Presidents A & B Neighborhood Roadway Reconstruction
Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!
This 2025 construction project includes:
- Complete reconstruction of the roadway asphalt pavement,
- Full installation or replacement of concrete curb and gutter,
- Complete reconstruction of two alleys west of Madison Avenue,
- Complete replacement of the watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems, and
- Proposed construction of multi-modal facilities along:
- Monroe Avenue (5' sidewalk)
- Belmore Lane (8' shared use path)
- Washington Avenue (8' shared use path)
- The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
- A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
- An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
- If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
Presidents A & B Neighborhood Roadway Reconstruction updates will be hosted on this project page. Sign up for email updates!
This 2025 construction project includes:
- Complete reconstruction of the roadway asphalt pavement,
- Full installation or replacement of concrete curb and gutter,
- Complete reconstruction of two alleys west of Madison Avenue,
- Complete replacement of the watermain and water services,
- Improvements to the sanitary sewer and storm sewer systems, and
- Proposed construction of multi-modal facilities along:
- Monroe Avenue (5' sidewalk)
- Belmore Lane (8' shared use path)
- Washington Avenue (8' shared use path)
- The project is funded by a combination of special assessments, property taxes, respective utility funds and the Pedestrian and Cyclist Safety (PACS) fund
- A preliminary assessment of $8,600 per Residential Equivalent Unit is proposed for the roadway improvements.
- An additional preliminary assessment amount of $1,300 per Residential Equivalent Unit is proposed for the gravel alley improvements for the properties bordering the alley between Washington and Adams Avenues.
- If unforeseen changes do not occur during construction, an assessment cost savings of up to 20% could occur.
-
Construction Update - 10/3/2025
Share Construction Update - 10/3/2025 on Facebook Share Construction Update - 10/3/2025 on Twitter Share Construction Update - 10/3/2025 on Linkedin Email Construction Update - 10/3/2025 linkRoad Closures
- Washington Avenue will be CLOSED until mid-October.
- The detour route is Maloney Avenue, Blake Road and Excelsior Boulevard
- The Maloney and 3rd Street intersections will be OPEN during the closure.
- Belmore Lane between Jefferson and Adams Avenues will be closed through Monday 10/6. Please use other routes until Tuesday, 10/7.
Project Area
-
See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phases 1 & 2
- Phase 2 sod installation will continue the week of 10/6.
- Sod care
- New retaining wall installation on Monroe Ave will continue into the week of 10/6.
- The final layer of asphalt paving is scheduled for late October.
Phase 3
- Crews will be onsite Saturday, 10/4 removing and replacing poor soils in preparation for curb and gutter.
- Storm sewer infiltration system Installation on Belmore Ln is complete.
- Curb and Gutter installation is scheduled to begin Tuesday, 10/7.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 3 roadways are paved.
Tyler Court
- Watermain lining on Tyler Court is complete.
- Temporary water is scheduled to be removed the week of 10/6.
- The roadway improvements have been postponed until 2026.
Harrison Avenue, Tyler Avenue, Tyler Ct, Belmore Lane east of Van Buren Avenue
The streets east of Van Buren Avenue will not begin until spring 2026. Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.
We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area.
- Washington Avenue will be CLOSED until mid-October.
-
Construction Update - 9/26/2025
Share Construction Update - 9/26/2025 on Facebook Share Construction Update - 9/26/2025 on Twitter Share Construction Update - 9/26/2025 on Linkedin Email Construction Update - 9/26/2025 linkRoad Closures
- Washington Avenue will be CLOSED until mid-October.
- The detour route is Maloney Avenue, Blake Road and Excelsior Boulevard
- The Maloney and 3rd Street intersections will be OPEN during the closure.
- Belmore Lane between Jefferson and Adams Avenues will be closed beginning the week of 9/29. Please use other routes.
Project Area
-
See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Sod care
- The final layer of asphalt paving is scheduled for late October.
Phase 2
- Concrete sidewalk installation on Monroe Ave and Belmore Ln is complete.
- Excavation in preparation for topsoil installation is scheduled to continue the week of 9/29.
- New retaining wall installation on Monroe Ave will continue into the week of 9/29.
Phase 3
- Crews will be onsite Saturday, 9/27 removing and replacing poor soils in preparation for curb and gutter. This work will continue the week of 9/29.
- Sump line installation on Adams Ave is complete.
- Watermain lining on Maloney Ave is complete.
- Installation of a storm sewer infiltration system on Belmore Ln between Jefferson Ave and Adams Ave is scheduled to begin the week of 9/29.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 3 roadways are paved.
Tyler Court
- Watermain lining on Tyler Court is complete.
- Brandon will be setting up times to reinstall water meters the week of 9/29 for homes affected by the watermain lining.
- The roadway improvements have been postponed until 2026.
Harrison and Tyler Avenues and Tyler Ct
- Washington Avenue will be CLOSED until mid-October.
-
Construction Update - 9/19/2025
Share Construction Update - 9/19/2025 on Facebook Share Construction Update - 9/19/2025 on Twitter Share Construction Update - 9/19/2025 on Linkedin Email Construction Update - 9/19/2025 linkRoad Closures
- Maloney Avenue will remain closed until Wed. 9/24.
- Washington Avenue will be CLOSED beginning Wed. 9/24 for approximately 3 weeks.
- Between Maloney Avenue and 3rd Street
- The detour route will be Maloney Avenue, Blake Road and Excelsior Boulevard
- The Maloney and 3rd Street intersections will be OPEN during the closure.
- Belmore Lane between Jefferson and Adams Avenues will be closed beginning the week of 9/22. Please use other routes.
Project Area
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Sod care
- The final layer of asphalt paving is scheduled for late October.
Phase 2
- The first layer of asphalt paving is complete.
- Concrete sidewalk installation on Monroe Ave and Belmore Ln is scheduled for the week of 9/22.
- Excavation in preparation for topsoil installation is scheduled to begin the week of 9/22.
- New retaining wall installation on Monroe Ave will continue into the week of 9/22.
Phase 3
- Water service installation on Adams Ave is complete.
- Sump line installation on Adams Ave will continue into the week of 9/22.
- Watermain lining on Maloney Ave will continue into the week of 9/22.
- Removal and replacement of poor soils in preparation for curb and gutter is scheduled to begin the week of 9/22.
- Installation of a storm sewer infiltration system on Belmore Ln between Jefferson Ave and Adams Ave is scheduled to begin the week of 9/22.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 3 roadways are paved.
Tyler Court
- Watermain lining on Tyler Court will continue into the week of 9/22.
- The roadway improvements have been postponed until 2026.
Harrison Avenue, Tyler Avenue, Tyler Ct, and Belmore Ln
-
Construction Update – 9/12/2025
Share Construction Update – 9/12/2025 on Facebook Share Construction Update – 9/12/2025 on Twitter Share Construction Update – 9/12/2025 on Linkedin Email Construction Update – 9/12/2025 linkMaloney Avenue Road Closure
- Please see the road closure update here for details.
Project Area
-
See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Landscaping replacement will continue the week of 9/15.
- Sod care
- The final layer of asphalt paving is scheduled for late October.
Phase 2
- The first layer of asphalt paving is scheduled for Monday, 9/15. Please have all vehicles off the street by 7am.
- Concrete sidewalk installation on Monroe Ave and Belmore Ln is scheduled for the week of 9/15.
Phase 3
- Water service installation on Jefferson Ave is complete.
- Sump line installation will continue into the week of 9/15.
- Watermain lining on Maloney Ave will continue into the week of 9/15.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 3 roadways are paved.
Tyler Court
- Watermain lining on Tyler Court will continue into the week of 9/15.
Harrison and Tyler Avenues
-
Fall Progress Update
Share Fall Progress Update on Facebook Share Fall Progress Update on Twitter Share Fall Progress Update on Linkedin Email Fall Progress Update linkWhile progress has been made this construction season, and all the streets west of Harrison Avenue will be complete by the original November 15, 2025, completion date, it’s highly likely the streets east of Van Buren Avenue will not begin until spring 2026.
Several factors contributed to the extended timeline, including the pace of utility work, challenging soil conditions, and weather delays. Crews remain on-site and are committed to completing the remaining work as quickly as possible.
We understand that extending construction to 2026 is an inconvenience and sincerely appreciate the patience of residents in the project area. We will continue to share updates as milestones are reached and a new 2026 completion schedule is confirmed.
-
Construction Update – 9/5/2025
Share Construction Update – 9/5/2025 on Facebook Share Construction Update – 9/5/2025 on Twitter Share Construction Update – 9/5/2025 on Linkedin Email Construction Update – 9/5/2025 linkMaloney Avenue Road Closure
- Please see the road closure update here for details.
Project Area
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Landscaping replacement will continue the week of 9/8
- Sod installation is complete.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 2 roadways are paved.
Phase 2
- Concrete curb and gutter installation is complete. “No Parking” signs have been posted on one side of the street. Residents may park vehicles in front of their homes starting Friday, 9/5 at 6pm through the weekend. Please have all vehicles moved by 7am on Monday, 9/8.
- Driveway access is expected to be restored by the end of the day Wednesday, 9/10.
- The first layer of asphalt paving is scheduled for the week of 9/15.
Phase 3
- Water service installation on Jefferson Ave will continue the week of 9/8.
- Watermain lining on Maloney Ave is scheduled to begin the week of 9/8.
Tyler Court
- Watermain lining on Tyler Court is scheduled to begin the week of 9/8.
- Temporary water is being setup on Tyler Court in preparation for watermain lining.
-
Maloney Avenue Closure 9/3-9/19
Share Maloney Avenue Closure 9/3-9/19 on Facebook Share Maloney Avenue Closure 9/3-9/19 on Twitter Share Maloney Avenue Closure 9/3-9/19 on Linkedin Email Maloney Avenue Closure 9/3-9/19 linkMaloney Avenue between Washington Avenue and Tyler Court will be closed for watermain lining improvements beginning on Tuesday September 3 through September 19. The detour route will be Blake Road, Excelsior Boulevard and Washington Avenue. Please contact Brandon Freeman at 952-826-0443 or BFreeman@edinamn.gov with any questions.
-
Construction Update - 8/29/25
Share Construction Update - 8/29/25 on Facebook Share Construction Update - 8/29/25 on Twitter Share Construction Update - 8/29/25 on Linkedin Email Construction Update - 8/29/25 linkConstruction Update – 8/29/2025
Project Area
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Landscaping replacement will continue the week of 9/2.
- Sod installation is complete.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 2 roadways are paved.
Phase 2
- Concrete curb and gutter installation are scheduled to begin on Tuesday, 9/2 (Weather dependent).
Phase 3
- Curb and driveway apron removals are complete.
- Installation of new water services on Washington Ave is complete.
- Watermain installation on Jefferson Ave is complete.
- Water service installation on Jefferson Ave is scheduled for the week of 9/2.
- Watermain lining on Maloney Ave is scheduled to begin the week of 9/8.
Phase 5
- Temporary water is being setup on Tyler Ct in preparation for watermain lining that is scheduled to begin the week of 9/8.
-
Construction Update – 8/22/2025
Share Construction Update – 8/22/2025 on Facebook Share Construction Update – 8/22/2025 on Twitter Share Construction Update – 8/22/2025 on Linkedin Email Construction Update – 8/22/2025 linkProject Area
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Landscaping replacement will continue the week of 8/25.
- Sod installation is complete.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 2 roadways are paved.
Phase 2
- Excavation of poor soils in preparation for the new roadway will continue into the week of 8/25.
- To avoid extended driveway access closures around the Labor Day holiday, curb and gutter installation is tentatively rescheduled to begin the week of 9/2 (Weather dependent).
Phase 3
- Curb and driveway apron removals are complete.
- Temporary water line installation is scheduled to continue into the week of 8/25.
- The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
- Anticipate short term water loss during this process.
- Installation of the new water main on Washington Ave is complete.
- Watermain installation on Jefferson Ave is scheduled to begin the week of 8/25
-
Construction Update – 8/15/2025
Share Construction Update – 8/15/2025 on Facebook Share Construction Update – 8/15/2025 on Twitter Share Construction Update – 8/15/2025 on Linkedin Email Construction Update – 8/15/2025 linkProject Area
- See the construction phasing map.
All Phases
- PLEASE consistently check your front door daily for time sensitive notifications of temporary driveway access or water loss.
- Vehicles cannot be parked on the street during construction.
- Please set out your garbage and recycling containers before 6 AM. We encouraged haulers to arrive early to avoid conflicts with the contractor and their operations.
Phase 1
- Excavation in preparation for topsoil installation is complete.
- Sod installation is scheduled to begin on Monday, 8/18 (Weather dependent)
- Landscaping replacement will continue the week of 8/18.
Alleys west of Madison Avenue
- Alley paving will occur at a future date when the Phase 2 roadways are paved.
Phase 2
- Crews will be onsite on Saturday, 8/16 to continue excavation of poor soils in preparation for the new roadway. This work will continue the week of 8/18.
- Sump line installation is complete.
- Curb and gutter Installation is tentatively scheduled to begin on 8/20 (Weather dependent).
Phase 3
- Curb and driveway apron removals are complete.
- Temporary water line installation is scheduled to continue into the week of 8/18.
- The watermain subcontractor, Kusske Construction, will be reaching out to residents to set up temporary water service to homes.
- Anticipate short term water loss during this process.
- Installation of the new water main is scheduled to begin the week of 8/18.
Email Signup
Sign Up for Emailed Project Updates
PRIVACY NOTICE: Under M.S. 13.356, your email address is private data. If you do not provide an email address you will not receive requested updates. Your email address will be available to anyone with a work assignment that reasonably require access.
Who's Listening
-
Phone 952-826-0448 Email BFreeman@Edinamn.gov -
Phone 952-826-0443 Email aditzler@EdinaMN.gov
Text Notifications
During the project there may be unexpected time sensitive resident impacts. In addition to providing those notices on the project page you may opt into receiving text notifications.
To sign up scan the QR code below or text PRESIDENTS-AB to 844-929-4328.
Key Dates
-
April 28 2025
-
April 01 2025
-
December 17 2024
Videos
Documents
-
Presidents A & B Project Area (145 KB) (pdf)
-
Living Streets Typical Section.pdf (885 KB) (pdf)
-
Construction Kickoff Update - Sample (84 KB) (docx)
-
Pedestrian Facilities Master Plan (1.98 MB) (pdf)
-
Bicycle Facilities Master Plan (1.96 MB) (pdf)
-
September 24 Informational Meeting Presentation Slides (10.2 MB) (pdf)
-
September 24 Informational Meeting Presentation Slides - Sidewalks_Paths (1.11 MB) (pdf)
-
Proposed Sidewalk and Path Facilities (299 KB) (pdf)
-
Proposed Street Widths, Sidewalk and Path Facilities (442 KB) (pdf)
-
Presidents A B Assessments - Roadway (145 KB) (pdf)
-
Presidents A B Assessments - Alley (150 KB) (pdf)
-
Assessment Benefit Report (6.88 MB) (pdf)
-
2025 Presidents A/B Engineering Study (12.4 MB) (pdf)
-
Presidents Public Hearing Presentation - 12/9/24 (9.45 MB) (pdf)
-
Utility Upgrade Letter Optional (824 KB) (pdf)
-
Construction Kickoff Update and What to Expect (108 KB) (pdf)
-
Construction Phasing Map - Updated (1.38 MB) (pdf)
-
Maloney Avenue Detour for CenterPoint Energy (8.54 MB) (pdf)
-
Sod Care Installation Phase 1 (68.3 KB) (docx)
-
Maloney Ave Detour (354 KB) (pdf)
-
Washington Avenue Detour (297 KB) (jpg)
-
Sanitary Sewer Lining Door Notice (120 KB) (pdf)