Morningside D & E Neighborhood Roadway Reconstruction
Morningside D & E Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!
This project began construction in 2022 and will continue in 2023. The work includes:
- Complete reconstruction of the asphalt pavement,
- Full replacement of concrete curb and gutter and sidewalk,
- Replacement of fire hydrants and watermain gate valves. The project will also include new water services between the main in the street and the property’s shut-off valve (curb stop),
- Improvements to the sanitary sewer and storm sewer systems, including flood risk reduction improvements, and
- Assessments to property owners for the roadway project costs, at $8,338.95 per residential equivalent unit
Morningside D & E Neighborhood Roadway Reconstruction updates will be hosted on this project page. Check back for updates!
This project began construction in 2022 and will continue in 2023. The work includes:
- Complete reconstruction of the asphalt pavement,
- Full replacement of concrete curb and gutter and sidewalk,
- Replacement of fire hydrants and watermain gate valves. The project will also include new water services between the main in the street and the property’s shut-off valve (curb stop),
- Improvements to the sanitary sewer and storm sewer systems, including flood risk reduction improvements, and
- Assessments to property owners for the roadway project costs, at $8,338.95 per residential equivalent unit
-
Construction Update 6/23/2022
Share Construction Update 6/23/2022 on Facebook Share Construction Update 6/23/2022 on Twitter Share Construction Update 6/23/2022 on Linkedin Email Construction Update 6/23/2022 linkPhase 1
- Following completion of the existing gas main removal in the roadway, Michels will install the replacement gas main, which is anticipated to conclude on 7/1.
- Upon completion of the gas main replacement on Lynn Ave, the contractor will begin excavating the streets and installing the new roadway base. This work is still anticipated to begin the week of 6/27 – beginning on Oakdale Ave and Littel St.
- Following the roadway excavation, concrete curb and gutter will be installed. This work is scheduled for late in the week of 6/27.
Phase 2
- The new watermain installation began on 6/21 and is anticipated to be complete on 6/27.
- Upon completion of the new watermain, crews will begin water service replacement work, which is scheduled to be complete during the week of 7/11. After the water services are installed, the crews will be taking homes off of the temporary water service. The contractor will need access to the home to transition water service from the temporary to the new permanent watermain.
Phase 3 – W 42nd Street
- Work on W 42nd Street is scheduled to begin the week of 7/11 with pavement reclamation, curb & gutter removals, and driveway apron removals.
- After the removals are complete, crews will begin installing a temporary above ground watermain in advance of the watermain work.
-
West 44th Street Road Closure
Share West 44th Street Road Closure on Facebook Share West 44th Street Road Closure on Twitter Share West 44th Street Road Closure on Linkedin Email West 44th Street Road Closure linkWest 44th St will be closed between Wooddale Avenue and Grimes Avenue beginning on 6/21 for watermain improvements in the Morningside D/E Street Reconstruction Project area. This closure is scheduled through the end of the day on 6/24. The detour route will be France Avenue, West 50th Street, and Brookside Avenue. If you have any questions, contact Evan Acosta.
-
Construction Update 6/15/22
Share Construction Update 6/15/22 on Facebook Share Construction Update 6/15/22 on Twitter Share Construction Update 6/15/22 on Linkedin Email Construction Update 6/15/22 linkPhase 1 - Utility Work Continues
- Michels is now scheduled to complete the gas main replacement in the roadway of Lynn Ave during the week of 6/20.
- Upon completion of the gas main replacement on Lynn Ave, the contractor will begin excavating the streets and installing the new roadway base. This work is now anticipated to begin the week of 6/27.
- Following the roadway excavation, concrete curb and gutter will be installed. This work is scheduled for late in the week of 6/27.
Phase 2 - Watermain Work to Begin
- The contractor will continue setting up temporary water service connections through 6/17.
- Kusske Construction will be reaching out to you to set up temporary water service. They will need access to the home to finalize the switch.
- Watermain work is scheduled to begin on 6/21 on Oakdale Ave south of Branson.
- The watermain work throughout the phase is scheduled to be complete the week of 6/21.
-
Construction Update 6/7/2022
Share Construction Update 6/7/2022 on Facebook Share Construction Update 6/7/2022 on Twitter Share Construction Update 6/7/2022 on Linkedin Email Construction Update 6/7/2022 linkStreet Parking During Construction
- Please remember that there is no on street parking during active construction unless you are instructed to via door notification.
Phase 1 - Utility Work Continues
- Completion of the storm sewer work is anticipated for 6/10.
- Michels, on behalf of CenterPoint Energy, will be replacing the Lynn Ave gas main in the roadway during the week of 6/13.
- Upon completion of the Lynn Ave gas main replacement, the contractor will begin roadway excavation and installing the new roadway base. This work is anticipated to begin the week of 6/20.
Phase 2 - Removals and Temporary Watermain
- The concrete curb and gutter, sidewalk, and driveway removals are ongoing and anticipated to be completed on 6/9.
- The above ground temporary watermain is being installed and tested. The contractor anticipates switching homeowners to the temporary water service later this week.
- Kusske Construction will be reaching out to homeowners to set up temporary water service. They will need access to the home to finalize the switch.
-
Construction Update 6/1/2022
Share Construction Update 6/1/2022 on Facebook Share Construction Update 6/1/2022 on Twitter Share Construction Update 6/1/2022 on Linkedin Email Construction Update 6/1/2022 linkPhase 1 - Utility Work Continues
- Water services have been completed.
- The remaining sanitary sewer and storm sewer improvements are now anticipated to continue through the week of 6/13.
Phase 2 - Removals and Temporary Watermain
- The Contractor is scheduled to remove curb, sidewalk, and driveways on 6/3 and early in the week of 6/6.
- The contractor is scheduled to begin setting up and testing the above ground temporary watermain during the week of 6/6.
- During the week of 6/6 Kusske Construction will be reaching out to residents to set up temporary water service. They will need access to the home to finalize the transition to the temporary watermain.
Material Delays and Shortages
- Due to nationwide shortages of building materials, the contractor is anticipating longer than average delivery times which may impact the duration of each construction phase.
Power Outage
City Staff were alerted to a power outage in the neighborhood around 8:45 AM, and power was restored around 10 AM. This was unrelated to the reconstruction activity and residents are encouraged to contact Xcel directly for updates if future power outages occur.
-
Construction Update 5/26/2022
Share Construction Update 5/26/2022 on Facebook Share Construction Update 5/26/2022 on Twitter Share Construction Update 5/26/2022 on Linkedin Email Construction Update 5/26/2022 linkPhase 1 Utility Work Continues
- The contractor anticipates completing the water service replacement by 6/3.
- Following the watermain work, replacement of substandard sanitary and storm sewer manholes will begin. This work is anticipated to last through 6/3.
Phase 2 to Begin Week of 5/31
- The Contractor is scheduled to remove curb, sidewalk, and driveway ends during the week of 5/31 in preparation for the temporary above ground watermain.
- The contractor is scheduled to begin setting up and testing the above ground temporary watermain at the end of the week of 5/31.
- During the week of 6/6 Kusske Construction will be reaching out to residents to set up temporary water service. They will need access to the home to finalize the transition to the temporary watermain.
Have a Safe Memorial Day!
There will be no work on site on Memorial Day, 5/30.
-
Construction Update 5/18/2022
Share Construction Update 5/18/2022 on Facebook Share Construction Update 5/18/2022 on Twitter Share Construction Update 5/18/2022 on Linkedin Email Construction Update 5/18/2022 linkPhase 1 Utility Work to Begin
- The Contractor is scheduled to complete removal of concrete driveway aprons, sidewalk, and curb and gutter on 5/18.
- Kusske Construction is scheduled to begin the watermain work on 5/19. During the water service replacements, check your front door for notifications of related to driveway access and temporary water shutoffs. The watermain work is anticipated to conclude around 6/1.
- Please set out your garbage and recycling containers by 6 AM. We have encouraged haulers to arrive between 6 and 7 AM to avoid conflicts with the contractor and their operations.
- Parking restrictions are in effect for Phase 1. There is No Parking from the hours of 7 AM to 9 PM (or until the contractor has noticeably left for the day).
-
Construction Begins!
Share Construction Begins! on Facebook Share Construction Begins! on Twitter Share Construction Begins! on Linkedin Email Construction Begins! linkProject Kickoff!
- GMH Asphalt began work on 5/9.
- The contractor is scheduled to reclaim Lynn Ave, Littel St, Oakdale Ave (both segments), and Branson St on 5/12. Reclaiming is the process of grinding the existing asphalt into an gravel base.
- Removal of curb and gutter, sidewalk, and driveway aprons will begin as necessary in preparation for the underground utility work.
- Watermain related work is scheduled to begin the week of 5/16.
- We invite you to review this document summarizing what to expect during construction.
As construction begins in your phase, we would like to continue to stress the importance of checking your front door daily for time sensitive notifications.
-
SMS Emergency Updates During Construction (Updated)
Share SMS Emergency Updates During Construction (Updated) on Facebook Share SMS Emergency Updates During Construction (Updated) on Twitter Share SMS Emergency Updates During Construction (Updated) on Linkedin Email SMS Emergency Updates During Construction (Updated) linkText MSIDE22 to 844-929-4328 to receive emergency updates for the project area (i.e. emergency water shutoff or emergency road closure).
-
CenterPoint Energy Begins Construction April 4
Share CenterPoint Energy Begins Construction April 4 on Facebook Share CenterPoint Energy Begins Construction April 4 on Twitter Share CenterPoint Energy Begins Construction April 4 on Linkedin Email CenterPoint Energy Begins Construction April 4 linkPlease see the following updates relating to CenterPoint Energy's gas main and service replacement project.
- CenterPoint Energy’s contractor, Michels Corporation, is scheduled to begin gas main installation on April 4.
- CenterPoint Energy's work is not part of the City's Morningside D & E Neighborhood Roadway Reconstruction contract.
- This work is occurring to replace old steel gas main and services prior to the City’s project.
- Work is anticipated to begin on West 42nd Street between Grimes Ave and the St Louis Park Border (just west of Oakdale Ave).
- Work will continue on the remaining streets later in the spring.
- City staff will only be onsite for this work periodically to ensure the gas main is not placed in the way of our future infrastructure.
- For additional gas main and service replacement information and updates please visit CenterPoint Energy’s project web page.
CenterPoint Energy Morningside Website
Thank you.
Email Signup
Sign Up for Emailed Project Updates
PRIVACY NOTICE: Under M.S. 13.356, your email address is private data. If you do not provide an email address you will not receive requested updates. Your email address will be available to anyone with a work assignment that reasonably require access.
Who's Listening
-
Phone 701-354-5621 Email NBonanno@sehinc.com -
Phone 952-912-2633 Email kmanzke@sehinc.com -
Phone 952-826-0443 Email aditzler@EdinaMN.gov
Key Dates
-
April 2023
-
September 2023
-
May 11 2022
-
April 19 2022
Text Notifications
During the project there may be unexpected time sensitive resident impacts. In addition to providing those notices on the project page you may opt into receiving text notifications.
To sign up text MSIDE22 to 5-7-8-3-8.
Photos
Videos
Documents
-
Construction Kickoff Update and What To Expect (107 KB) (pdf)
-
Utility Upgrade Letter (938 KB) (pdf)
-
Morningside D_E Project Area Map (181 KB) (pdf)
-
Engineering Study Morningside D & E (24.8 MB) (pdf)
-
Estimated Market Benefit - Morningside (1.54 MB) (pdf)
-
September 26, 2019 Open House Presentation (6.11 MB) (pdf)
-
Living Streets Typical Section.pdf (885 KB) (pdf)
-
Pedestrian Facilities Master Plan.pdf (497 KB) (pdf)
-
Assessment History (102 KB) (pdf)