.
    • For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.
Page last updated: 18 Sep 2026, 12:37 PM