Prospect Knolls A/C/D Neighborhood Roadway Reconstruction
Prospect Knolls A/C/D Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!
The proposed 2026 reconstruction project includes:
- Complete reconstruction of the roadway asphalt pavement,
- Installation or replacement of concrete curb and gutter,
- Replacement of a portion of the watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems, and
- The project is funded by a combination of special assessments, property taxes, and respective utility funds.
- Based on the assessment policy, 52.6% of the roadway project costs will be assessed to Prospect Knolls A/C/D property owners, and 47.4% of the roadway project costs will be paid for by property taxes. Estimated preliminary assessment amounts, by district, are:
- District 1 - $19,000 per Residential Equivalent Unit (REU)
- District 2 - $9,700 per REU
- District 3 - $1,700 per multi-family residential unit (condominium)
Prospect Knolls A/C/D Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!
The proposed 2026 reconstruction project includes:
- Complete reconstruction of the roadway asphalt pavement,
- Installation or replacement of concrete curb and gutter,
- Replacement of a portion of the watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems, and
- The project is funded by a combination of special assessments, property taxes, and respective utility funds.
- Based on the assessment policy, 52.6% of the roadway project costs will be assessed to Prospect Knolls A/C/D property owners, and 47.4% of the roadway project costs will be paid for by property taxes. Estimated preliminary assessment amounts, by district, are:
- District 1 - $19,000 per Residential Equivalent Unit (REU)
- District 2 - $9,700 per REU
- District 3 - $1,700 per multi-family residential unit (condominium)
-
Construction Update- 9/18/26
Share Construction Update- 9/18/26 on Facebook Share Construction Update- 9/18/26 on X (formerly Twitter) Share Construction Update- 9/18/26 on Linkedin Email Construction Update- 9/18/26 linkProject Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
- Tree replacements will happen later in the fall.
- The final layer of asphalt will be installed later in the fall.
Phase 1:
- Ongoing Work (week of 9/21)
- Lanham Lane, Kemrich Drive (East of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
- Backfilling behind curb in preparation for topsoil installation
- Landscape restoration
- Sod installation
- Lanham Lane, Kemrich Drive (East of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
Phase 2:
- Upcoming Work (week of 9/21)
- Dublin Circle, Dublin Road, Antrim Road, and 70th St
- Restoring access to driveways
- Paving the base layer of asphalt
- Dublin Circle, Dublin Road, Antrim Road, and 70th St
- Ongoing Work
- Tralee Drive
- Backfilling behind curb in preparation for topsoil installation
- Irrigation and landscape restoration
- Tralee Drive
Phase 3:
- Upcoming Work (week of 9/21)
- Down Road, Lee Valley Road, Kemrich Drive (West of Lanham Lane)
- Water service replacement
- Fire hydrant and gate valve replacement
- Removal of existing curb and gutter on Kemrich Drive
- Down Road, Lee Valley Road, Kemrich Drive (West of Lanham Lane)
- Completed Work
- Mailbox removals. The temporary mail bank is located at W 69th adjacent to Calvary Lutheran Church.
Project Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
- Tree replacements will happen later in the fall.
- The final layer of asphalt will be installed later in the fall.
Phase 1:
- Ongoing Work (week of 9/21)
- Lanham Lane, Kemrich Drive (East of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
- Backfilling behind curb in preparation for topsoil installation
- Landscape restoration
- Sod installation
- Lanham Lane, Kemrich Drive (East of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
Phase 2:
- Upcoming Work (week of 9/21)
- Dublin Circle, Dublin Road, Antrim Road, and 70th St
- Restoring access to driveways
- Paving the base layer of asphalt
- Dublin Circle, Dublin Road, Antrim Road, and 70th St
- Ongoing Work
- Tralee Drive
- Backfilling behind curb in preparation for topsoil installation
- Irrigation and landscape restoration
- Tralee Drive
Phase 3:
- Upcoming Work (week of 9/21)
- Down Road, Lee Valley Road, Kemrich Drive (West of Lanham Lane)
- Water service replacement
- Fire hydrant and gate valve replacement
- Removal of existing curb and gutter on Kemrich Drive
- Down Road, Lee Valley Road, Kemrich Drive (West of Lanham Lane)
- Completed Work
- Mailbox removals. The temporary mail bank is located at W 69th adjacent to Calvary Lutheran Church.
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
-
Construction Update - 9/11/2026
Share Construction Update - 9/11/2026 on Facebook Share Construction Update - 9/11/2026 on X (formerly Twitter) Share Construction Update - 9/11/2026 on Linkedin Email Construction Update - 9/11/2026 linkProject Area
- Crews will onsite Saturday, 9/12.
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- A revision was made to include the entirety of Shannon Drive in Phase 3.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1:
- Upcoming Work (week of 9/14, unless otherwise noted)
- Village Drive sod installation
- Weston Circle and Lee Valley Circle tree replacements will happen later in the fall
- Ongoing Work
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
- Backfilling behind curb in preparation for topsoil installation
- Landscape restoration
- Sod installation
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
Phase 2:
- Upcoming Work (week of 9/14)
- Fleetwood Drive and Tralee Drive
- Backfilling behind curb in preparation for topsoil installation
- Irrigation and landscape restoration
- Dublin Circle, Dublin Road, Antrim Road, and 70th St
- Curb and gutter installation
- Concrete driveway installation
- Fleetwood Drive and Tralee Drive
- Ongoing Work
- Fleetwood Drive and Tralee Drive
- Backfilling behind curb in preparation for topsoil installation
- Irrigation and landscape restoration
- Completed Work
- Dublin Circle
- Sump line installation continues
Project Area
- Crews will onsite Saturday, 9/12.
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- A revision was made to include the entirety of Shannon Drive in Phase 3.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1:
- Upcoming Work (week of 9/14, unless otherwise noted)
- Village Drive sod installation
- Weston Circle and Lee Valley Circle tree replacements will happen later in the fall
- Ongoing Work
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
- Backfilling behind curb in preparation for topsoil installation
- Landscape restoration
- Sod installation
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
Phase 2:
- Upcoming Work (week of 9/14)
- Fleetwood Drive and Tralee Drive
- Backfilling behind curb in preparation for topsoil installation
- Irrigation and landscape restoration
- Dublin Circle, Dublin Road, Antrim Road, and 70th St
- Curb and gutter installation
- Concrete driveway installation
- Fleetwood Drive and Tralee Drive
- Ongoing Work
- Fleetwood Drive and Tralee Drive
- Backfilling behind curb in preparation for topsoil installation
- Irrigation and landscape restoration
- Completed Work
- Dublin Circle
- Sump line installation continues
-
Construction Update - 9/4/2026
Share Construction Update - 9/4/2026 on Facebook Share Construction Update - 9/4/2026 on X (formerly Twitter) Share Construction Update - 9/4/2026 on Linkedin Email Construction Update - 9/4/2026 linkProject Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- A revision was made to include the entirety of Shannon Drive in Phase 3.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1:
- Upcoming Work (week of 9/7)
- Village Drive sod installation.
- Weston Circle and Lee Valley Circle tree replacements will happen later in the fall.
- Ongoing Work
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
- Backfilling behind curb in preparation for topsoil installation.
- Irrigation and landscape restoration
- Paver driveway reinstallation
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
Phase 2:
- Upcoming Work (week of 9/7)
- Fleetwood Drive and Tralee Drive
- Backfilling behind curb in preparation for topsoil installation.
- Irrigation and landscape restoration.
- Mailbox reinstallation
- Fleetwood Drive and Tralee Drive
- Kerry Road, Dublin Road, Antrim Road and Wexford Road
- Removal of poor soils in preparation for curb and gutter installation
- Curb and Gutter installation
- Ongoing Work
- Dublin Circle
- Sump line installation continues.
Project Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- A revision was made to include the entirety of Shannon Drive in Phase 3.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1:
- Upcoming Work (week of 9/7)
- Village Drive sod installation.
- Weston Circle and Lee Valley Circle tree replacements will happen later in the fall.
- Ongoing Work
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
- Backfilling behind curb in preparation for topsoil installation.
- Irrigation and landscape restoration
- Paver driveway reinstallation
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
Phase 2:
- Upcoming Work (week of 9/7)
- Fleetwood Drive and Tralee Drive
- Backfilling behind curb in preparation for topsoil installation.
- Irrigation and landscape restoration.
- Mailbox reinstallation
- Fleetwood Drive and Tralee Drive
- Kerry Road, Dublin Road, Antrim Road and Wexford Road
- Removal of poor soils in preparation for curb and gutter installation
- Curb and Gutter installation
- Ongoing Work
- Dublin Circle
- Sump line installation continues.
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
-
Construction Update - 8/28/2026
Share Construction Update - 8/28/2026 on Facebook Share Construction Update - 8/28/2026 on X (formerly Twitter) Share Construction Update - 8/28/2026 on Linkedin Email Construction Update - 8/28/2026 linkProject Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- A revision was made to include the entirety of Shannon Drive in Phase 3.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- Crews will be onsite continuing restoration Saturday, 8/29.
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1:
- Upcoming Work (week of 8/31 unless otherwise noted)
- Village Drive sod installation is tentatively scheduled for the week of 9/7.
- Weston Circle and Lee Valley Circle tree replacements will happen at a later date.
- Lanham Lane mailbox reinstallation
- Ongoing Work
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
- Backfilling behind curb in preparation for topsoil installation.
- Irrigation and landscape restoration
- Asphalt driveway paving
- Paver driveway reinstallation
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
Phase 2:
- Upcoming Work (week of 8/31)
- Fleetwood Drive and Tralee Drive
- Backfilling behind curb in preparation for topsoil installation
- Irrigation and landscape restoration
- Asphalt driveway replacements
- Mailbox reinstallation
- Dublin Circle
- Sump drain installation
- Curb and gutter removal
- Kerry Road, Dublin Road and Wexford Road
- Water service installation
- Fleetwood Drive and Tralee Drive
- Completed Work
- Dublin Circle storm sewer installation.
- Dublin Circle and Antrim Road water service installation
- 70th Street sanitary sewer main installation
- Antrim Road storm sewer installation
Project Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- A revision was made to include the entirety of Shannon Drive in Phase 3.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- Crews will be onsite continuing restoration Saturday, 8/29.
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1:
- Upcoming Work (week of 8/31 unless otherwise noted)
- Village Drive sod installation is tentatively scheduled for the week of 9/7.
- Weston Circle and Lee Valley Circle tree replacements will happen at a later date.
- Lanham Lane mailbox reinstallation
- Ongoing Work
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
- Backfilling behind curb in preparation for topsoil installation.
- Irrigation and landscape restoration
- Asphalt driveway paving
- Paver driveway reinstallation
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
Phase 2:
- Upcoming Work (week of 8/31)
- Fleetwood Drive and Tralee Drive
- Backfilling behind curb in preparation for topsoil installation
- Irrigation and landscape restoration
- Asphalt driveway replacements
- Mailbox reinstallation
- Dublin Circle
- Sump drain installation
- Curb and gutter removal
- Kerry Road, Dublin Road and Wexford Road
- Water service installation
- Fleetwood Drive and Tralee Drive
- Completed Work
- Dublin Circle storm sewer installation.
- Dublin Circle and Antrim Road water service installation
- 70th Street sanitary sewer main installation
- Antrim Road storm sewer installation
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
-
Construction Update - 8/21/2026
Share Construction Update - 8/21/2026 on Facebook Share Construction Update - 8/21/2026 on X (formerly Twitter) Share Construction Update - 8/21/2026 on Linkedin Email Construction Update - 8/21/2026 linkProject Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- Please see the construction phasing map
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations
- All work dates below are weather permitting
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours
- Check your front door daily for notification of temporary water loss
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1:
- Upcoming Work (Week of 8/24)
- Lee Valley Circle, Weston Circle and Village Drive sod installation is tentatively scheduled for the week of 8/24.
- Lanham Lane
- Asphalt driveway paving
- Paver driveway reinstallation
- Mailbox installation
- Dublin Circle storm sewer installation
- Ongoing Work
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
- Backfilling behind curb in preparation for topsoil installation.
- Irrigation and landscape restoration
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
Phase 2:
- Upcoming Work(Week of 8/24)
- Fleetwood Drive and Tralee Drive
- Backfilling behind curb in preparation for topsoil installation
- Irrigation and landscape restoration
- Asphalt driveway replacements
- Mailbox installation
- Antrim Road storm sewer installation
- Fleetwood Drive and Tralee Drive
- Ongoing Work
- Kerry Road, Dublin Road and Wexford Road water service installation
- 70th Street sanitary sewer main installation
- Completed Work
- Dublin Circle and Antrim Road water service installation
Project Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- Please see the construction phasing map
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations
- All work dates below are weather permitting
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours
- Check your front door daily for notification of temporary water loss
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1:
- Upcoming Work (Week of 8/24)
- Lee Valley Circle, Weston Circle and Village Drive sod installation is tentatively scheduled for the week of 8/24.
- Lanham Lane
- Asphalt driveway paving
- Paver driveway reinstallation
- Mailbox installation
- Dublin Circle storm sewer installation
- Ongoing Work
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
- Backfilling behind curb in preparation for topsoil installation.
- Irrigation and landscape restoration
- Lanham Lane, Kemrich Drive (east of Lanham Lane), Tara Road, Antrim Court and Antrim Terrace
Phase 2:
- Upcoming Work(Week of 8/24)
- Fleetwood Drive and Tralee Drive
- Backfilling behind curb in preparation for topsoil installation
- Irrigation and landscape restoration
- Asphalt driveway replacements
- Mailbox installation
- Antrim Road storm sewer installation
- Fleetwood Drive and Tralee Drive
- Ongoing Work
- Kerry Road, Dublin Road and Wexford Road water service installation
- 70th Street sanitary sewer main installation
- Completed Work
- Dublin Circle and Antrim Road water service installation
-
Construction Update - 8/14/2026
Share Construction Update - 8/14/2026 on Facebook Share Construction Update - 8/14/2026 on X (formerly Twitter) Share Construction Update - 8/14/2026 on Linkedin Email Construction Update - 8/14/2026 linkProject Area
- Kerry Road between Dublin Road and Wexford Road will have limited access due to watermain installation during the week of 8/17. Expect delays and use alternate routes if you can.
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1:
- Upcoming Work
- Lanham Lane and Kemrich Drive (east of Lanham Lane):
- driveway access will be restored by the end of the day on Monday, 8/17.
- The first layer of asphalt paving is scheduled for the week of 8/17, weather permitting.
- Lee Valley Circle, Weston Circle and Village Drive sod installation is tentatively scheduled for the week of 8/17.
- Lanham Lane and Kemrich Drive (east of Lanham Lane):
- Ongoing Work
- Tara Road, Antrim Court, and Antrim Terrace backfilling behind curb in preparation for topsoil installation.
Phase 2:
- Upcoming Work
- Fleetwood Drive and Tralee Drive
- driveway access will be restored by the end of the day on Monday, 8/17.
- The first layer of asphalt paving is scheduled for the week of 8/17, weather permitting.
- Dublin Circle and Antrim Road water service installation is scheduled for the week of 8/17.
- 70th Street sanitary sewer main installation is scheduled for the week of 8/17.
- Fleetwood Drive and Tralee Drive
- Ongoing Work
- Kerry Road, Dublin Road, Wexford Road water main installation continues the week of 8/17.
- Completed Work
- Tralee Drive and Kerry Road sanitary sewer main lining is complete.
Project Area
- Kerry Road between Dublin Road and Wexford Road will have limited access due to watermain installation during the week of 8/17. Expect delays and use alternate routes if you can.
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1:
- Upcoming Work
- Lanham Lane and Kemrich Drive (east of Lanham Lane):
- driveway access will be restored by the end of the day on Monday, 8/17.
- The first layer of asphalt paving is scheduled for the week of 8/17, weather permitting.
- Lee Valley Circle, Weston Circle and Village Drive sod installation is tentatively scheduled for the week of 8/17.
- Lanham Lane and Kemrich Drive (east of Lanham Lane):
- Ongoing Work
- Tara Road, Antrim Court, and Antrim Terrace backfilling behind curb in preparation for topsoil installation.
Phase 2:
- Upcoming Work
- Fleetwood Drive and Tralee Drive
- driveway access will be restored by the end of the day on Monday, 8/17.
- The first layer of asphalt paving is scheduled for the week of 8/17, weather permitting.
- Dublin Circle and Antrim Road water service installation is scheduled for the week of 8/17.
- 70th Street sanitary sewer main installation is scheduled for the week of 8/17.
- Fleetwood Drive and Tralee Drive
- Ongoing Work
- Kerry Road, Dublin Road, Wexford Road water main installation continues the week of 8/17.
- Completed Work
- Tralee Drive and Kerry Road sanitary sewer main lining is complete.
-
Construction Update - 8/7/2026
Share Construction Update - 8/7/2026 on Facebook Share Construction Update - 8/7/2026 on X (formerly Twitter) Share Construction Update - 8/7/2026 on Linkedin Email Construction Update - 8/7/2026 linkProject Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1
- Upcoming Work
- Lanham Lane and Kemrich Drive (east of Lanham Lane) concrete driveway installation is scheduled for Monday, 8/10.
- Ongoing Work
- Lee Valley Circle, Weston Circle and Village Drive sod installation is tentatively scheduled for the week of 8/17.
- Tara Road, Antrim Court, and Antrim Terrace irrigation repairs are scheduled to continue the week of 8/10.
- Antrim Court/Terrace paver driveway replacements will continue the week of 8/10.
Phase 2:
- Upcoming Work
- Fleetwood Drive and Tralee Drive curb and gutter installation is scheduled for the week of 8/10.
- Dublin Circle water service installation is scheduled for the week of 8/10.
- Crews will be onsite Saturday, 8/8 reclaiming the existing road surface on Kerry Road and W 70th Street.
- Ongoing Work
- Kerry Road, Dublin Road, Wexford Road water main installation resumes.
Project Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1
- Upcoming Work
- Lanham Lane and Kemrich Drive (east of Lanham Lane) concrete driveway installation is scheduled for Monday, 8/10.
- Ongoing Work
- Lee Valley Circle, Weston Circle and Village Drive sod installation is tentatively scheduled for the week of 8/17.
- Tara Road, Antrim Court, and Antrim Terrace irrigation repairs are scheduled to continue the week of 8/10.
- Antrim Court/Terrace paver driveway replacements will continue the week of 8/10.
Phase 2:
- Upcoming Work
- Fleetwood Drive and Tralee Drive curb and gutter installation is scheduled for the week of 8/10.
- Dublin Circle water service installation is scheduled for the week of 8/10.
- Crews will be onsite Saturday, 8/8 reclaiming the existing road surface on Kerry Road and W 70th Street.
- Ongoing Work
- Kerry Road, Dublin Road, Wexford Road water main installation resumes.
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
-
Construction Update - 7/31/2026
Share Construction Update - 7/31/2026 on Facebook Share Construction Update - 7/31/2026 on X (formerly Twitter) Share Construction Update - 7/31/2026 on Linkedin Email Construction Update - 7/31/2026 linkProject Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1
- Upcoming Work
- Lanham Lane and Kemrich Drive east of Lanham Lane curb and gutter installation is tentatively scheduled to begin on Wednesday, 8/5.
- Ongoing Work
- Lee Valley Circle and Weston Circle sod installation will begin when weather permits.
- Tara Road, Antrim Court, and Antrim Terrace irrigation repairs are scheduled to continue the week of 8/3
Phase 2:
- Upcoming Work
- Fleetwood Drive and Tralee Drive curb and gutter installation is tentatively scheduled for the week of 8/10.
- Ongoing Work
- Fleetwood Drive sump drain installation will continue during the week of 8/3.
Project Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Please see the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1
- Upcoming Work
- Lanham Lane and Kemrich Drive east of Lanham Lane curb and gutter installation is tentatively scheduled to begin on Wednesday, 8/5.
- Ongoing Work
- Lee Valley Circle and Weston Circle sod installation will begin when weather permits.
- Tara Road, Antrim Court, and Antrim Terrace irrigation repairs are scheduled to continue the week of 8/3
Phase 2:
- Upcoming Work
- Fleetwood Drive and Tralee Drive curb and gutter installation is tentatively scheduled for the week of 8/10.
- Ongoing Work
- Fleetwood Drive sump drain installation will continue during the week of 8/3.
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
-
Construction Update - 7/24/2026
Share Construction Update - 7/24/2026 on Facebook Share Construction Update - 7/24/2026 on X (formerly Twitter) Share Construction Update - 7/24/2026 on Linkedin Email Construction Update - 7/24/2026 linkGleason Road Closure Notice
Gleason Road between Schey Drive and Tupa Drive will be closed for utility improvements until approximately Monday, 7/27. The detour route will be Hilary Lane and Valley View Road.
Project Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Work will occur on Saturday, July 25.
- Please see the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1
- Upcoming Work
- Tara Road, Antrim Court, and Antrim Terrace mailbox installation is scheduled for the week of 7/27. The contractor will notify you when mail delivery will be restored. Until that time, please continue to collect your mail at the temporary mail bank location.
- Ongoing Work
- Lanham Lane and Kemrich Drive roadway and soil corrections is scheduled to continue into the week of 7/27. Crews will be onsite continuing work on Kemrich Drive Saturday, 7/25.
- Lee Valley Circle and Weston Circle sod installation will begin when weather permits.
- Tara Road, Antrim Court, and Antrim Terrace irrigation repairs are scheduled to continue the week of 7/27.
Phase 2:
- Upcoming Work
- Fleetwood Drive and Tralee Drive roadway excavation and soil corrections is scheduled to begin the week of 7/27.
- Ongoing Work
- Fleetwood Drive sump drain installation will continue during the week of 7/27.
- Completed Work
- Dublin Circle watermain replacement is complete.
- Tralee Drive storm sewer improvements are complete.
Gleason Road Closure Notice
Gleason Road between Schey Drive and Tupa Drive will be closed for utility improvements until approximately Monday, 7/27. The detour route will be Hilary Lane and Valley View Road.
Project Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Work will occur on Saturday, July 25.
- Please see the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1
- Upcoming Work
- Tara Road, Antrim Court, and Antrim Terrace mailbox installation is scheduled for the week of 7/27. The contractor will notify you when mail delivery will be restored. Until that time, please continue to collect your mail at the temporary mail bank location.
- Ongoing Work
- Lanham Lane and Kemrich Drive roadway and soil corrections is scheduled to continue into the week of 7/27. Crews will be onsite continuing work on Kemrich Drive Saturday, 7/25.
- Lee Valley Circle and Weston Circle sod installation will begin when weather permits.
- Tara Road, Antrim Court, and Antrim Terrace irrigation repairs are scheduled to continue the week of 7/27.
Phase 2:
- Upcoming Work
- Fleetwood Drive and Tralee Drive roadway excavation and soil corrections is scheduled to begin the week of 7/27.
- Ongoing Work
- Fleetwood Drive sump drain installation will continue during the week of 7/27.
- Completed Work
- Dublin Circle watermain replacement is complete.
- Tralee Drive storm sewer improvements are complete.
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
-
Construction Update - 7/17/2026
Share Construction Update - 7/17/2026 on Facebook Share Construction Update - 7/17/2026 on X (formerly Twitter) Share Construction Update - 7/17/2026 on Linkedin Email Construction Update - 7/17/2026 linkGleason Road Closure Notice
Gleason Road between Schey Drive and Tupa Drive will be closed for utility improvements until approximately Friday, 7/24. The detour route will be Hilary Lane and Valley View Road.
Project Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Minor work will occur on Saturday, July 18.
- Please see the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1
- Upcoming Work
- Tara Road, Antrim Court, and Antrim Terrace roadway grading in preparation of asphalt paving is scheduled to begin the week of 7/20.
- The first layer of asphalt paving is tentatively scheduled for the end of the week of 7/20.
- Lanham Lane and Kemrich Drive roadway and soil corrections is scheduled to begin the week of 7/20.
- Lee Valley Circle and Weston Circle sod installation will begin when weather permits.
- Tara Road, Antrim Court, and Antrim Terrace roadway grading in preparation of asphalt paving is scheduled to begin the week of 7/20.
Phase 2:
- Upcoming Work
- Fleetwood Drive roadway excavation and soil corrections is scheduled to begin the week of 7/20.
- Dublin Circle watermain installation is scheduled to begin the week of 7/20.
- Tralee Drive storm sewer installation is scheduled to begin the week of 7/20.
- Ongoing Work
- Fleetwood Drive storm sewer and sump drain installation will continue during the week of 7/20.
- Dublin Road, Kerry Road, and Wexford Road watermain installation will continue the week of 7/20.
- Completed Work
- 70th St and Dublin Circle watermain valve replacement is complete.
Gleason Road Closure Notice
Gleason Road between Schey Drive and Tupa Drive will be closed for utility improvements until approximately Friday, 7/24. The detour route will be Hilary Lane and Valley View Road.
Project Area
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
- See the statement provided by Xcel Energy.
- Minor work will occur on Saturday, July 18.
- Please see the construction phasing map.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
- All work dates below are weather permitting.
Phase 1 & 2:
- General Notes
- Vehicles cannot be parked on the street during construction working hours.
- Check your front door daily for notification of temporary water loss.
- Driveway Accessibility
- You will generally have access in and out of your driveway each morning and evening, and potentially throughout the day. Exceptions include periodic excavations in front of your driveway that may last hours. The contractor will knock on your door notifying you of the excavation work and give you time to park your car on the street, so you aren’t blocked in.
Phase 1
- Upcoming Work
- Tara Road, Antrim Court, and Antrim Terrace roadway grading in preparation of asphalt paving is scheduled to begin the week of 7/20.
- The first layer of asphalt paving is tentatively scheduled for the end of the week of 7/20.
- Lanham Lane and Kemrich Drive roadway and soil corrections is scheduled to begin the week of 7/20.
- Lee Valley Circle and Weston Circle sod installation will begin when weather permits.
- Tara Road, Antrim Court, and Antrim Terrace roadway grading in preparation of asphalt paving is scheduled to begin the week of 7/20.
Phase 2:
- Upcoming Work
- Fleetwood Drive roadway excavation and soil corrections is scheduled to begin the week of 7/20.
- Dublin Circle watermain installation is scheduled to begin the week of 7/20.
- Tralee Drive storm sewer installation is scheduled to begin the week of 7/20.
- Ongoing Work
- Fleetwood Drive storm sewer and sump drain installation will continue during the week of 7/20.
- Dublin Road, Kerry Road, and Wexford Road watermain installation will continue the week of 7/20.
- Completed Work
- 70th St and Dublin Circle watermain valve replacement is complete.
- If you have any power outages or electrical appliance issues at your home, please call Xcel Energy at 1-800-895-1999.
Sign Up for Emailed Project Updates
PRIVACY NOTICE: Under M.S. 13.356, your email address is private data. If you do not provide an email address you will not receive requested updates. Your email address will be available to anyone with a work assignment that reasonably require access.
-
Phone 952-826-0444 Email CMoore@EdinaMN.gov -
Phone 952-826-0443 Email aditzler@EdinaMN.gov
During the project there may be unexpected time sensitive resident impacts. In addition to providing those notices on the project page you may opt into receiving text notifications.
To sign up scan the QR code below or text PROSPECT to 844-929-4328.

-
April 27 2026
-
April 07 2026
-
December 16 2025
-
Project Area Map (187 KB) (pdf)
-
Living Streets Typical Section.pdf (885 KB) (pdf)
-
Pedestrian Facilities Master Plan (1.98 MB) (pdf)
-
Bicycle Facilities Master Plan (1.96 MB) (pdf)
-
Proposed Sidewalk Locations (1.28 MB) (pdf)
-
Aug 26 Info Meeting Presentation Slides (5.26 MB) (pdf)
-
Assessment Districts and REUs (195 KB) (pdf)
-
Preliminary Market Benefit Report - Assessment District 1 (3.56 MB) (pdf)
-
Preliminary Market Benefit Report - Assessment District 2 (3.2 MB) (pdf)
-
Preliminary Market Benefit Report - Assessment District 3 (1.83 MB) (pdf)
-
Ped and Bike Interactive Online Mapping 2017 (302 KB) (jpg)
-
Ped and Bike Interactive Online Mapping 2017 - Prospect Knolls (105 KB) (jpg)
-
Prospect Knolls Sidewalk 30 Percent Design DRAFT (9.33 MB) (pdf)
-
Engineering Study (26.6 MB) (pdf)
-
Street Widths (17.1 KB) (docx)
-
Temporary Mailbox Bank Antrim Ct Antrim Terr (1.66 MB) (doc)
-
Temporary Mailbox Bank Lanham Ln Kemrich Tara (1.64 MB) (doc)
-
Temporary Mailbox Bank Lee Valley Cir Weston Cir.doc (1.98 MB) (doc)
-
Construction Kickoff Frequently Asked Questions (73 KB) (docx)
-
Project Area Phasing Map 2026 08 28 (232 KB) (pdf)
-
Prospect Knolls ACD Phase 1 Temp Watermain Map.pdf (221 KB) (pdf)
-
Prospect Knolls ACD Watermain Map.pdf (228 KB) (pdf)
-
Notice - Temporary Water Service Installation_TEMPLATE.docx (29.5 KB) (docx)
-
Temporary Mailbox Bank Phase 2.doc (1.73 MB) (doc)