Southdale B Neighborhood Roadway Reconstruction

Share Southdale B Neighborhood Roadway Reconstruction on Facebook Share Southdale B Neighborhood Roadway Reconstruction on Twitter Share Southdale B Neighborhood Roadway Reconstruction on Linkedin Email Southdale B Neighborhood Roadway Reconstruction link

Southdale B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This project, scheduled for construction in 2024, includes:

  • Complete reconstruction of the asphalt pavement,
  • Complete reconstruction of the concrete pavement with asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete replacement of the majority of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems,
  • Complete replacement of the street lighting system, and
  • Construction of a concrete sidewalk along Barrie Road and a portion of West 65th Street and Heritage Drive to complete gaps in the pedestrian network.
  • A preliminary assessment amount of $950.00 per multi-family residential unit (condominium or apartment owner), was approved by the Council at the December 2023 public hearing. This $950.00 per REU amount has been recorded with Hennepin County as pending assessments for all impacted properties.

Southdale B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This project, scheduled for construction in 2024, includes:

  • Complete reconstruction of the asphalt pavement,
  • Complete reconstruction of the concrete pavement with asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete replacement of the majority of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems,
  • Complete replacement of the street lighting system, and
  • Construction of a concrete sidewalk along Barrie Road and a portion of West 65th Street and Heritage Drive to complete gaps in the pedestrian network.
  • A preliminary assessment amount of $950.00 per multi-family residential unit (condominium or apartment owner), was approved by the Council at the December 2023 public hearing. This $950.00 per REU amount has been recorded with Hennepin County as pending assessments for all impacted properties.
  • Asphalt Paving on Barrie Rd - 10/4/2024

    Share Asphalt Paving on Barrie Rd - 10/4/2024 on Facebook Share Asphalt Paving on Barrie Rd - 10/4/2024 on Twitter Share Asphalt Paving on Barrie Rd - 10/4/2024 on Linkedin Email Asphalt Paving on Barrie Rd - 10/4/2024 link

    Access to Barrie Road from W 66th Street and Heritage Drive will be closed on Friday, 10/4 due to paving the first layer of asphalt on Barrie Rd. This is anticipated to begin at 7 AM.

    • The daytime road closure is anticipated to one day.
    • Barrie Road will be accessible from W 65th Street during this time.
    • Expect short term delays driving on Barrie Road between W 66th Street and Heritage Drive.
    • Delays accessing Barrie Road from properties can be up to 15 minutes due to paving.
    • Please plan your trips to account for these short-term delays.
    • As soon as the large rollers are done compacting the pavement, vehicles can access Barrie Road.
    • A map visualizing this traffic update can be found here.



  • Construction Update - 9/27/2024

    Share Construction Update - 9/27/2024 on Facebook Share Construction Update - 9/27/2024 on Twitter Share Construction Update - 9/27/2024 on Linkedin Email Construction Update - 9/27/2024 link

    Traffic Update

    • Expect short term delays driving on Barrie Road between W 66th Street and Heritage Drive late during the week of 9/30 or during the week of 10/7 due to asphalt paving. Please plan your trips to account for these short-term delays.
    • Access to Barrie Road from W 66th Street and Heritage Drive will be closed during asphalt paving. The daytime closure is anticipated to one day. Barrie Road will be accessible from W 65th Street during this time.
    • Excessive vehicle speeds are prevalent in the project area, so please slow down. We encourage safety for both you AND the construction crew.
    • A map visualizing this traffic update can be found here.


    Barrie Road

    • Driveway apron and concrete sidewalk installation will continue into week of 9/30.
    • The first layer of asphalt paving is scheduled to begin late during the week of 9/30 or during the week of 10/7 following driveway apron installation.
      • Delays accessing Barrie Road from properties can be up to 15 minutes due to paving.
      • As soon as the large rollers are done compacting the pavement, vehicles can access Barrie Road.


    Heritage Drive

    • Tree replacement planting is scheduled to begin week of 9/30.
    • Although the first layer of asphalt is complete, no parking remains in effect on Heritage Drive.


    W. 65th Street

    • Xcel Energy’s relocation of their facilities has been delayed. Sorry for the delay.
    • While the street is gravel, it is open to vehicular traffic. Please drive slowly.


  • Construction Update - 9/20/2024

    Share Construction Update - 9/20/2024 on Facebook Share Construction Update - 9/20/2024 on Twitter Share Construction Update - 9/20/2024 on Linkedin Email Construction Update - 9/20/2024 link

    Barrie Road

    • Driveway aprons and concrete sidewalk installation is scheduled to begin the week of 9/23 and conclude the week of 9/30.


    Heritage Drive

    • Irrigation repairs will continue into week of 9/23.
    • Although the first layer of asphalt is complete, no parking remains in effect on Heritage Drive.


    W. 65th Street

    • Xcel Energy’s relocation of their facilities is scheduled to continue into the week of 9/23.
    • While the street is gravel, it is open to vehicular traffic. Please drive slowly.


  • Construction Update - 9/13/2024

    Share Construction Update - 9/13/2024 on Facebook Share Construction Update - 9/13/2024 on Twitter Share Construction Update - 9/13/2024 on Linkedin Email Construction Update - 9/13/2024 link

    Construction Update – 9/13/2024


    Traffic Update

    • Expect short term delays driving on Barrie Road between W 66th Street and Heritage Drive during the week of 9/16 due to curb installation. Please plan your trips to account for these short-term delays.
    • Excessive vehicle speeds are prevalent in the project area, so please slow down. We encourage safety for both you AND the construction crew.
    • A map visualizing this traffic update can be found here.


    Barrie Road

    • Roadway excavation is complete.
    • Curb installation is scheduled for late during the week of 9/16.


    Heritage Drive

    • Irrigation repairs will continue into week of 9/16.
    • Although the first layer of asphalt is complete, no parking remains in effect on Heritage Drive.


    W. 65th Street

    • While the street is gravel, it is open to vehicular traffic. Please drive slowly.
    • Xcel Energy’s relocation of their facilities is scheduled to begin mid-September. Sorry for the delay.


  • Construction Update - 9/6/2024

    Share Construction Update - 9/6/2024 on Facebook Share Construction Update - 9/6/2024 on Twitter Share Construction Update - 9/6/2024 on Linkedin Email Construction Update - 9/6/2024 link

    Traffic Update

    • Expect short term delays driving on Barrie Road between W 65th Street and Heritage Drive during the week of 9/9. These delays will include closures to excavate for the road. Please plan your trips to account for these short-term delays.
    • Access to properties along Barrie Road between W 65th Street and Heritage Drive will have delays that may be up to 30 minutes. If that is too long of a delay, please refer to map for parking options.
    • Residents of The Colony at Edina with only one driveway access within the road excavation area are encouraged to park on Barrie Road in the yellow areas on the map or be patient with the construction crews.
    • Excessive vehicle speeds are prevalent in the project area, so please slow down. We encourage safety for both you AND the construction crew.
    • A map visualizing this traffic update can be found here.


    Barrie Road

    • Roadway excavation will continue into the week of 9/9 between W 65th Street and Heritage Drive.
    • Curb installation is scheduled for week of 9/16.


    Heritage Drive

    • Irrigation repairs and retaining wall installation is scheduled for the week of 9/9.
    • Although the first layer of asphalt is complete, no parking remains in effect on Heritage Drive.


    W. 65th Street

    • While the street is gravel, it is open to vehicular traffic. Please drive slowly.
    • Xcel Energy’s relocation of their facilities is scheduled to begin mid-September. Sorry for the delay.


  • Construction Update - 9/5/2024

    Share Construction Update - 9/5/2024 on Facebook Share Construction Update - 9/5/2024 on Twitter Share Construction Update - 9/5/2024 on Linkedin Email Construction Update - 9/5/2024 link

    Traffic Update

    • Expect short term delays driving on Barrie Road between W 66th Street and Heritage Drive. These delays will include closures to excavate for the road. Please plan your trips to account for these short-term delays.
    • Access to properties along Barrie Road between W 65th Street and Heritage Drive will have delays that may be up to 30 minutes. If that is too long of a delay, please refer to map for parking options.
    • Residents of The Colony at Edina with only one driveway access within the road excavation area are encouraged to park on Barrie Road in the yellow areas on the map, or be patient with the construction crews.
    • One of the Edina Towers driveways will be open and the other will be closed during the excavation work. Residents of Edina Towers will need to be aware and use the open driveway while the other is closed.
    • Excessive vehicle speeds are prevalent in the project area, so please slow down. We encourage safety for both you AND the construction crew.
    • A map visualizing this traffic update can be found here.
  • Construction Update - 9/4/2024

    Share Construction Update - 9/4/2024 on Facebook Share Construction Update - 9/4/2024 on Twitter Share Construction Update - 9/4/2024 on Linkedin Email Construction Update - 9/4/2024 link

    Traffic Update

    • Expect short term delays driving on Barrie Road between W 66th Street and Heritage Drive. These delays will include closures to excavate for the road. Please plan your trips to account for these short-term delays.
    • Access to properties along Barrie Road between W 65th Street and Heritage Drive will have delays that may be up to 30 minutes. If that is too long of a delay, please refer to map for parking options.
    • Residents of The Colony at Edina with only one driveway access within the road excavation area are encouraged to park on Barrie Road in the yellow areas on the map, or be patient with the construction crews.
    • One of the Edina Towers driveways will be open and the other will be closed during the excavation work. Residents of Edina Towers will need to be aware and use the open driveway while the other is closed.
    • Excessive vehicle speeds are prevalent in the project area, so please slow down. We encourage safety for both you AND the construction crew.
    • A map visualizing this traffic update can be found here.


  • Construction Update - 9/3/2024

    Share Construction Update - 9/3/2024 on Facebook Share Construction Update - 9/3/2024 on Twitter Share Construction Update - 9/3/2024 on Linkedin Email Construction Update - 9/3/2024 link

    Traffic Update

    • The intersection of Barrie Road and W 65th Street will be closed on Wednesday, 9/4 due to road excavation work and will likely open by 9/5.
    • Expect short term delays driving on Barrie Road between W 66th Street and Heritage Drive. These delays will include closures to excavate for the road. Please plan your trips to account for these short-term delays.
    • Access to properties along Barrie Road between W 65th Street and Heritage Drive will have delays that may be up to 30 minutes. If that is too long of a delay, please refer to map for parking options.
    • Residents of The Colony at Edina with only one driveway access within the road excavation area are encouraged to park on Barrie Road in the yellow areas on the map, or be patient with the construction crews.
    • One of the Edina Towers driveways will be open and the other will be closed during the excavation work. Residents of Edina Towers will need to be aware and use the open driveway while the other is closed.
    • Excessive vehicle speeds are prevalent in the project area, so please slow down. We encourage safety for both you AND the construction crew.
    • A map visualizing this traffic update can be found here.
  • Construction Update - 8/30/2024

    Share Construction Update - 8/30/2024 on Facebook Share Construction Update - 8/30/2024 on Twitter Share Construction Update - 8/30/2024 on Linkedin Email Construction Update - 8/30/2024 link

    Crews will not be working during the Monday, 9/2 Labor Day holiday.


    Traffic Update

    • Access to Barrie Road from W 66th Street will be closed on Tuesday, 9/3 due to road excavation work and will likely open by 9/5.
    • Expect short term delays driving on Barrie Road between W 66th Street and Heritage Drive during the week of 9/3. These delays will include closures to excavate for the road. Please plan your trips to account for these short-term delays.
    • Access to Barrie Road businesses between W 66th Street and W 65th Street will be open from the north, with delays that may be up to 30 minutes. If that is too long of a delay, please refer to map for parking options.
    • Excessive vehicle speeds are prevalent in the project area, so please slow down. We encourage safety for both you AND the construction crew.
    • A map visualizing this traffic update can be found here.

    Barrie Road

    • Storm sewer installation is complete.
    • Roadway excavation is scheduled for the week of 9/3 starting on W 66thStreet.
      • This work will cause traffic delays of up to 30 minutes on Barrie Road. Updates will be sent out throughout next week as roadway excavation continues north from W. 66th Street to Heritage Drive.
      • Excavation work is anticipated to last at least one week.


    Heritage Drive

    • Sidewalk installation is complete.
    • Irrigation repairs and retaining wall installation is scheduled for the week of 9/9.
    • Although the first layer of asphalt is complete, no parking remains in effect on Heritage Drive.


    W. 65th Street

    • While the street is gravel, it is open to vehicular traffic. Please drive slowly.
    • Xcel Energy’s relocation of their facilities is scheduled to begin mid-September. Sorry for the delay.
  • Construction Update - 8/23/24

    Share Construction Update - 8/23/24 on Facebook Share Construction Update - 8/23/24 on Twitter Share Construction Update - 8/23/24 on Linkedin Email Construction Update - 8/23/24 link

    Traffic Update

    • Expect short term delays driving on Barrie Road between W 65th Street and Heritage Drive during the week of 8/26. These delays may include hourly closures to install new storm sewer. Please plan your trips to account for these short-term delays.
    • Delays on Barrie Road can be up to 15 minutes. If that is too long of a delay, please refer to map for parking options.
    • Excessive vehicle speeds are prevalent in the project area, so please slow down. We encourage safety for both you AND the construction crew.
    • A map visualizing this traffic update can be found here.

    Barrie Road

    • Storm sewer installation will continue into the week of 8/26.
    • Roadway excavation is scheduled for the week of 8/26 following storm sewer installation. This work will cause traffic delays of up to 15 minutes on Barrie Road. A more detailed update will be sent out early next week prior to roadway excavation work.

    Heritage Drive

    • Streetlight installation is complete.
    • Sidewalk installation is scheduled for the week of 8/26.
    • Although the first layer of asphalt is complete, no parking remains in effect on Heritage Drive.


    W. 65th Street

    • While the street is gravel, it is open to vehicular traffic. Please drive slowly.
    • Xcel Energy’s relocation of their facilities is scheduled to begin late August or early September. Sorry for the delay.
Page last updated: 12 Jun 2025, 12:17 PM