Concord B & C Neighborhood Roadway Reconstruction

Share Concord B & C Neighborhood Roadway Reconstruction on Facebook Share Concord B & C Neighborhood Roadway Reconstruction on Twitter Share Concord B & C Neighborhood Roadway Reconstruction on Linkedin Email Concord B & C Neighborhood Roadway Reconstruction link

Concord B & C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This project, scheduled for construction in 2024, includes:

  • Complete reconstruction of the asphalt pavement,
  • Complete reconstruction of the concrete pavement with asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete replacement of the majority of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Construction of concrete sidewalks or pedestrian facilities along
    • Concord Avenue between West 64th Street and Valley View Road
    • Wooddale Avenue between Nancy Lane and Valley View Road, and
    • West 64th Street between Concord Avenue and Rose Court.
  • A preliminary assessment amount of $13,400 per Residential Equivalent Unit was approved by the Council at the December 2023 public hearing. This $13,400 per REU amount has been recorded with Hennepin County as pending assessments for all impacted properties. If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.

Concord B & C Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!

This project, scheduled for construction in 2024, includes:

  • Complete reconstruction of the asphalt pavement,
  • Complete reconstruction of the concrete pavement with asphalt pavement,
  • Full installation or replacement of concrete curb and gutter,
  • Complete replacement of the majority of the watermain and water services,
  • Improvements to the sanitary sewer and storm sewer systems, and
  • Construction of concrete sidewalks or pedestrian facilities along
    • Concord Avenue between West 64th Street and Valley View Road
    • Wooddale Avenue between Nancy Lane and Valley View Road, and
    • West 64th Street between Concord Avenue and Rose Court.
  • A preliminary assessment amount of $13,400 per Residential Equivalent Unit was approved by the Council at the December 2023 public hearing. This $13,400 per REU amount has been recorded with Hennepin County as pending assessments for all impacted properties. If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
  • Construction Update - 7/12/2024

    Share Construction Update - 7/12/2024 on Facebook Share Construction Update - 7/12/2024 on Twitter Share Construction Update - 7/12/2024 on Linkedin Email Construction Update - 7/12/2024 link

    As construction begins on your street, PLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 7/15 and are WEATHER PERMITTING.


    Traffic Update

    • Expect closures and delays near the intersection of St. Johns/ Garrison Ln. We recommend using alternate routes during the week.
    • A map visualizing this traffic update can be found here.


    W 64th St, Millers Ln, and Rose Ct

    • Concrete sidewalk installation on W 64th St. is tentatively scheduled for 7/18.
    • Excavation in preparation for topsoil is occurring sporadically.


    Concord Ave

    • Concrete curb and gutter installation is complete.
    • Concrete sidewalk installation is tentatively scheduled for 7/18.
    • The first layer of asphalt paving is complete. Please continue to park vehicles in driveways or on adjacent streets to prevent construction interruptions.
    • Asphalt driveway restoration paving is scheduled for 7/19.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Ashcroft Ln

    • Removal of the remaining concrete on the west side of the roadway.
    • Removal and replacement of poor soils in preparation for curb and gutter.
    • Water service installation is complete.
    • Temporary water has been removed.
    • Check your front door daily for notification of temporary driveway access or water loss.


    St. Johns Ave south of Garrison Ln

    • Removal of temporary water service from homes.
    • Sump line installation from W64th St to Garrison Ln.
    • Storm sewer will be installed on Monday, 7/15 and Tuesday, 7/16 at the intersection of St. Johns Ave / Garrison Ln. Please use alternate routes if traveling in this area.
    • Water service installation is complete.
    • Check your front door daily for notification of temporary driveway access or water loss.


    W. 63rd St, Garrison Ln, Nancy Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.

    • Temporary above ground water lines have been installed in preparation for the upcoming water main installation.
    • Bituminous Roadways will be reaching out to coordinate hooking up the temporary water line to homes the week of 7/15.
    • Storm sewer will be installed on Monday, 7/15 and Tuesday, 7/16 at the intersection of St. Johns Ave / Garrison Ln. Please use alternate routes if traveling in this area.
    • Check your front door daily for notification of temporary driveway access or water loss.


    W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.


    Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.



  • Construction Update- 6/28/2024

    Share Construction Update- 6/28/2024 on Facebook Share Construction Update- 6/28/2024 on Twitter Share Construction Update- 6/28/2024 on Linkedin Email Construction Update- 6/28/2024 link
    supporting image

    As construction begins on your street, PLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 7/1 and are WEATHER PERMITTING.

    Crews will not be working onsite Thursday, 7/4 or Friday, 7/5. Happy 4th of July!


    Traffic Update

    • Expect delays driving on Concord Avenue during concrete installation. We recommend using alternate routes during the week.
    • A map visualizing this traffic update can be found here.


    W 64th St, Millers Ln, and Rose Ct

    • Irrigation repairs began. If your system has not been repaired, please reach out to Brandon Freeman.
    • Excavation in preparation for topsoil installation will continue following completion of irrigation repairs.
    • Concrete sidewalk installation on W 64th St. has been tentatively rescheduled for the week of 7/1.


    Concord Ave

    • Concrete curb and gutter installation, closely followed by concrete driveway installations has been tentatively rescheduled for Monday, 7/1. This work is tentatively scheduled to be completed by Wednesday, 7/3.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Ashcroft Ln

    • Water service installation work will continue the week of 7/1.
    • Check your front door daily for notification of temporary driveway access or water loss.


    St. Johns Ave south of Garrison Ln

    • Water service installation is scheduled to begin the week of 7/8.
    • Check your front door daily for notification of temporary driveway access or water loss.


    W. 63rd St, Garrison Ln, Nancy Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.

    • Temporary above ground water lines have been installed in preparation for the upcoming water main installation.
    • Check your front door daily for notification of temporary driveway access or water loss.


    W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.


    Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.

  • Construction Update- 6/21/2024

    Share Construction Update- 6/21/2024 on Facebook Share Construction Update- 6/21/2024 on Twitter Share Construction Update- 6/21/2024 on Linkedin Email Construction Update- 6/21/2024 link

    As construction begins in your phase, PLEASE consistently check your front door daily for time sensitive notifications. All updates below are scheduled for the week of 6/24 and are WEATHER PERMITTING.


    W 64th St, Millers Ln, and Rose Ct

    • Irrigation repairs will continue. The contractor will be reaching out to coordinate with homeowners.
    • Excavation in preparation for topsoil installation will continue following completion of irrigation repairs.
    • Sidewalk installation on W 64th St. has been tentatively rescheduled for the week of 6/24.

    Concord Ave

    • Curb and gutter installation has been tentatively rescheduled for the week of 6/24.
    • Roadway excavation and gravel installation from W. 63rd to 64th St. will begin on 6/24.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Ashcroft Ln

    • Water service installation work will continue this week.
    • Check your front door daily for notification of temporary driveway access or water loss.


    St. Johns Ave south of Garrison Ln

    • Water main installation is complete.
    • Water service installation work will begin this week.
    • Check your front door daily for notification of temporary driveway access or water loss.


    W. 63rd St, Garrison Ln, Nancy Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.

    • Temporary above ground water lines have been installed in preparation for the upcoming water main installation.
    • Check your front door daily for notification of temporary driveway access or water loss.


    W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.


    Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.



  • Construction Update - 6/14/2024

    Share Construction Update - 6/14/2024 on Facebook Share Construction Update - 6/14/2024 on Twitter Share Construction Update - 6/14/2024 on Linkedin Email Construction Update - 6/14/2024 link

    As construction begins in your phase, PLEASE consistently check your front door daily for time sensitive notifications. All of the updates below are weather permitting.


    Phase 1: W 64th St, Millers Ln, and Rose Ct

    • Irrigation repairs are scheduled to begin the week of 6/17.
    • Weather permitting, excavation in preparation for topsoil installation will continue into the week of 6/17.
    • Weather permitting, sidewalk installation on W 64th St is scheduled for the week of 6/17.


    Phase 1: Concord Ave

    • Sump line installation on Concord Ave is complete.
    • Curb and gutter notifications will likely be sent out on Monday 6/17. Weather permitting, curb will begin the week of 6/17.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 2: Ashcroft Ln

    • Water main installation is complete.
    • Water service installations will continue into the week of 6/17.
    • Sump line installation will continue into the week of 6/17.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 2: St. Johns Ave south of Garrison Ln

    • Temporary water lines have now been installed.
    • Road removals for the installation of the new water main are complete.
    • Water main installation will begin the week of 6/17.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 2: W. 63rd St, Garrison Ln, Nancy Ln, St. Johns Ave south of Garrison Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.

    • Temporary above ground water lines have been installed in preparation for the upcoming water main installation.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 3: W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.


    Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.






  • Construction Update - 6/7/2024

    Share Construction Update - 6/7/2024 on Facebook Share Construction Update - 6/7/2024 on Twitter Share Construction Update - 6/7/2024 on Linkedin Email Construction Update - 6/7/2024 link

    As construction begins in your phase, PLEASE consistently check your front door daily for time sensitive notifications. All of the updates below are weather permitting.


    Phase 1: W 64th St, Millers Ln, and Rose Ct

    • Irrigation repairs are scheduled to begin the week of 6/10.
    • Excavation in preparation for topsoil installation will continue into the week of 6/10.
    • Sidewalk installation on W 64th St is scheduled for the week of 6/17.


    Phase 1: Concord Ave

    • Temporary above ground water lines have been removed from homes.
    • Sump line installation will begin the week of 6/10.
    • Roadway excavation and grading work on the west side of Concord Ave will continue the week of 6/10.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 2: Ashcroft Ln

    • Temporary above ground water main setup is complete. If you have not scheduled a time to have your home switched to temporary water, please contact Brandon Freeman 952-826-0448.
    • Sump line installation will begin the week of 6/10.
    • Installation of the new water main will begin the week of 6/10.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 2: W. 63rd St, Garrison Ln, Nancy Ln, St. Johns Ave south of Garrison Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.

    • Temporary above ground water lines have been installed in preparation for the upcoming water main installation.
    • The intersection of St Johns Ave and Garrison Ln will be closed for one day late during the week of 6/10 for water main repairs. Please be aware of road closed ahead signs and use alternative routes.


    Phase 3: W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.

    Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.

  • Construction Update - 5/31/2024

    Share Construction Update - 5/31/2024 on Facebook Share Construction Update - 5/31/2024 on Twitter Share Construction Update - 5/31/2024 on Linkedin Email Construction Update - 5/31/2024 link

    As construction begins in your phase, PLEASE consistently check your front door daily for time sensitive notifications. -


    Phase 1: W 64th St, Millers Ln, and Rose Ct

    • Asphalt driveways are scheduled to be replaced Monday, 6/3.
    • Excavation in preparation for topsoil installation will continue into the week of 6/3, weather permitting.
    • A select number of trees will be removed or trimmed during the week of 6/3 on the south side of W 64th St for the new sidewalk installation.


    Phase 1: Concord Ave

    • Water service installation is complete.
    • Crews are onsite removing temporary water from homes. If you have not been contacted, please reach out to Brandon Freeman at 952-826-0448.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Roadway excavation and grading work will continue the week of 6/3.
    • A select number of trees will be removed on Thursday, 6/6.


    Phase 2: Ashcroft Ln

    • Temporary water line installation began in preparation for the new water main installation.
    • Notifications will be sent out the week of 6/3 to get homes set up with temporary water.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 2: W. 63rd St, Garrison Ln, Nancy Ln, St. Johns Ave south of Garrison Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.

    • A select number of trees will be removed Thursday, 6/6 in concurrence with Phase 1 tree removals.


    Phase 3: W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.

    • A select number of trees will be removed Wednesday, 6/6 in concurrence with Phase 1 tree removals.


    Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.





  • Construction Update - 5/24/2024

    Share Construction Update - 5/24/2024 on Facebook Share Construction Update - 5/24/2024 on Twitter Share Construction Update - 5/24/2024 on Linkedin Email Construction Update - 5/24/2024 link

    As construction begins in your phase, PLEASE consistently check your front door daily for time sensitive notifications.


    Phase 1: W 64th St, Millers Ln, and Rose Ct

    • The first layer of asphalt paving is complete.
    • Excavation in preparation for topsoil installation will begin the week of 5/27.
    • A select number of trees will be removed or trimmed on the south side of W 64th St for the new sidewalk installation during the week of 5/27.


    Phase 1: Concord Ave

    • Completion of water service installation will occur the week of 5/27.
    • Temporary above ground water system will be removed the week of 5/27.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Roadway excavation and grading work on Concord Ave will continue the week of 5/27.
    • A select number of trees will be removed on Concord Ave on Wednesday, 5/29.


    Phase 2: Ashcroft Ln

    • Driveway removals related to temporary water system installation will continue the week of 5/27.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 2: W. 63rd St, Garrison Ln, Nancy Ln, St. Johns Ave south of Garrison Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.

    • A select number of trees will be removed Wednesday, 5/29 in concurrence with Phase 1 tree removals.


    Phase 3: W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.

    • A select number of trees will be removed Wednesday, 5/29 in concurrence with Phase 1 tree removals.


    Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.

  • Construction Update - 5/17/2024

    Share Construction Update - 5/17/2024 on Facebook Share Construction Update - 5/17/2024 on Twitter Share Construction Update - 5/17/2024 on Linkedin Email Construction Update - 5/17/2024 link

    As construction begins in your phase, PLEASE consistently check your front door daily for time sensitive notifications.


    Phase 1: W 64th St, Millers Ln, and Rose Ct

    • Curb and driveway apron installation is complete.
    • Access will be restored to driveways the week of 5/20 once the new concrete has cured.
    • The first layer of asphalt will be paved the week of 5/20 pending weather conditions.
    • A select number of trees will be removed or trimmed on the south side of W 64th St for the installation of the new sidewalk.


    Phase 1: Concord Ave

    • Watermain and hydrant installations are complete.
    • Water service installation will continue into the week of 5/20.
    • Temporary above ground water will be removed from homes as water services are completed.
    • Check your front door daily for notification of temporary driveway access or water loss.
    • Roadway work will begin at Concord/64th St the week of 5/20.


    Phase 2: Ashcroft Ln

    • Driveway removals for temporary water installation will begin the week of 5/20.
    • A select number of trees will be removed in concurrence with Phase 1 tree removals.


    Phase 2: W. 63rd St, Ashcroft Ln, Garrison Ln, Nancy Ln, St. Johns Ave south of Garrison Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.

    • A select number of trees will be removed in concurrence with Phase 1 tree removals.


    Phase 3: W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.

    • A select number of trees will be removed in concurrence with Phase 1 tree removals.


    Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


  • Construction Update - 5/10/2024

    Share Construction Update - 5/10/2024 on Facebook Share Construction Update - 5/10/2024 on Twitter Share Construction Update - 5/10/2024 on Linkedin Email Construction Update - 5/10/2024 link

    As construction begins in your phase, PLEASE consistently check your front door daily for time sensitive notifications.


    Phase 1: W 64th St, Millers Ln, and Rose Ct

    • Curb and gutter installation is scheduled for the week of 5/13 pending weather conditions.
    • Watermain work is now complete.
    • Check your front door daily for notification of temporary driveway access loss.


    Phase 1: Concord Ave

    • Removals including curb and gutter, driveways, and landscaping will continue into the week of 5/13. A select number of trees will be removed as well.
    • Temporary above ground water main setup is complete.
    • Watermain work will continue into the week of 5/13.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 2: W. 63rd St, Ashcroft Ln, Garrison Ln, Nancy Ln, St. Johns Ave south of Garrison Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.

    • A select number of trees will be removed in concurrence with Phase 1 tree removals.


    Phase 3: W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.

    • A select number of trees will be removed in concurrence with Phase 1 tree removals.


    Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.


  • Construction Update - 5/3/2024

    Share Construction Update - 5/3/2024 on Facebook Share Construction Update - 5/3/2024 on Twitter Share Construction Update - 5/3/2024 on Linkedin Email Construction Update - 5/3/2024 link

    As construction begins in your phase, PLEASE consistently check your front door daily for time sensitive notifications.


    Phase 1: Concord Ave, W 64th St, Millers Ln, and Rose Ct

    • Removals including curb and gutter, driveways, and landscaping will continue into the week of 5/6. A select number of trees will be removed as well.
    • Watermain work on Millers Ln, Rose Ct, and W. 64thSt. will be complete the week of 5/6, including removal of the temporary water system.
      • Check your front door for notification of transitioning from the temporary to permanent water service.
    • Temporary above ground water main setup is complete on Concord Avenue.
      • Bituminous Roadways delivered notifications to Concord Ave residents to set up temporary water service.
      • If your home has not been set up by 5/3, please reach out to Jake Evertz with Bituminous Roadways at (651) 600-9120 to avoid interruptions in your water service.
    • Watermain work on Concord Ave is scheduled to begin on 5/6.
    • Storm sewer work on W. 64th St will continue into the week of 5/6.
    • Check your front door daily for notification of temporary driveway access or water loss.


    Phase 2: W. 63rd St, Ashcroft Ln, Garrison Ln, Nancy Ln, St. Johns Ave south of Garrison Ln, and Wooddale Ave – Work tentatively scheduled to begin early July.

    • A select number of trees will be removed in concurrence with Phase 1 tree removals.


    Phase 3: W. 62nd St, Ashcroft Ave, St Johns Ave north of Garrison Ln, and Virginia Ln – Work tentatively scheduled to begin early August.

    • A select number of trees will be removed in concurrence with Phase 1 tree removals.


    Please set out your garbage and recycling containers before 6 AM. We have encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.

Page last updated: 18 Apr 2025, 07:48 AM